BLD-Final | 8/17/2017 | 8/18/2017 | 8/18/2017 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Pieroni
|
DOC - Permit Finaled | 8/18/2017 | 8/18/2017 | 8/18/2017 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 8/17/2017 | 8/17/2017 | 8/17/2017 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Pieroni,, all good ,, just need brow roof areas finished
|
BLD-Final | 8/16/2017 | 8/17/2017 | 8/17/2017 | A | PEND |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Pieroni
|
BLD-Final | 8/15/2017 | 8/16/2017 | 8/16/2017 | P | PART |
Tony Young
|
|
|
HVAC us scheduled for a am inspection, expecting that to pass. Tony if possible see you in the afternoon for your final. Home loan closes Friday, in case there is an issue i have a day to correct, thanks Phone #: ###-#### Inspection requested via web by Marty Pieroni// needs to finish roof,, fire caulking,, attic access cover
|
BLD-Energy code compliance | 6/13/2017 | 6/14/2017 | 6/14/2017 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Pieroni
|
BLD-Framing/Rough-in | 6/8/2017 | 6/9/2017 | 6/9/2017 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Pieroni
|
BLD-Wall Bracing | 5/15/2017 | 5/16/2017 | 5/16/2017 | A | PASS |
Brandon Shaw
|
|
|
Inspection requested via web by Marty Pieroni
|
BLD-Footing | 4/17/2017 | 4/18/2017 | 4/18/2017 | A | PASS |
Brandon Shaw
|
|
|
Matt Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/14/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/14/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 4/7/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 3/8/2017 | 3/8/2017 | 4/7/2017 | | DONE |
Brian McGowan
|
|
|
(see bld17-203)
|
1st review completed | | | 4/7/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/7/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 4/7/2017 | | DONE |
|
|
|
All Met
|
Routing - PLAN CHECK | 3/6/2017 | | 4/7/2017 | | PASS |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 3/6/2017 | | 3/9/2017 | | PASS |
Troy James
|
|
|
|
Plan assigned to (LEG) Tisha | 3/6/2017 | | 3/8/2017 | | DEFR |
Tisha Gallop
|
|
|
|
Route to Impact Fee Review | 3/6/2017 | 3/9/2017 | 3/7/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of all new news permit requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 3/6/2017 | | DONE |
|
|
|
|
Intake Approval | | | 3/6/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/6/2017 | | DONE |
|
|
|
|
Routing - PLANNING | 3/6/2017 | | 3/6/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 3/6/2017 | | 3/6/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/6/2017 | | 3/6/2017 | | PASS |
Rachael Beierle
|
|
|
|
Telephone call | | | 3/6/2017 | | DONE |
|
|
|
emailed customer that we need the designer to move his general notes to a different spot so we have a clear area for the stamped approved
|
Application received | | | 3/3/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 3 2017 2:36PM
|