First Notice | 1/22/2018 | 1/22/2018 | 2/16/2018 | | DONE |
Dave Hannah
|
|
|
This permit finaled on the web by Kim Anderson
|
BLD-Final | 1/22/2018 | 1/22/2018 | 1/22/2018 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Kaleb Checketts
|
DOC - Permit Finaled | 1/22/2018 | 1/22/2018 | 1/22/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 12/15/2017 | 12/18/2017 | 12/18/2017 | A | FAIL |
Dave Hannah
|
|
|
Requesting 11/11:30, please call for access - Ryan Phone #: ###-#### they havea pull box in 1hr rated stair tower
|
Issue PAID IN FULL permit | | | 8/25/2017 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 8/11/2017 | 8/11/2017 | 8/17/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
8/18 L2 BOI Century Link Arena ePlan
|
1st review completed | | | 8/17/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/17/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/17/2017 | | DONE |
|
|
|
need
rev cert of val- met
Met GC
|
Routing - PLAN CHECK | 8/7/2017 | | 8/17/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Plan assigned to (JG) | 8/7/2017 | 8/7/2017 | 8/11/2017 | | DEFR |
Javier Guzman
|
|
|
8/18 L2 BOI Century Link Arena ePlan
|
Routing - PLANNING | 8/7/2017 | | 8/7/2017 | | PASS |
Celine Acord
|
|
|
per CAA16-00165
|
Routing - Design Review | 8/7/2017 | | 8/7/2017 | | PASS |
Katelyn Menuge
|
|
|
DRH16-00373
|
Intake Approval | | | 8/7/2017 | | PASS |
Javier Guzman
|
|
|
|
Plan assigned to (JCB) | 8/7/2017 | | 8/7/2017 | | DEFR |
Javier Guzman
|
|
|
L2 BOI Century Link Arena ePlan
|
Intake Approval | | | 7/21/2017 | | FAIL |
Julie Romig
|
|
|
Need: 1. Completed 518 Submittal Checklist with any additional information as required.
2. Completed Form 304 Registered Design Professional for engineer.
3. Stamp and/or signature on sheet MISC and Survey sheet.
|
Intake Approval | | | 7/19/2017 | | FAIL |
Julie Romig
|
|
|
Need:
1. Completed 518 Submittal Checklist with any additional information as required.
2. Completed Form 304 Registered Design Professional for engineer.
3. Stamp and/or signature on sheet MISC and Survey sheet.
4. Rename sheets per City of Boise naming convention - Sheet number and brief description (ex T100_Title). Drawing sheets have been deleted so renamed sheets can be uploaded.
|
Application received | | | 2/23/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 23 2017 2:50PM
|