BLD-Final | 7/31/2017 | 7/31/2017 | 7/31/2017 | P | PASS |
Tony Young
|
|
|
Jeff Phone #: ###-####
|
DOC - Permit Finaled | 7/31/2017 | 7/31/2017 | 7/31/2017 | P | PASS |
Tony Young
|
|
|
|
Zoning Approval | 7/25/2017 | 7/25/2017 | 7/25/2017 | | PASS |
Ted Vanegas
|
|
|
|
BLD-Final | 7/21/2017 | 7/24/2017 | 7/24/2017 | A | CANC |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Called Jeff, Still needs zoning. Jeff noted that he still had a few things on the exterior to complete.
|
BLD-Final | 7/20/2017 | 7/21/2017 | 7/21/2017 | P | PART |
Tony Young
|
|
|
Jeff Phone #: ###-####,, walk through,, needs historical
|
BLD-Framing/Rough-in | 5/10/2017 | 5/12/2017 | 5/12/2017 | A | PART |
Tony Young
|
|
|
Jeff Phone #: ###-####,, exterior ok to cover,, interior ok after any trades
|
BLD-Framing/Rough-in | 5/10/2017 | 5/10/2017 | 5/10/2017 | P | PART |
Tony Young
|
|
|
Jeff Phone #: ###-####,, shear is work in progress,, ok to finish and cover
|
BLD-Foundation | 5/3/2017 | 5/3/2017 | 5/3/2017 | P | PART |
Tony Young
|
|
|
Jeff Phone #: ###-####
|
BLD-Footing | 5/2/2017 | 5/3/2017 | 5/3/2017 | A | PART |
Tony Young
|
|
|
Jeff Phone #: ###-####,, hole is dug
|
BLD-Energy code compliance | 4/27/2017 | 4/28/2017 | 4/28/2017 | A | PASS |
Tony Young
|
|
|
Insulation.... Call first // Jeff Phone #: ###-####
|
BLD-Energy code compliance | 4/25/2017 | 4/26/2017 | 4/26/2017 | A | PART |
Tony Young
|
|
|
Please call ahead for access - Jeff Phone #: ###-####,, seal pack ok,, ok to insulate
|
BLD-Framing/Rough-in | 4/21/2017 | 4/25/2017 | 4/25/2017 | P | PART |
Tony Young
|
|
|
Please call ahead for access - Jeff Phone #: ###-####,, verbal corrections,, ok to insulate,, point loads, truss nailing, overbuild support,, seal pack, etc
|
BLD-Wall Bracing | 4/21/2017 | 4/25/2017 | 4/25/2017 | P | PASS |
Tony Young
|
|
|
Please call ahead for access - Jeff Phone #: ###-####
|
BLD-Energy code compliance | 4/21/2017 | 4/25/2017 | 4/25/2017 | P | NR |
Tony Young
|
|
|
Please call ahead for access - Jeff Phone #: ###-####,, need to verify seal package at energy inspection
|
BLD-Footing | 3/13/2017 | 3/13/2017 | 3/13/2017 | P | PART |
Tony Young
|
|
|
Derick Phone #: ###-####,, work in progress
|
OVERRIDE | | | 3/1/2017 | | |
|
|
|
|
Telephone call | | | 3/1/2017 | | DONE |
|
|
|
called Jeff to let know permit is ready and how much is owed
|
Issue PAID IN FULL permit | | | 3/1/2017 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 2/28/2017 | | 3/1/2017 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 2/28/2017 | | 3/1/2017 | | PASS |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 3/1/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/1/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/1/2017 | | DONE |
|
|
|
need RP
|
Plan resubmittals received | | | 2/28/2017 | | DONE |
|
|
|
received resubmittals required for review
|
Routing Walk-In (Zoning) | 2/24/2017 | 2/24/2017 | 2/24/2017 | A | PASS |
Ted Vanegas
|
|
|
|
Routing Walk-In (BLD) | 2/24/2017 | 2/24/2017 | 2/24/2017 | A | FAIL |
Tisha Gallop
|
|
|
Took in as level 2; need es report for foam insulation and garage foundation detail
|
1st review completed | | | 2/24/2017 | | FAIL |
|
|
|
|
Application received | | 2/24/2017 | | | |
|
|
|
|