BLD-Final | 12/1/2017 | 12/1/2017 | 12/1/2017 | P | PASS |
Tony Young
|
|
|
Glenn-call for access Phone #: ###-####
|
DOC - Permit Finaled | 12/1/2017 | 12/1/2017 | 12/1/2017 | P | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 8/24/2017 | 8/24/2017 | 8/29/2017 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 8/25/2017 | 8/25/2017 | 8/29/2017 | | PEND |
Tony Young
|
|
|
|
BLD-Foundation | 4/11/2017 | 4/12/2017 | 4/12/2017 | A | PASS |
Tony Young
|
|
|
Wayne Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/9/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 3/8/2017 | | |
|
|
|
|
Plan assigned to (DAF) | 3/2/2017 | 3/2/2017 | 3/8/2017 | | DONE |
David Ferguson
|
|
|
(1st done) due 3/8 - Planning failed due to fence height
|
Routing - PLAN CHECK | | | 3/8/2017 | | PASS |
David Ferguson
|
|
|
Failed planning for fence height restrictions
|
Routing - Erosion and Sediment | 3/7/2017 | | 3/8/2017 | | PASS |
Andy J. Long
|
|
|
ESC general permit for pool contractor. Need to keep site BMPs in place, contain concrete washout, and clean up any trackout from adajecent lots or access.
|
Inspection Record Card- Bld | | | 3/8/2017 | | DONE |
|
|
|
|
Telephone call | | | 3/8/2017 | | DONE |
|
|
|
Spoke with Carter informing him that this permit is ready and the fee amount due for issuance
|
Case Summary (BLD) | | | 3/8/2017 | | DONE |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 3/8/2017 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/8/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/8/2017 | | DONE |
|
|
|
All MET
|
Routing PW Grading-Hillside | 3/2/2017 | | 3/7/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the pool & spa subgrade is acceptable must be approved by Public Works prior to scheduling inspections. If you have any questions call Jason Taylor ###-####.
|
Routing Walk-In (BLD) | 3/2/2017 | 3/2/2017 | 3/2/2017 | P | FAIL |
David Ferguson
|
|
|
Level II hillside boor - routed to ESC, and Hillside for approvals
|
Routing Walk-In (Zoning) | 2/10/2017 | 2/10/2017 | 2/10/2017 | P | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (BLD) | 2/10/2017 | 2/10/2017 | 2/10/2017 | P | FAIL |
Brian McGowan
|
|
|
Need stampped and signed engineering for the construction of the pool itself.
|
1st review completed | | | 2/10/2017 | | FAIL |
Brian McGowan
|
|
|
Need stampped and signed engineering for the construction of the pool itself.
|
Routing - PLAN CHECK | 2/10/2017 | | 2/10/2017 | | FAIL |
Brian McGowan
|
|
|
Need stampped and signed engineering for the construction of the pool itself.
|
Application received | | 2/10/2017 | | | |
|
|
|
|