First Notice | | 7/15/2017 | 8/7/2017 | | DONE |
|
|
|
This permit finaled on the web by Mike McHargue
|
Permanent Occupancy | | | 7/5/2017 | | DONE |
|
|
|
|
BLD-Final | 6/21/2017 | 6/22/2017 | 6/22/2017 | A | PASS |
Mike Jordan
|
|
|
Final TI Inspection. Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue. ok for perm occ.
|
FIRE-Final Inspection | 6/15/2017 | 6/15/2017 | 6/15/2017 | P | PASS |
Troy Cobbley
|
|
|
Fire Life Safety Passed
|
BLD-Ceiling Grid Inspection | 6/9/2017 | 6/9/2017 | 6/9/2017 | P | PASS |
Brandon Shaw
|
|
|
Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD-Wall cover | 4/26/2017 | 4/26/2017 | 4/26/2017 | P | PASS |
Mike Jordan
|
|
|
Contact: Hunter Gomez.. Late PM; pending passing Mech. Pressure Test Inspection Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD-Energy code compliance | 4/25/2017 | 4/26/2017 | 4/26/2017 | A | NR |
Mike Jordan
|
|
|
Mid-Late Morning. Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue. Needs to resolve mech. isssues.
|
BLD-Wall cover | 4/25/2017 | 4/26/2017 | 4/26/2017 | A | CANC |
Mike Jordan
|
|
|
Mid-Late Morning. Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD-Framing/Rough-in | 4/24/2017 | 4/25/2017 | 4/25/2017 | P | PASS |
Mike Jordan
|
|
|
Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue. INterior wood framed wood walls and platform ok.
|
Issue PAID IN FULL permit | | | 3/31/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/31/2017 | | DONE |
|
|
|
|
Plan assigned to (JG) | 3/10/2017 | 3/10/2017 | 3/29/2017 | | PASS |
Javier Guzman
|
|
|
3/28 L3 208 Real Estate Expansion
|
Routing - PLAN CHECK | 3/10/2017 | | 3/29/2017 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 3/29/2017 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/29/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/29/2017 | | DONE |
|
|
|
Needs; GC Form & Revised Cert of Value
|
Routing - FIRE | 3/10/2017 | 3/10/2017 | 3/13/2017 | | PASS |
Katie Marron
|
|
|
No comments required. Basic Life Safety.
|
Routing - Addressing | 3/10/2017 | | 3/13/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - MECHANICAL | 3/10/2017 | | 3/13/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 3/10/2017 | | 3/10/2017 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PUBLIC WORKS | 3/10/2017 | | 3/10/2017 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 3/8/2017 | | PASS |
David Ferguson
|
|
|
1) Naming convention of sheets not followed. Upload each plan sheet using the names as they appear on the sheet index.
(Example: A-1.1 Floor Plan, M0.0 Mechanical Schedules and Calcs, etc.) The page number only is not sufficient, we also need the description of what is on the page).
|
Intake Approval | | | 3/8/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
pre screen passed by Dave, plan review fees paid
|
Intake Approval | | | 3/7/2017 | | FAIL |
David Ferguson
|
|
|
#304 form not complete
Naming convention of sheets not followed
No sheet A4.1
Two sheets A6.1
|
Application received | | | 3/6/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 6 2017 2:46PM
|