Second Notice | | 10/22/2017 | 10/24/2017 | | DONE |
|
|
|
This permit finaled on the web by Joseph knight
|
First Notice | | 9/28/2017 | 10/12/2017 | | DONE |
|
|
|
Mailed 10-13-17
|
BLD-Final | 9/17/2017 | 9/18/2017 | 9/18/2017 | P | PASS |
Tony Young
|
|
|
The earlier the better Phone #: ###-#### Inspection requested via web by Joseph knight
|
FIRE-Final Inspection | 9/17/2017 | 9/18/2017 | 9/18/2017 | A | PASS |
Jim Page
|
|
|
Previously noted items have been addressed, no fire sprinklers, no fire alarms, fire extinguisher is in place with a current inspection tag. Final life fire safety inspection passed/complete.
|
Permanent Occupancy | | | 9/18/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/13/2017 | 9/14/2017 | 9/14/2017 | A | FAIL |
Troy Cobbley
|
|
|
Provide small documents, repair the exit discharge light at the main exit, provide panic hardware on both exit doors, possible occupant load signs, tag on the fire extinguisher
|
Zoning Approval | 9/14/2017 | 9/14/2017 | 9/14/2017 | | PASS |
Ted Vanegas
|
|
|
|
BLD-Final | 9/13/2017 | 9/13/2017 | 9/13/2017 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Joseph knight,, conf only
|
BLD-Framing/Rough-in | 6/28/2017 | 6/28/2017 | 6/28/2017 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Joseph knight
|
Print Occupancy Form | | | 4/24/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/24/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 4/21/2017 | | |
|
|
|
|
Routing - FIRE | 4/17/2017 | 4/17/2017 | 4/21/2017 | | PASS |
Scott Arellano
|
|
|
Attached review comments to plans.
|
Plan assigned to (CJW) | 3/13/2017 | 3/13/2017 | 4/21/2017 | | PASS |
Carl Westfall
|
|
|
(2nd done) (Mar 31 - 15 days) (30 sheets) Camel's Crossing
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/21/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/21/2017 | | DONE |
|
|
|
Need GC Form and Revised Cert of Value
|
Routing - MECHANICAL | 4/17/2017 | | 4/18/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 4/17/2017 | | 4/17/2017 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines
|
Plan resubmittals received | | | 4/17/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 4/10/2017 | 4/13/2017 | 4/11/2017 | | PASS |
Tonya Wallace
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 4/10/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 4/10/2017 | | DONE |
|
|
|
|
Routing PW Environmental | 3/13/2017 | | 4/10/2017 | | PASS |
Terry Alber
|
|
|
|
Routing - PLAN CHECK | 3/13/2017 | | 4/8/2017 | | FAIL |
Carl Westfall
|
|
|
1st review completed
|
Routing - PLANNING | 3/13/2017 | | 4/7/2017 | | PASS |
Susan Riggs
|
|
|
|
Routing Off Site - C.D.H | 3/13/2017 | | 3/23/2017 | | PASS |
Carl Westfall
|
|
|
Joe Antonucci
|
Routing - FIRE | 3/13/2017 | 3/13/2017 | 3/16/2017 | | PASS |
Katie Marron
|
|
|
Waiting for IBC plan review to gather addional information on basement access.
|
Routing PW Environmental | 3/13/2017 | | 3/16/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLUMBING | 3/13/2017 | | 3/15/2017 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Addressing | 3/13/2017 | | 3/13/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/13/2017 | | 3/13/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 3/13/2017 | | 3/13/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver submitted and approved. Need to designate valid RP
|
Routing - MECHANICAL | 3/13/2017 | | 3/13/2017 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 3/13/2017 | | 3/13/2017 | | PASS |
Ted Vanegas
|
|
|
|
Plan Reviewer's activity | | | 3/13/2017 | | PASS |
|
|
|
Plan intake review completed
|
Intake Approval | | | 3/13/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Carl W approved pre screen, plan review fees paid varified
|
Intake Approval | | | 3/6/2017 | | FAIL |
|
|
|
(3-6-17) Please see the circled items in the plan intake checklist. Please resolve each item as noted. CJW
|
Intake Approval | | | 3/2/2017 | | FAIL |
|
|
|
(3-2-17) Each drawing is required to be uploaded as a separate file. Please follow the ePlanReview standards. Give each file the same name as given to that sheet in the sheet index. This needs to be done before the plan intake review can continue. A plan intake review has not been done yet. Please upload the drawings properly and complete your task. Drawings that did not comply with the ePlanReview standard were deleted. CJW
|
Application received | | | 2/24/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 24 2017 8:19AM
|