Permit Information
Permit NumberBLD17-00503
StatusFinaled
Name TRILOGY DEVELOPMENT INC
Site Address 9840 W OVERLAND RD Unit: STE 120
Project Name208 Real Estate - SUITE #120
Customer Number 
ePlanReviewYes
Description
**(208 REAL ESTATE – SUITE #120)** (Note: Do not final until BLD15-01393 is finaled) Permit for first time build out of a 1,890 sq. ft. space, this new space is for the expansion of the existing 3,455 sq. ft. business tenant under BLD16-03518, to create a total of 5,345 sq. ft. business space. Core and shell built under BLD15-01393. Approval is contingent on adhering to the approved plans and attached documents. Work to include: construction of interior non-bearing walls to create (8) offices, (1) conference room, a lobby area and an accessible restroom to the disabled, new door/door frames, interior concrete slab work, suspended acoustic ceiling, select gypsum ceiling, new light fixtures, electrical work, plumbing work, mechanical work and interior finishes to be in compliance with Ch. 8 of the 2012 IBC. This building is not fire sprinklered. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 7/15/20178/7/2017 DONE
This permit finaled on the web by Mike McHargue
Permanent Occupancy  7/5/2017 DONE
BLD-Final6/21/20176/22/20176/22/2017APASS
DetailsMike Jordan
Final TI Inspection. Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue. ok for perm occ.
FIRE-Final Inspection6/15/20176/15/20176/15/2017PPASS
DetailsTroy Cobbley
Fire Life Safety Passed
BLD-Ceiling Grid Inspection6/9/20176/9/20176/9/2017PPASS
DetailsBrandon Shaw
Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD-Wall cover4/26/20174/26/20174/26/2017PPASS
DetailsMike Jordan
Contact: Hunter Gomez.. Late PM; pending passing Mech. Pressure Test Inspection Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD-Energy code compliance4/25/20174/26/20174/26/2017ANR
DetailsMike Jordan
Mid-Late Morning. Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue. Needs to resolve mech. isssues.
BLD-Wall cover4/25/20174/26/20174/26/2017ACANC
DetailsMike Jordan
Mid-Late Morning. Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD-Framing/Rough-in4/24/20174/25/20174/25/2017PPASS
DetailsMike Jordan
Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue. INterior wood framed wood walls and platform ok.
Issue PAID IN FULL permit  3/31/2017 DONE
Print Occupancy Form  3/31/2017 DONE
Plan assigned to (JG)3/10/20173/10/20173/29/2017 PASS
DetailsJavier Guzman
3/28 L3 208 Real Estate Expansion
Routing - PLAN CHECK3/10/2017 3/29/2017 PASS
DetailsJavier Guzman
1st review completed  3/29/2017 DONE
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  3/29/2017 DONE
Permit Ready to Issue  3/29/2017 DONE
Needs; GC Form & Revised Cert of Value
Routing - FIRE3/10/20173/10/20173/13/2017 PASS
DetailsKatie Marron
No comments required. Basic Life Safety.
Routing - Addressing3/10/2017 3/13/2017 PASS
DetailsLaura Hunter
Routing - MECHANICAL3/10/2017 3/13/2017 PASS
DetailsTroy James
Routing - PLUMBING3/10/2017 3/10/2017 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - PUBLIC WORKS3/10/2017 3/10/2017 PASS
DetailsMorgan Webb
Intake Approval  3/8/2017 PASS
DetailsDavid Ferguson
1) Naming convention of sheets not followed. Upload each plan sheet using the names as they appear on the sheet index.
(Example: A-1.1 Floor Plan, M0.0 Mechanical Schedules and Calcs, etc.) The page number only is not sufficient, we also need the description of what is on the page).
Intake Approval  3/8/2017 PASS
DetailsAdele J Schaffeld-Griffin
pre screen passed by Dave, plan review fees paid
Intake Approval  3/7/2017 FAIL
DetailsDavid Ferguson
#304 form not complete
Naming convention of sheets not followed
No sheet A4.1
Two sheets A6.1
Application received  3/6/2017 DONE
Application submitted via PDS Online on Mar 6 2017 2:46PM