First Notice | | 4/21/2017 | 5/10/2017 | | DONE |
|
|
|
Mailed 5-11
|
BLD-Final | 4/10/2017 | 4/11/2017 | 4/11/2017 | P | PASS |
Jim Sly
|
|
|
Jason Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 4/10/2017 | 4/11/2017 | 4/11/2017 | A | PASS |
Troy Cobbley
|
|
|
Lifes safety passed. Owner to remove the non-functional/non-required emergency lights prior to a building inspection.
|
Permanent Occupancy | | | 4/11/2017 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 4/4/2017 | 4/4/2017 | 4/4/2017 | P | PASS |
Jim Sly
|
|
|
jim Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/22/2017 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 3/6/2017 | 3/6/2017 | 3/21/2017 | | PASS |
Carl Westfall
|
|
|
(1st done) (Mar 14 - 7 days) Pino's Restaurant
|
Routing - PUBLIC WORKS | 3/20/2017 | | 3/21/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Sewer Rating | 3/21/2017 | | 3/21/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLAN CHECK | 3/21/2017 | | 3/21/2017 | | DONE |
Carl Westfall
|
|
|
Routed back from Public Works
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/21/2017 | | DONE |
Christina Prado
|
|
|
All met 3/22/17 C_P /// Need GC Form and Revised Cert of Value
|
Print Occupancy Form | | | 3/21/2017 | | DONE |
|
|
|
|
Telephone call | | | 3/21/2017 | | DONE |
Christina Prado
|
|
|
Called Jaysen to advise permit is ready for pick up pending GC form & revised valuation from proposed GC
|
Route to Impact Fee Review | 3/20/2017 | 3/23/2017 | 3/20/2017 | | PASS |
Tonya Wallace
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 3/18/2017 | | 3/20/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to plans.
|
1st review completed | | | 3/20/2017 | | FAIL |
|
|
|
Failed PW
|
Routing - PLAN CHECK | 3/20/2017 | | 3/20/2017 | | DONE |
Carl Westfall
|
|
|
Waiting for resubmittal. Talked to MW about her review. She will contact the applicant and explain what is required. Meanwhile, the drawings are at CJW's desk.
Routed back to Public Works.
|
Routing - PLAN CHECK | 3/16/2017 | | 3/18/2017 | | PASS |
Carl Westfall
|
|
|
Changed to a Level III because of all the places it routed to.
|
Routing - MECHANICAL | 3/14/2017 | | 3/16/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 3/10/2017 | | 3/14/2017 | | PASS |
Daryl Spivey
|
|
|
all kitchen waste to grease line.
|
Routing - PUBLIC WORKS | | | 3/10/2017 | | FAIL |
|
|
|
SEE SEWER RATING
|
Routing PW Sewer Rating | 3/8/2017 | | 3/10/2017 | | FAIL |
Morgan Webb
|
|
|
PLANS MUST INCLUDE FLOOR PLAN TO SCALE FOR MEASUREMENTS AND ALSO NEED A MENU.
|
Routing PW Environmental | 3/8/2017 | | 3/9/2017 | | PASS |
Rick Christenson
|
|
|
Exsiting Grease line shared GI
|
Routing - Addressing | 3/6/2017 | | 3/7/2017 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/6/2017 | | DONE |
|
|
|
|
Intake Approval | | | 3/6/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/6/2017 | | DONE |
|
|
|
|
Application received | | 3/6/2017 | | | |
|
|
|
|