Permit Information
Permit NumberBLD17-00382
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 5641 E HOOTOWL DR
Project NameHN 49-1
Customer Number 
ePlanReviewYes
Description
Hillside, WUI Foothills, Zone "A" Requirements, Class "A" roof required. Permit for the construction of a new 3013 sq. ft., one story single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 376 sq. ft. of covered patio/porch and a 927 sq. ft. attached garage per the approved plans. Prescriptive Energy Code is proposed. **BJM** SP-01 zoning and setbacks per planning. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 608-7168.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/9/201710/10/201710/10/2017APASS
DetailsBrandon Shaw
Rolo Phone #: ###-####
DOC - Permit Finaled10/10/201710/10/201710/10/2017PPASS
DetailsBrandon Shaw
BLD-Final10/2/201710/2/201710/2/2017PNR
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Brad McJunkin
PubWorks Occupancy Approval9/28/20179/28/20179/28/2017 DONE
DetailsMelissa Jannusch

A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Foundation9/11/20179/12/20179/11/2017ACANC
DetailsBrandon Shaw
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
BLD-Footing9/7/20179/8/20179/7/2017APASS
DetailsBrandon Shaw
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
BLD-Final8/3/20178/3/20178/3/2017PCANC
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
BLD-Other7/13/20177/13/20177/13/2017PPASS
DetailsBrandon Shaw
Fire Soffit.- Rollo Phone #: ###-####
BLD-Energy code compliance6/27/20176/28/20176/28/2017APASS
DetailsBrandon Shaw
rollo Phone #: ###-####
BLD-Framing/Rough-in6/26/20176/26/20176/26/2017PPASS
DetailsBrandon Shaw
rollo Phone #: ###-####
BLD-Wall Bracing6/12/20176/13/20176/13/2017APASS
DetailsBrandon Shaw
rollo Phone #: ###-####
BLD-Foundation5/3/20175/3/20175/3/2017PPASS
DetailsBrandon Shaw
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
BLD-Footing5/2/20175/2/20175/2/2017PPASS
DetailsBrandon Shaw
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
PubWorks Subgrade Approval5/2/20175/2/20175/2/2017 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
Issue PAID IN FULL permit  4/26/2017 DONE
Inspection Record Card- Bld  4/26/2017 DONE
Inspection Record Card- Bld  4/26/2017 DONE
Telephone call  4/25/2017 DONE
Sent an email to Chelsea informing her that there were fees still due for issuance. Both PRK and SWR have the GC name in the list of people so that they can be seen
OVERRIDE  4/18/2017  
Plan assigned to (BJM)4/5/20174/5/20174/18/2017 DONE
DetailsBrian McGowan
BHH Priority Review - (Due 4-24)
1st review completed  4/18/2017 DONE
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  4/18/2017 DONE
DetailsBrian McGowan
Permit Ready to Issue  4/18/2017 DONE
met
Routing - PLAN CHECK4/5/2017 4/18/2017 PASS
DetailsBrian McGowan
Routing PW Grading-Hillside4/5/2017 4/13/2017 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
Route to Impact Fee Review4/5/20174/8/20174/6/2017 PASS
DetailsTonya Wallace
Initial residential review of new SFD permits requested for now.
Routing - FIRE4/5/20174/5/20174/6/2017 PASS
DetailsKatie Marron
Plans were reviewed for FD Access, hydrant availability and defensible space.
Routing - Erosion and Sediment4/5/2017 4/6/2017 PASS
DetailsAndy J. Long
ESC plan and site map provided. Valid RP & PD designated. Site preparation inspection required.
Plan assigned to (AJS)4/5/20174/5/20174/5/2017 DEFR
DetailsAdele J Schaffeld-Griffin
Plans ACCEPTED BY PLAN TECH  4/5/2017 DONE
Intake Approval  4/5/2017 PASS
Recd Pcfee & Taken To Pln CK  4/5/2017 DONE
Routing - MECHANICAL4/5/2017 4/5/2017 PASS
DetailsTroy James
Routing - PLANNING4/5/2017 4/5/2017 PASS
DetailsSue Cummings
Routing - Addressing4/5/2017 4/5/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS4/5/2017 4/5/2017 PASS
DetailsRachael Beierle
Application received  2/24/2017 DONE
Application submitted via PDS Online on Feb 24 2017 10:00AM