Permanent Occupancy | | | 3/23/2017 | | DONE |
|
|
|
|
Permanent Occupancy | | | 3/23/2017 | | DONE |
|
|
|
|
BLD-Final | 3/22/2017 | 3/22/2017 | 3/22/2017 | P | PASS |
Mike Jordan
|
|
|
Russ Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 3/22/2017 | 3/22/2017 | 3/22/2017 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 3/6/2017 | 3/9/2017 | 3/9/2017 | A | FAIL |
Troy Cobbley
|
|
|
Remove the storage in the west warehouse, provide single action lever type hardware on the two exterior exit doors, mount and tag two 4a fire extinguishers as discussed.
|
BLD-Conference | 3/9/2017 | 3/9/2017 | 3/9/2017 | P | DONE |
Mike Jordan
|
|
|
Russ Phone #: ###-####. Provide lever hardware on required exits.
|
Issue PAID IN FULL permit | | | 3/2/2017 | | DONE |
|
|
|
|
Routing - FIRE | 2/28/2017 | 2/28/2017 | 2/28/2017 | | PASS |
Katie Marron
|
|
|
|
Plan assigned to (CDM) | 2/22/2017 | 2/22/2017 | 2/28/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/22/2017 | | 2/28/2017 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 2/28/2017 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 2/28/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/28/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/28/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/28/2017 | | DONE |
|
|
|
|
Telephone call | | | 2/28/2017 | | DONE |
|
|
|
called Russ to let know permit is ready
|
Plans ACCEPTED BY PLAN TECH | | | 2/22/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 2/22/2017 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/22/2017 | | DONE |
Christina Prado
|
|
|
|
First Notice | | 4/2/2017 | | | |
|
|
|
|
First Notice | | 4/2/2017 | | | |
|
|
|
|
Application received | | 2/22/2017 | | | |
|
|
|
|