BLD-Final | 8/8/2017 | 8/8/2017 | 8/8/2017 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
DOC - Permit Finaled | 8/8/2017 | 8/8/2017 | 8/8/2017 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 8/4/2017 | 8/4/2017 | 8/4/2017 | P | FAIL |
Brandon Shaw
|
|
|
No Mech final
|
BLD-Energy code compliance | 5/30/2017 | 5/30/2017 | 5/30/2017 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Framing/Rough-in | 5/25/2017 | 5/25/2017 | 5/25/2017 | P | PEND |
Dave Hannah
|
|
|
ok to insulate after plumbing rough in is oked
|
BLD-Conference | 5/25/2017 | 5/25/2017 | 5/25/2017 | P | CANC |
Dave Hannah
|
|
|
|
BLD-Wall Bracing | 5/14/2017 | 5/15/2017 | 5/15/2017 | A | PASS |
Jim Storey
|
|
|
Inspection requested via web by Ryan Lierman
|
BLD-Other | 5/1/2017 | 5/2/2017 | 5/2/2017 | P | PASS |
Jim Storey
|
|
|
firewall insp// Jason Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/28/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/28/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 3/24/2017 | | |
|
|
|
|
Permit Ready to Issue | | | 3/24/2017 | | DONE |
|
|
|
all requirements met
|
1st review completed | | | 3/23/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Plan assigned to (LEG) Tisha | 3/6/2017 | | 3/23/2017 | | DONE |
Tisha Gallop
|
|
|
3/23 L2 duplex
|
Routing - PLAN CHECK | 3/6/2017 | | 3/23/2017 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/23/2017 | | DONE |
|
|
|
|
Routing - MECHANICAL | 3/6/2017 | | 3/10/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 3/6/2017 | 3/9/2017 | 3/7/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of all new news permit requested for now.
|
Routing - PLANNING | 3/6/2017 | | 3/6/2017 | | PASS |
Nicolette Womack
|
|
|
Eaves shall not encroach more than 2' into any setback.
|
Routing - Addressing | 3/6/2017 | | 3/6/2017 | | PASS |
Laura Hunter
|
|
|
North duplex is 1212 S Lincoln Ave south duplex is 1214 S Lincoln Ave
|
Routing - PUBLIC WORKS | 3/6/2017 | | 3/6/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/6/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 3/6/2017 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/6/2017 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 3/3/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 3 2017 5:01PM
|