First Notice | 8/18/2017 | 8/18/2017 | 9/19/2017 | | DONE |
Candy A. Nichols
|
|
|
sent in mail 9-20-17
|
BLD-Final | 8/17/2017 | 8/18/2017 | 8/18/2017 | A | PASS |
Brandon Shaw
|
|
|
Kevin Phone #: ###-####
|
DOC - Permit Finaled | 8/18/2017 | 8/18/2017 | 8/18/2017 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Framing/Rough-in | 7/20/2017 | 7/21/2017 | 7/21/2017 | A | PASS |
Jim Storey
|
|
|
Shear as well - Kevin Phone #: ###-#### framing ok
|
BLD-Foundation | 6/28/2017 | 6/29/2017 | 6/29/2017 | A | PASS |
Brandon Shaw
|
|
|
Kevin-Wall Phone #: ###-####
|
BLD-Footing | 6/26/2017 | 6/27/2017 | 6/27/2017 | A | PASS |
Jim Storey
|
|
|
Am pour Phone #: ###-#### Inspection requested via web by Jeff Bell
|
Issue PAID IN FULL permit | | | 5/25/2017 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 5/25/2017 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 5/25/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 5/22/2017 | 5/25/2017 | 5/23/2017 | | PASS |
Marissa Taylor
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 5/23/2017 | | DONE |
Christina Prado
|
|
|
***need ACHD and GC form but not the rev cert of val 5-25-17 CAN***Need ACHD, GC Form & Revised Certificate of Value for issuance
|
Plan assigned to (JAR) | 4/18/2017 | 4/18/2017 | 5/22/2017 | | DONE |
Julie Romig
|
|
|
05/22 - 502. Bonneville Pointe Mailbox Kiosk
|
1st review completed | | | 5/22/2017 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/22/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/18/2017 | | 5/22/2017 | | PASS |
Julie Romig
|
|
|
|
Routing - FIRE | 4/18/2017 | 4/18/2017 | 4/21/2017 | | PASS |
Scott Arellano
|
|
|
No plan review report attached.
|
Routing - PLANNING Land Div | 4/18/2017 | | 4/20/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Erosion and Sediment | 4/18/2017 | | 4/19/2017 | | PASS |
Andy J. Long
|
|
|
No ESC permit required. See ESC16-00439 for coverage at Bonneville Point sub.
|
Plan assigned to (JG) | 4/18/2017 | 4/18/2017 | 4/18/2017 | | DEFR |
Javier Guzman
|
|
|
|
Routing - Addressing | 4/18/2017 | | 4/18/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/18/2017 | | 4/18/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Drainage | 4/18/2017 | | 4/18/2017 | | PASS |
Brian Murphy
|
|
|
SUBDIVISION INSIGNIFICANT TO TOTAL, TALKED TO JT
|
Routing - PLANNING | 4/18/2017 | | 4/18/2017 | | PASS |
Cody Riddle
|
|
|
|
Intake Approval | | | 4/18/2017 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 4/17/2017 | | |
|
|
|
Tied to permit ESC14-00206 for erosion per Andy Long.
|
Plan Reviewer's activity | | | 4/17/2017 | | |
|
|
|
Route to Planning for review.
|
Intake Approval | | | 3/24/2017 | | FAIL |
Julie Romig
|
|
|
Provide the following:
Soils and geotech report
Verification of Legal Lot or Parcel Form
Site specific Fire Flow at Hydrants Letter
Site Drainage Report/Plans
Erosion & Sediment Control Narrative/Plan
Show location of fire hydrants (new and existing)
Erosion & Sediment Control Narrative/Plan
Show location of fire hydrants (new and existing)
|
Intake Approval | | | 3/15/2017 | | FAIL |
|
|
|
1. Please re-upload the plan sheets as individual documents as required per the E-plan submittal requirements.
2. Please upload a completed form 502 submittal checklist with all required items.
|
Application received | | | 3/1/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 1 2017 3:37PM
|