First Notice | | 1/7/2019 | 1/7/2019 | | DONE |
|
|
|
mailed 1-11-19
|
BLD-Final | 12/27/2018 | 12/28/2018 | 12/28/2018 | P | PASS |
Jim Storey
|
|
|
Please call Dutch 30 minutes prior to arrival thank you Phone #: ###-#### Inspection requested via web by Dennis Harmon final ok wrong card need c.o. per plan reviewer insp. card and lc will not achive this requirment. 301
|
Print Occupancy Form | | | 12/28/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/28/2018 | | DONE |
|
|
|
|
Meeting | | | 12/28/2018 | | DONE |
|
|
|
Spoke with Carl M and he stated that this permit should have been for occupancy and said it was ok to check CofO status (signatures) to Y
|
BLD-Final | 12/21/2018 | 12/24/2018 | 12/24/2018 | A | FAIL |
Jim Storey
|
|
|
Please call Dutch one hour prior to arrival Thank You Phone #: ###-#### Inspection requested via web by Dennis Harmon counter arch to resolve work space to not impeed with fire shudder/ need listing for 45 min door closers.
|
FIRE-Final Inspection | 12/20/2018 | 12/21/2018 | 12/21/2018 | P | PASS |
Jim Page
|
|
|
Previously noted iyems have been corrected, final life fire safety inspection for area of work complete.
Have scheduled door company for a 1:00pm drop test on coil door if any questions please call Dutch @ 208 249 6313 Thank you Phone #: ###-#### Inspection requested via web by Dennis Harmon
|
BLD-Aging Inspection | 10/5/2018 | 10/5/2018 | 10/5/2018 | | PASS |
Jim Storey
|
|
|
5/23/2018 5/24/2018 5/24/2018 A FAIL
DetailsTroy Cobbley Repair main entrance exit discharge light, Provide panic hardware on door 111A, Provide listed smoke detectors, both sides, for release of door. See NFPA 72 17.7.5.6 for door 113A, Provide installation and testing of roll down fire door per NFPA 80, Provide exit sign/emergency llight and single action hardware at door 116A, Provide revised floor plans showing revised wall layout at doors 113A and 116A, Provide emergency lighting at interior west stairs as shown on the plans, Remove dead bolts from doors 119A, 119B and 115B, Provide racking permit for storage racks exceeding 8'-0" in height, Provide list of type/quantity of hazardous chemicals such as oil storage (new & waste), parts solvents, batteries...ect.
|
CHANGE STATUS TO (ISS) | | | 8/27/2018 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 7/16/2018 | 7/16/2018 | 8/23/2018 | | PASS |
Carl D Madsen
|
|
|
Plan Mod - revise customer counter
|
Routing - PLAN CHECK | 8/23/2018 | | 8/23/2018 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/23/2018 | | DONE |
|
|
|
PLAN MOD
|
Plan Modification Accepted | | | 7/16/2018 | | DONE |
|
|
|
Plan Mod - revise customer counter
|
FIRE-Final Inspection | 5/23/2018 | 5/24/2018 | 5/24/2018 | A | FAIL |
Troy Cobbley
|
|
|
Repair main entrance exit discharge light, Provide panic hardware on door 111A, Provide listed smoke detectors, both sides, for release of door. See NFPA 72 17.7.5.6 for door 113A, Provide installation and testing of roll down fire door per NFPA 80, Provide exit sign/emergency llight and single action hardware at door 116A, Provide revised floor plans showing revised wall layout at doors 113A and 116A, Provide emergency lighting at interior west stairs as shown on the plans, Remove dead bolts from doors 119A, 119B and 115B, Provide racking permit for storage racks exceeding 8'-0" in height, Provide list of type/quantity of hazardous chemicals such as oil storage (new & waste), parts solvents, batteries...ect.
please call Dutch @###-#### 1 hr before arrival, Thank you Phone #: ###-#### Inspection requested via web by Dennis Harmon
|
BLD-Framing/Rough-in | 2/25/2018 | 2/26/2018 | 2/26/2018 | A | PASS |
Jim Storey
|
|
|
Please call Dutch 1/2 hour prior to arrival thank you Phone #: ###-#### Inspection requested via web by Dennis Harmon 2nd floor north end fire wall ch studs and core board ok fire stopping insided wall on shop side.
|
(F) Reprint permit | | | 2/23/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/23/2018 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 1/29/2018 | 1/29/2018 | 2/1/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/1/2018 | | 2/1/2018 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/1/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/1/2018 | | DONE |
|
|
|
DO NOT REISSUE PLAN MOD
|
Plan Modification Accepted | | | 1/29/2018 | | DONE |
|
|
|
|
BLD-Conference | 12/8/2017 | 12/11/2017 | 12/11/2017 | A | DONE |
Jim Storey
|
|
|
Please call Dutch 45 minutes prior to arrival thank you Phone #: ###-#### Inspection requested via web by Dennis Harmon need info floor bearing on rated wall/ radted counter tag and listing/ girt and purlins fire stopping aproval// hvac protections// no spk hourly rating on wall .
|
Issue PAID IN FULL permit | | | 12/4/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/4/2017 | | DONE |
|
|
|
|
Extend Review Timeline | | | 11/7/2017 | | DONE |
|
|
|
1st approved 180 day extension per Adele. See documents
|
Telephone call | | | 11/6/2017 | | DONE |
|
|
|
Spoke with Dennis informing him that I had spoken with Pat on 9/22 informing him that the permit took a bit longer in review and recommended to send in a request for an extension if not ready to pick up the permit. Also told Dennis I left a message for Pat on 10/17 about the same thing. Dennis stated he would send in a request
|
Telephone call | | | 10/17/2017 | | DONE |
|
|
|
Left a message for Pat informing him that this permit is 55 days past the expiration date, that it looks like the review time took a bit longer and recommended to send in a request for a 180 day extension
|
Plan assigned to (CDM) | 4/28/2017 | 4/28/2017 | 9/22/2017 | | PASS |
Carl D Madsen
|
|
|
1st review completed Peterbuilt (Dave)
|
Routing - PLAN CHECK | 9/22/2017 | | 9/22/2017 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/22/2017 | | DONE |
|
|
|
|
Telephone call | | | 9/22/2017 | | DONE |
|
|
|
Spoke with Pat informing him I know this permit is still being worked on and just wanted to recommend sending in a request for an extension
|
Permit Ready to Issue | | | 9/22/2017 | | DONE |
Christina Prado
|
|
|
Met
Need:
GC Form
Revised Certificate of Value
|
Plan assigned to (DAF) | 2/24/2017 | 2/24/2017 | 4/28/2017 | | DEFR |
David Ferguson
|
|
|
(1st done) due 3/9
|
Route to Impact Fee Review | 3/10/2017 | 3/13/2017 | 3/13/2017 | | PASS |
Tonya Wallace
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 2/24/2017 | | 3/10/2017 | | FAIL |
David Ferguson
|
|
|
|
1st review completed | | | 3/10/2017 | | DONE |
David Ferguson
|
|
|
|
Routing PW Environmental | 2/24/2017 | | 3/2/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing - FIRE | 2/24/2017 | 2/24/2017 | 3/1/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Intake Approval | | | 2/24/2017 | | PASS |
David Ferguson
|
|
|
|
Routing - Addressing | 2/24/2017 | | 2/24/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/24/2017 | | 2/24/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 2/23/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 23 2017 6:01PM
|