BLD-Final | 9/12/2017 | 9/13/2017 | 9/13/2017 | P | PASS |
Brandon Shaw
|
|
|
Call Dan Appel for access instructions Phone #: ###-#### Inspection requested via web by Daniel Appel
|
DOC - Permit Finaled | 9/13/2017 | 9/13/2017 | 9/13/2017 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 9/11/2017 | 9/11/2017 | 9/11/2017 | P | NR |
Jim Sly
|
|
|
Call Dan for access Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Wall cover | 6/20/2017 | 6/21/2017 | 6/21/2017 | P | PASS |
Jim Sly
|
|
|
Mid pm please Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Energy code compliance | 6/20/2017 | 6/21/2017 | 6/21/2017 | P | PASS |
Jim Sly
|
|
|
Mid pm please Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Framing/Rough-in | 6/16/2017 | 6/19/2017 | 6/19/2017 | A | PART |
Dave Hannah
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel ok to insulate but nr needs to show how they are going to rent roof/ceiling
|
BLD-Framing/Rough-in | 6/16/2017 | 6/16/2017 | 6/16/2017 | P | DEFR |
Jim Storey
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel out of time defered to monday am
|
Plan Modification Accepted | | | 6/6/2017 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 6/6/2017 | | 6/6/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 6/1/2017 | 6/2/2017 | 6/2/2017 | P | PASS |
Jim Sly
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Wall Bracing | 5/30/2017 | 6/1/2017 | 6/1/2017 | A | NR |
Jim Sly
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Foundation | 4/28/2017 | 5/1/2017 | 5/1/2017 | P | PASS |
Jim Sly
|
|
|
Gary Phone #: ###-####
|
BLD-Footing | 4/21/2017 | 4/24/2017 | 4/24/2017 | P | PASS |
Jim Sly
|
|
|
Jerry Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/30/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/30/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 3/21/2017 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/21/2017 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 2/27/2017 | | 3/21/2017 | | DONE |
Tisha Gallop
|
|
|
1st review 3/14; 3/10
|
Plan resubmittals received | | | 3/15/2017 | | DONE |
|
|
|
|
1st review completed | | | 3/14/2017 | | DONE |
|
|
|
2
|
Routing - PLAN CHECK | 2/27/2017 | | 3/14/2017 | | FAIL |
Tisha Gallop
|
|
|
|
Route to Impact Fee Review | 2/27/2017 | 3/2/2017 | 3/6/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of all new news permit requested for now.
|
Routing - PLANNING | 2/27/2017 | | 3/2/2017 | | PASS |
Jeff Lowe
|
|
|
|
Routing - MECHANICAL | 2/27/2017 | | 3/1/2017 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 2/27/2017 | | 2/27/2017 | | PASS |
Laura Hunter
|
|
|
Will retire 4517 W Freemont St and the new SFD will be addressed as 4519 W Freemont St
|
Routing - PUBLIC WORKS | 2/27/2017 | | 2/27/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 2/27/2017 | | FAIL |
Christina Prado
|
|
|
This lot requires planning approval for a substandard lot prior to submitting for a building permit.
|
Plans ACCEPTED BY PLAN TECH | | | 2/27/2017 | | DONE |
|
|
|
|
Intake Approval | | | 2/27/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/27/2017 | | DONE |
|
|
|
|
Application received | | | 2/26/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 26 2017 3:35PM
|