Print Statement | | | 7/5/2017 | | DONE |
|
|
|
|
First Notice | 6/5/2017 | 6/5/2017 | 6/12/2017 | | DONE |
Candy A. Nichols
|
|
|
mailed 6-13-17
|
Permanent Occupancy | | | 6/6/2017 | | DONE |
|
|
|
|
BLD-Final | 6/5/2017 | 6/5/2017 | 6/5/2017 | P | PASS |
Brandon Shaw
|
|
|
David Phone #: ###-####
|
DOC - Permit Finaled | 6/5/2017 | 6/5/2017 | 6/5/2017 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 5/31/2017 | 5/31/2017 | 5/31/2017 | P | PASS |
Scott Arellano
|
|
|
Inspection Passed
|
FIRE-Conference | 5/24/2017 | 5/25/2017 | 5/25/2017 | A | DONE |
Jim Page
|
|
|
Fire conference complete, exit discharge lighting will be installed over south exit, one fire extinguisher will be required for space, commercial hood fire suppression system has a current inspection tag but the Class K fire extinguisher will need to be inspected and tagged with a current inspection tag.
|
Issue PAID IN FULL permit | | | 4/27/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/27/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/16/2017 | | DONE |
|
|
|
**MET** need GC & rev cert of val
|
Plan assigned to (DAF) | 2/24/2017 | 2/24/2017 | 3/15/2017 | | DONE |
David Ferguson
|
|
|
(1st done) due 3/2
|
Routing - PLAN CHECK | 3/15/2017 | | 3/15/2017 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/15/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 3/2/2017 | 3/5/2017 | 3/6/2017 | | PASS |
Tonya Wallace
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 2/24/2017 | | 3/2/2017 | | FAIL |
David Ferguson
|
|
|
|
Routing PW Environmental | 2/24/2017 | | 3/2/2017 | | PASS |
Rick Christenson
|
|
|
|
1st review completed | | | 3/2/2017 | | FAIL |
David Ferguson
|
|
|
|
Routing - FIRE | 2/24/2017 | 2/24/2017 | 2/27/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to case
|
Routing - MECHANICAL | 2/24/2017 | | 2/24/2017 | | PASS |
Troy James
|
|
|
No mechanical work with this permit. All existing.
|
Routing - Addressing | 2/24/2017 | | 2/24/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/24/2017 | | 2/24/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plan Reviewer's activity | | | 2/24/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
CDH approved drawings submitted with permit set
|
Intake Approval | | | 2/24/2017 | | PASS |
David Ferguson
|
|
|
|
Application received | | | 2/20/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 20 2017 7:16AM
|