Print Statement | | | 3/26/2018 | | DONE |
|
|
|
|
First Notice | | 3/3/2018 | 3/13/2018 | | DONE |
|
|
|
mailed 3-14-18
|
BLD-Final | 2/20/2018 | 2/21/2018 | 2/21/2018 | A | PASS |
Jim Sly
|
|
|
Keith Phone #: ###-####
|
PubWorks Occupancy Approval | 2/21/2018 | 2/21/2018 | 2/21/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 2/21/2018 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/14/2018 | 2/20/2018 | 2/20/2018 | A | PASS |
Jim Page
|
|
|
Life fire safety inspection complete.
|
BLD-Aging Inspection | 2/7/2018 | 2/7/2018 | 2/7/2018 | | PART |
Jim Storey
|
|
|
|
Zoning Approval | 12/12/2017 | 12/12/2017 | 12/12/2017 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Final | 12/8/2017 | 12/8/2017 | 12/8/2017 | P | PART |
Jim Storey
|
|
|
temp ok
|
Temporary Occupancy | 12/8/2017 | 3/8/2018 | 12/8/2017 | | DONE |
Candy A. Nichols
|
|
|
|
FIRE-Final Inspection | 12/5/2017 | 12/6/2017 | 12/6/2017 | A | PASS |
Jim Page
|
|
|
Life fire safety inspection for this permit passed/complete.
|
Zoning Approval Temp | 11/21/2017 | 11/21/2017 | 11/21/2017 | | DONE |
Andrea Tuning
|
|
|
Bond has been placed for fencing and striping. The site still needs 2 more street trees on Federal Way, 6 new street trees along I-84, a tree in the terminal planter and additional vegetation around the swale adjacent to Federal Way.
|
BLD-Footing | 8/15/2017 | 8/16/2017 | 8/16/2017 | A | PASS |
Jim Storey
|
|
|
building n- Chris Phone #: ###-#### si on site
|
Permit Ready to Issue | | | 7/28/2017 | | DONE |
|
|
|
all met
|
Issue PAID IN FULL permit | | | 7/28/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/28/2017 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 7/18/2017 | | 7/18/2017 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/17/2017 | | 7/18/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - Erosion and Sediment | 3/16/2017 | | 7/18/2017 | | PASS |
Andy J. Long
|
|
|
|
Routing PW Environmental | 3/16/2017 | | 7/18/2017 | | PASS |
Rick Christenson
|
|
|
|
Plan assigned to (CDM) | 3/16/2017 | 3/16/2017 | 7/17/2017 | | PASS |
Carl D Madsen
|
|
|
1st comp SE Boise Boat & RV Storage
|
Routing PW Drainage | 3/16/2017 | | 7/17/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 3/16/2017 | | 7/17/2017 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 3/16/2017 | | 7/17/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Solid Waste | 3/16/2017 | | 7/17/2017 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Design Review | 7/17/2017 | | 7/17/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - Design Review | 6/2/2017 | | 6/2/2017 | | FAIL |
Andrea Tuning
|
|
|
This project has not receieved DR approval.
|
Routing - FIRE | 7/18/2017 | 7/18/2017 | 5/25/2017 | | PASS |
Scott Arellano
|
|
|
|
Routing Off Site - STRUCTURAL | 3/16/2017 | | 4/27/2017 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 4/27/2017 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 3/16/2017 | | 4/27/2017 | | FAIL |
Carl D Madsen
|
|
|
SE Boise Boat & RV Storage
|
Plan assigned to (DAF) | 3/16/2017 | 3/16/2017 | 3/21/2017 | | DEFR |
David Ferguson
|
|
|
SE Boise Boat & RV Storage
|
Routing - Addressing | 3/16/2017 | | 3/21/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - FIRE | 3/16/2017 | 3/16/2017 | 3/20/2017 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
Routing - PUBLIC WORKS | 3/16/2017 | | 3/16/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 3/16/2017 | | 3/16/2017 | | PASS |
Cody Riddle
|
|
|
|
Routing - PLANNING Land Div | 3/16/2017 | | 3/16/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Design Review | 3/16/2017 | | 3/16/2017 | | FAIL |
Sarah Schafer
|
|
|
An administrative level design review modification is needed to DRH16-00446. Changes to the building lengths, locations, design of the office building, and sidewalk location. Corinne was notified 3/16/17.
|
Intake Approval | | | 3/16/2017 | | PASS |
|
|
|
|
Application received | | 3/3/2017 | | | |
|
|
|
|