Permit Information
Permit NumberBLD17-00510
StatusFinaled
Name CANYON CREST HOMES
Site Address 3986 N GOSHAWK PL
Project NameSoppe Residence
Customer Number 
ePlanReviewYes
Description
WUI Zone A - Class "A" roof required ** Permit for the construction of a new 2,788 sq. ft., two story (first story 2,018 sq. ft., second story 770 sq. ft.) single family dwelling with 4 bedrooms, 3 bathrooms, approximately 138 sq. ft. of covered patio/porch and a 952 sq. ft. attached garage per the approved plans, and any notations. A-1 zoning and setbacks per planning. **DAF** A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 608-7168.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/8/20179/11/20179/11/2017APASS
DetailsTony Young
Larry Phone #: ###-####
DOC - Permit Finaled9/11/20179/11/20179/11/2017PPASS
DetailsTony Young
c of o issued
PubWorks Occupancy Approval9/7/20179/7/20179/7/2017 DONE
DetailsMelissa Jannusch
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Conference8/28/20178/28/20178/28/2017PPART
DetailsTony Young
Larry Phone #: ###-####,, stair ?s,, nosings, treads
BLD-Other6/21/20176/21/20176/21/2017PPASS
DetailsTony Young
Fire seal // Tobey Phone #: ###-####,, soffit ok
BLD-Energy code compliance6/21/20176/21/20176/21/2017PPASS
DetailsTony Young
Larry Phone #: ###-####
BLD-Framing/Rough-in6/15/20176/16/20176/16/2017APASS
DetailsTony Young
Larry Phone #: ###-####
BLD-Conference6/2/20176/2/20176/2/2017ADONE
DetailsJim Sly
Have questions on the wood burning fireplace chase height. Phone #: ###-#### Inspection requested via web by David Wipper
BLD-Wall Bracing5/26/20175/30/20175/30/2017APART
DetailsTony Young
Phone #: ###-#### Inspection requested via web by David Wipper,, ext ok
BLD-Foundation4/14/20174/17/20174/17/2017APASS
DetailsBrandon Shaw
Chris Phone #: ###-####
Foundation walls already poured at time of inspection.
BLD-Foundation4/13/20174/14/20174/14/2017ANR
DetailsTony Young
Chris Phone #: ###-####,, too much snow/rain
BLD-Footing4/12/20174/12/20174/12/2017PPART
DetailsTony Young
Chris Phone #: ###-####,, work in progress
PubWorks Subgrade Approval4/11/20174/11/20174/11/2017 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####
OVERRIDE  3/31/2017  
Plan assigned to (DAF)3/15/20173/15/20173/31/2017 DONE
DetailsDavid Ferguson
(1st done) due 3/29 - Need addl. WUI details
Routing - PLAN CHECK3/31/2017 3/31/2017 PASS
DetailsDavid Ferguson
PLANS/APPL TAKEN TO FRONT DESK  3/31/2017 DONE
Permit Ready to Issue  3/31/2017 DONE
all requirements met
Issue PAID IN FULL permit  3/31/2017 DONE
Inspection Record Card- Bld  3/31/2017 DONE
1st review completed  3/28/2017 DONE
DetailsDavid Ferguson
Routing - PLAN CHECK3/10/2017 3/28/2017 FAIL
DetailsDavid Ferguson
Plan assigned to (LEG) Tisha3/10/2017 3/15/2017 DEFR
DetailsTisha Gallop
Routing PW Grading-Hillside3/10/2017 3/14/2017 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
Route to Impact Fee Review3/10/20173/13/20173/13/2017 PASS
DetailsTonya Wallace
Initial residential review of all new news permit requested for now.
Routing - Erosion and Sediment3/10/2017 3/13/2017 PASS
DetailsAndy J. Long
ESC plan approved. Valid RP and PD designated. ESC site preparation inspection REQUIRED.
Routing - FIRE3/10/20173/10/20173/10/2017 PASS
DetailsKatie Marron
Plans were reviewed for FD Access, hydrant availability and defensible space.
Routing - MECHANICAL3/10/2017 3/10/2017 PASS
DetailsTroy James
Routing - PLANNING3/10/2017 3/10/2017 PASS
DetailsSue Cummings
Routing - Addressing3/10/2017 3/10/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS3/10/2017 3/10/2017 PASS
DetailsRachael Beierle
Plans ACCEPTED BY PLAN TECH  3/10/2017 DONE
Intake Approval  3/10/2017 PASS
Recd Pcfee & Taken To Pln CK  3/10/2017 DONE
Intake Approval  3/9/2017 FAIL
***met*** Need ESC Narrative, ResCheck and wall section/r-value
Telephone call  3/9/2017 DONE
called Dave-i need him to show me where some of the items are that failed in the 1st pre screen. I amy just be missing them-left him a message to callo me back
Application received  3/6/2017 DONE
Application submitted via PDS Online on Mar 6 2017 4:25PM