Telephone call | | | 6/30/2017 | | DONE |
|
|
|
called GM Northrup-left message-need revised final values on mechanical
|
Print Statement | | | 6/19/2017 | | DONE |
|
|
|
|
First Notice | | 6/1/2017 | 6/12/2017 | | DONE |
|
|
|
Mailed 6-13-17
|
Permanent Occupancy | | | 5/22/2017 | | DONE |
|
|
|
|
BLD-Final | 5/16/2017 | 5/19/2017 | 5/19/2017 | P | PASS |
Tony Young
|
|
|
Rick Phone #: ###-####
|
BLD-Final | 5/16/2017 | 5/17/2017 | 5/17/2017 | A | PASS |
Tony Young
|
|
|
Rick Phone #: ###-####,, ok for perm c of o
|
BLD-Final | 5/15/2017 | 5/16/2017 | 5/17/2017 | P | PASS |
Tony Young
|
|
|
Rick Phone #: ###-####
|
BLD-Final | 5/12/2017 | 5/15/2017 | 5/15/2017 | P | PEND |
Tony Young
|
|
|
Rick Phone #: ###-####
|
BLD-Final | 5/12/2017 | 5/12/2017 | 5/12/2017 | P | PART |
Tony Young
|
|
|
Rick Phone #: ###-####,, final ok pending mech pass
|
FIRE-Final Inspection | 5/12/2017 | 5/12/2017 | 5/12/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor is to remove the thumbturn dead bolt from the office door prior to the building inspection
|
FIRE-Conference | 5/10/2017 | 5/10/2017 | 5/10/2017 | P | DONE |
Jim Page
|
|
|
Fire conference complete, fire extinguisher will be mounted in discussed location.
|
BLD-Framing/Rough-in | 5/2/2017 | 5/2/2017 | 5/2/2017 | P | PART |
Mike Jordan
|
|
|
Rick Phone #: ###-####. Interior steelstud framed walls only. Pending electrical rough in inspection. Grid is existing.
|
Issue PAID IN FULL permit | | | 5/1/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/1/2017 | | DONE |
|
|
|
|
Plan assigned to (DAF) | 3/6/2017 | 3/6/2017 | 4/6/2017 | | DONE |
David Ferguson
|
|
|
due 4/5 - resubmittal (1st done) due 3/31 -need additional ADA related details.
|
Routing - PLAN CHECK | 4/6/2017 | | 4/6/2017 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/6/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/6/2017 | | DONE |
|
|
|
***met***need GC & rev cert of val
|
Route to Impact Fee Review | 3/28/2017 | 3/31/2017 | 3/29/2017 | | PASS |
Tonya Wallace
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 3/6/2017 | | 3/28/2017 | | FAIL |
David Ferguson
|
|
|
|
1st review completed | | | 3/28/2017 | | DONE |
David Ferguson
|
|
|
|
Routing - FIRE | 3/6/2017 | 3/6/2017 | 3/6/2017 | | PASS |
Katie Marron
|
|
|
No comments attached.
|
Routing - PLUMBING | 3/6/2017 | | 3/6/2017 | | PASS |
Daryl Spivey
|
|
|
Reviewed under BLD17-00160
|
Routing - MECHANICAL | 3/6/2017 | | 3/6/2017 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 3/6/2017 | | 3/6/2017 | | PASS |
Laura Hunter
|
|
|
Suite number 135
|
Routing - PUBLIC WORKS | 3/6/2017 | | 3/6/2017 | | PASS |
Rachael Beierle
|
|
|
RATED IN BLD17-00170 UNDER SWR17-00063
|
Intake Approval | | | 3/6/2017 | | PASS |
David Ferguson
|
|
|
|
Intake Approval | | | 2/17/2017 | | FAIL |
David Ferguson
|
|
|
Provide Fire Flow letter from Suez Water
|
Application received | | | 2/16/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 16 2017 2:50PM
|