First Notice | | 6/28/2018 | 7/11/2018 | | DONE |
|
|
|
mailed 7-12-18
|
Temporary Occupancy | 6/18/2018 | 9/16/2018 | 6/18/2018 | | DONE |
Candy A. Nichols
|
|
|
as per Jason B-temp c of o extension approved for 30 days
|
Permanent Occupancy | | | 6/18/2018 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 6/12/2018 | | DONE |
|
|
|
emailed tandrews@wbtbc.com that the temp c of o was about to expire
|
Temporary Occupancy | 4/6/2018 | 7/5/2018 | 4/6/2018 | | DONE |
Candy A. Nichols
|
|
|
Jaswon B ok'd ext of the Temp C of O
|
BLD-Aging Inspection | 3/26/2018 | 3/26/2018 | 3/26/2018 | | PASS |
Mike Jordan
|
|
|
|
PubWorks Occupancy Approval | 3/20/2018 | 3/20/2018 | 3/20/2018 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 1/5/2018 | 1/5/2018 | 1/5/2018 | P | PASS |
Mike Jordan
|
|
|
Cory Phone #: ###-####
|
Temporary Occupancy | 1/5/2018 | 4/5/2018 | 1/5/2018 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 1/5/2018 | | DONE |
|
|
|
called ACHD talked to Valerie-she transferred me to Morgen-he is the inspector for ACHD-Morgen told me that all permits on that parcel are a pass with ACHD-the GC will take the sign off card to ACHD to have signed before he picks up the perm c of o
|
BLD-Final | 1/2/2018 | 1/3/2018 | 1/3/2018 | P | FAIL |
Mike Jordan
|
|
|
Cory Phone #: ###-####. Provide special inspection report for high strength bolting, provide non shrink grout under columns, post building number and provide ADA Hardware were required.
|
FIRE-Final Inspection | 1/3/2018 | 1/4/2018 | 1/3/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Cory Phone #: ###-####
|
PubWorks Temp Occupancy Appr | 12/18/2017 | 12/18/2017 | 12/18/2017 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 12/13/2017 | 12/13/2017 | 12/13/2017 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Framing/Rough-in | 12/11/2017 | 12/12/2017 | 12/12/2017 | A | PASS |
Mike Jordan
|
|
|
FIre wall - Corey Phone #: ###-####
|
BLD-Framing/Rough-in | 12/5/2017 | 12/5/2017 | 12/5/2017 | P | PASS |
Mike Jordan
|
|
|
Cory Phone #: ###-####. Steel stud framing for 3hr. wall at bldg. #3.
|
BLD-Footing | 8/23/2017 | 8/24/2017 | 8/24/2017 | A | PART |
Mike Jordan
|
|
|
Cory Phone #: ###-####. Bldg #3 column pad footings. work in progress.
|
BLD-Conference | 8/9/2017 | 8/9/2017 | 8/9/2017 | P | CANC |
Mike Jordan
|
|
|
Angel Phone #: ###-####. wrong permit scheduled.
|
Issue PAID IN FULL permit | | | 6/5/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/5/2017 | | DONE |
|
|
|
|
Routing - FIRE | 5/10/2017 | 5/10/2017 | 5/10/2017 | | PASS |
Katie Marron
|
|
|
signed off in ePlan by Fire Katie Marron
|
Plan assigned to (JG) | 2/27/2017 | 2/27/2017 | 5/10/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 3/30 Victory Storage #3 ePlan
|
Routing PW Sewer Design | 5/10/2017 | | 5/10/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
signed off in ePlan by Sewer Design Kyle Rosenmeyer
|
Routing PW Street Lights | 5/10/2017 | | 5/10/2017 | | PASS |
Tom Marshall
|
|
|
signed off in ePlan by Street Lights Tom Marshall
|
Routing PW Drainage | 5/10/2017 | | 5/10/2017 | | PASS |
Brian Murphy
|
|
|
signed off in ePlan by Drainage Brian Murphy
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/10/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/10/2017 | | DONE |
|
|
|
Need ACHD only as of 5/17/17 C_P /// Need revised COV (for each building), GC form, and ACHD
|
Routing - Design Review | 5/9/2017 | | 5/9/2017 | | PASS |
Sarah Schafer
|
|
|
Approved per DRH16-00402
Easement agreement received 5-8-17
|
Routing - PLAN CHECK | 5/1/2017 | | 5/1/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 5/1/2017 | | 5/1/2017 | | PASS |
Javier Guzman
|
|
|
Signed off in ePlan by AHJ Engineers Chris Holladay
|
Route to Impact Fee Review | 4/4/2017 | 4/7/2017 | 4/5/2017 | | PASS |
Tonya Wallace
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 2/27/2017 | | 4/4/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLANNING | 2/27/2017 | | 4/4/2017 | | PASS |
Javier Guzman
|
|
|
Passed in ePlan by Current Planning Cody Riddle
|
Routing Off Site - STRUCTURAL | 2/27/2017 | | 4/4/2017 | | FAIL |
Javier Guzman
|
|
|
Failed in eplan by AHJ Engineers Chris Holladay
|
Routing PW Solid Waste | 2/27/2017 | | 4/4/2017 | | PASS |
Evan Carpenter
|
|
|
Passed in ePlan by Solid Waste Peter McCullough
|
Routing PW Sewer Design | 2/27/2017 | | 4/4/2017 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Failed in ePlan by Sewer Design Kyle Rosenmeyer
|
Routing PW Street Lights | 2/27/2017 | | 4/4/2017 | | FAIL |
Tom Marshall
|
|
|
Failed in ePlan by Street Lights Tom Marshall
|
Routing PW Drainage | 2/27/2017 | | 4/4/2017 | | FAIL |
Brian Murphy
|
|
|
Failed in ePlan by Drainage Brian Murphy
|
Routing - Erosion and Sediment | 2/27/2017 | | 4/4/2017 | | PASS |
Andy J. Long
|
|
|
Passed in ePlan by Erosion Melissa Jannusch
|
1st review completed | | | 4/4/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Design Review | 2/27/2017 | | 3/6/2017 | | FAIL |
Sarah Schafer
|
|
|
Cross Access agreement with parcel to the east requirement per DRH16-00402 prior to building permit sign off. Revised elevations also required for Design Review package to match.
|
Routing - FIRE | 2/27/2017 | 2/27/2017 | 3/1/2017 | | FAIL |
Katie Marron
|
|
|
|
Plan Reviewer's activity | | | 3/1/2017 | | DONE |
Javier Guzman
|
|
|
I added filles (calculations and premanufactured building plans for building 3)
|
Routing - PLANNING Land Div | 2/27/2017 | | 2/28/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 2/27/2017 | | 2/27/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/27/2017 | | 2/27/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 2/27/2017 | | PASS |
|
|
|
|
Application received | | 2/14/2017 | | | |
|
|
|
|
Application received | | 2/14/2017 | | | |
|
|
|
|