Second Notice | | 1/22/2018 | 1/17/2018 | | DONE |
|
|
|
This permit finaled on the web by Brad Anderson
|
First Notice | | 1/15/2018 | 1/17/2018 | | DONE |
|
|
|
This permit finaled on the web by Brad Anderson
|
First Notice | 1/5/2018 | 1/5/2018 | 1/12/2018 | | DONE |
Brandon Shaw
|
|
|
Mailed 1-12-18
|
BLD-Final | 1/4/2018 | 1/5/2018 | 1/5/2018 | A | PASS |
Brandon Shaw
|
|
|
Mark Phone #: ###-####
|
DOC - Permit Finaled | 1/5/2018 | 1/5/2018 | 1/5/2018 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 1/5/2018 | 1/5/2018 | 1/5/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 1/5/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/5/2018 | | DONE |
|
|
|
|
BLD-Final | 12/1/2017 | 12/1/2017 | 12/1/2017 | P | PART |
Dave Hannah
|
|
|
for temp occ // Mark Phone #: ###-#### ok for temp occ
|
Temporary Occupancy | 12/1/2017 | 3/1/2018 | 12/1/2017 | | DONE |
Brittany Hill
|
|
|
|
BLD-Ceiling Grid Inspection | 11/30/2017 | 11/30/2017 | 11/30/2017 | P | PASS |
Dave Hannah
|
|
|
Mark-in basement Phone #: ###-####
|
PubWorks Temp Occupancy Appr | 11/30/2017 | 11/30/2017 | 11/30/2017 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 11/28/2017 | 11/29/2017 | 11/29/2017 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
BLD-Ceiling Grid Inspection | 11/20/2017 | 11/21/2017 | 11/21/2017 | A | PASS |
Dave Hannah
|
|
|
Mark Phone #: ###-####
|
BLD-Energy code compliance | 10/26/2017 | 10/27/2017 | 10/27/2017 | A | PASS |
Jim Storey
|
|
|
Mark Phone #: ###-#### rim at high ceilling insulated above windows ok to cover soffits
|
BLD-Energy code compliance | 10/13/2017 | 10/13/2017 | 10/13/2017 | P | PASS |
Tony Young
|
|
|
Mark Phone #: ###-####
|
BLD-Energy code compliance | 10/10/2017 | 10/11/2017 | 10/12/2017 | A | PASS |
Dave Hannah
|
|
|
Please call ahead for access - Mark Phone #: ###-####
|
BLD-Framing/Rough-in | 10/5/2017 | 10/9/2017 | 10/9/2017 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Framing/Rough-in | 9/12/2017 | 9/12/2017 | 9/12/2017 | P | PART |
Tony Young
|
|
|
Mark-Roof-framing Phone #: ###-####,, roof straps on south end to tie across trusses ok
|
BLD-Wall Bracing | 8/28/2017 | 8/29/2017 | 8/30/2017 | A | PASS |
Dave Hannah
|
|
|
Mark Phone #: ###-####
|
FIRE-Conference | 7/3/2017 | 7/5/2017 | 7/5/2017 | A | DONE |
Troy Cobbley
|
|
|
Mark and I discussed the removal of an old sprinkler system in the basement. I deferred him to a demo permit. The existing system consists of two upright heads in the mechanical room with a flow switch, alarm bell in the room and a quarter turn valve locked open. The 1" piping is fed from a 3/4" feed. I could not find any old permits for this work and there are no annual inspection tags.
|
BLD-Foundation | 6/26/2017 | 6/26/2017 | 6/26/2017 | P | PASS |
Dave Hannah
|
|
|
Rebar // Mark Phone #: ###-####
|
BLD-Foundation | 6/19/2017 | 6/20/2017 | 6/20/2017 | P | PASS |
Tony Young
|
|
|
Rebar // Catrina Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/27/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/27/2017 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 2/24/2017 | 2/24/2017 | 4/24/2017 | | PASS |
Carl D Madsen
|
|
|
1st comp Mountain West Bank
|
Routing - PLAN CHECK | 4/21/2017 | | 4/24/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 4/21/2017 | | 4/24/2017 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/24/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/24/2017 | | DONE |
|
|
|
*** met 4/27/17 CAN***Need ACHD, RP, GC Form and Revised Cert of Value
|
Routing - PLAN CHECK | 4/12/2017 | | 4/21/2017 | | PASS |
Carl D Madsen
|
|
|
Pending engineering approval
|
Routing Off Site - STRUCTURAL | 4/12/2017 | | 4/21/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 3/27/2017 | | 4/8/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 3/27/2017 | | 3/28/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Route to Impact Fee Review | 3/16/2017 | 3/19/2017 | 3/17/2017 | | PASS |
Tonya Wallace
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 3/16/2017 | | FAIL |
|
|
|
|
Routing - PLANNING | 2/24/2017 | | 3/16/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 2/24/2017 | | 3/16/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Drainage | 2/24/2017 | | 3/9/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 2/24/2017 | | 3/8/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLANNING Land Div | 2/24/2017 | | 2/28/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - FIRE | 2/24/2017 | 2/24/2017 | 2/27/2017 | | PASS |
Scott Arellano
|
|
|
Comments attached to case.
|
Routing PW Street Lights | 2/24/2017 | | 2/27/2017 | | PASS |
Tom Marshall
|
|
|
|
Routing - Design Review | 2/24/2017 | | 2/27/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - MECHANICAL | 2/24/2017 | | 2/24/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 2/24/2017 | | 2/24/2017 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC. Site backflow protection checked on Rough in.
|
Intake Approval | | | 2/24/2017 | | PASS |
|
|
|
|
Routing PW Solid Waste | 2/24/2017 | | 2/24/2017 | | PASS |
|
|
|
Project does not affect solid waste.
|
Routing - Addressing | 2/24/2017 | | 2/24/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/24/2017 | | 2/24/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 2/24/2017 | | 2/24/2017 | | PASS |
Andy J. Long
|
|
|
No review required. see ESC17-00012 for coverage at site.
|
Plan Reviewer's activity | | | 2/23/2017 | | PASS |
|
|
|
The only deficiency I could find is that a backflow preventer is not shown (or I could not find it). Not knowing how Plumbing looks at existing installations and it being the only item, I approved the plan intake review. If a backflow preventer is required, have them revise and resubmit as part of the Plumbing Plan Review.
|
Intake Approval | | | 2/22/2017 | | FAIL |
|
|
|
Please resolve each circled item on the plan intake checklist as directed.
|
Application received | | | 2/17/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 17 2017 10:55AM
|
PubWorks Occupancy Approval | 1/4/2018 | 1/4/2018 | | | |
|
|
|
|