Letter of compliance/Occupancy | | | 12/18/2017 | | DONE |
|
|
|
|
Zoning Approval | 12/13/2017 | 12/13/2017 | 12/13/2017 | | DONE |
Leon Letson
|
|
|
|
BLD-Final | 10/26/2017 | 10/27/2017 | 10/30/2017 | A | PASS |
Dave Hannah
|
|
|
Michael Phone #: ###-####
|
DOC - Permit Finaled | 10/30/2017 | 10/30/2017 | 10/30/2017 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 8/8/2017 | 8/8/2017 | 8/8/2017 | P | PASS |
Jim Storey
|
|
|
Michael Phone #: ###-####
|
BLD-Framing/Rough-in | 8/4/2017 | 8/7/2017 | 8/7/2017 | A | PASS |
Brandon Shaw
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 8/3/2017 | 8/4/2017 | 8/4/2017 | P | CANC |
Dave Hannah
|
|
|
Jeff Phone #: ###-####
|
BLD-Wall cover | 5/19/2017 | 5/19/2017 | 5/23/2017 | P | PASS |
Dave Hannah
|
|
|
Shear // Michael Phone #: ###-####
|
BLD-Wall Bracing | 5/22/2017 | 5/22/2017 | 5/22/2017 | A | PASS |
Dave Hannah
|
|
|
Shear // Michael Phone #: ###-####
|
BLD-Foundation | 4/14/2017 | 4/17/2017 | 4/17/2017 | P | PASS |
Dave Hannah
|
|
|
Dane Phone #: ###-####
|
BLD-Foundation | 4/13/2017 | 4/14/2017 | 4/15/2017 | P | NR |
Tony Young
|
|
|
Dane Phone #: ###-####
|
BLD-Foundation | 4/13/2017 | 4/14/2017 | 4/14/2017 | A | CANC |
Jim Storey
|
|
|
Mike ###-####,, late am
|
BLD-Footing | 4/13/2017 | 4/13/2017 | 4/13/2017 | A | PART |
Tony Young
|
|
|
Mike ###-####,, work in progress,, ok
|
Override - Condition Holds | | | 4/13/2017 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/13/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/13/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 3/24/2017 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/24/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/24/2017 | | DONE |
|
|
|
ESC is for both permits-hold is for P & Z-they need Deed before final DO NOT issue w/o BLD17-00398
|
Plan assigned to (LEG) Tisha | 2/27/2017 | | 3/24/2017 | | DONE |
Tisha Gallop
|
|
|
1st review 3/10 (ADU); plan check and planning
|
Routing - PLANNING | 3/22/2017 | | 3/23/2017 | | PASS |
Leon Letson
|
|
|
per ePlan approved by Leon Letson
|
Routing - PLAN CHECK | 3/22/2017 | | 3/23/2017 | | PASS |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | 3/15/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/27/2017 | | 3/10/2017 | | FAIL |
Tisha Gallop
|
|
|
|
Routing - PLANNING | 2/27/2017 | | 3/10/2017 | | FAIL |
Leon Letson
|
|
|
CAA17-00007 requires deed restriction and conditions of approval to be recorded. Also, second story does not meet R-3 setbacks.
|
1st review completed | | | 3/10/2017 | | FAIL |
|
|
|
pending approval by planning and plan check
|
Route to Impact Fee Review | 2/27/2017 | 3/2/2017 | 3/6/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of all new news permit requested for now.
|
Routing - MECHANICAL | 2/27/2017 | | 3/6/2017 | | PASS |
Troy James
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/27/2017 | | DONE |
|
|
|
|
Intake Approval | | | 2/27/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/27/2017 | | DONE |
|
|
|
|
Routing - Addressing | 2/27/2017 | | 2/27/2017 | | PASS |
Laura Hunter
|
|
|
ADU Address is 1010 N 30th St
|
Routing - PUBLIC WORKS | 2/27/2017 | | 2/27/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | 2/27/2017 | | | |
|
|
|
|