BLD-Final | 9/8/2017 | 9/11/2017 | 9/11/2017 | A | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####
|
DOC - Permit Finaled | 9/11/2017 | 9/11/2017 | 9/11/2017 | P | PASS |
Tony Young
|
|
|
c of o issued
|
PubWorks Occupancy Approval | 9/7/2017 | 9/7/2017 | 9/7/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Conference | 8/28/2017 | 8/28/2017 | 8/28/2017 | P | PART |
Tony Young
|
|
|
Larry Phone #: ###-####,, stair ?s,, nosings, treads
|
BLD-Other | 6/21/2017 | 6/21/2017 | 6/21/2017 | P | PASS |
Tony Young
|
|
|
Fire seal // Tobey Phone #: ###-####,, soffit ok
|
BLD-Energy code compliance | 6/21/2017 | 6/21/2017 | 6/21/2017 | P | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####
|
BLD-Framing/Rough-in | 6/15/2017 | 6/16/2017 | 6/16/2017 | A | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####
|
BLD-Conference | 6/2/2017 | 6/2/2017 | 6/2/2017 | A | DONE |
Jim Sly
|
|
|
Have questions on the wood burning fireplace chase height. Phone #: ###-#### Inspection requested via web by David Wipper
|
BLD-Wall Bracing | 5/26/2017 | 5/30/2017 | 5/30/2017 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper,, ext ok
|
BLD-Foundation | 4/14/2017 | 4/17/2017 | 4/17/2017 | A | PASS |
Brandon Shaw
|
|
|
Chris Phone #: ###-#### Foundation walls already poured at time of inspection.
|
BLD-Foundation | 4/13/2017 | 4/14/2017 | 4/14/2017 | A | NR |
Tony Young
|
|
|
Chris Phone #: ###-####,, too much snow/rain
|
BLD-Footing | 4/12/2017 | 4/12/2017 | 4/12/2017 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, work in progress
|
PubWorks Subgrade Approval | 4/11/2017 | 4/11/2017 | 4/11/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####
|
OVERRIDE | | | 3/31/2017 | | |
|
|
|
|
Plan assigned to (DAF) | 3/15/2017 | 3/15/2017 | 3/31/2017 | | DONE |
David Ferguson
|
|
|
(1st done) due 3/29 - Need addl. WUI details
|
Routing - PLAN CHECK | 3/31/2017 | | 3/31/2017 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/31/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/31/2017 | | DONE |
|
|
|
all requirements met
|
Issue PAID IN FULL permit | | | 3/31/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/31/2017 | | DONE |
|
|
|
|
1st review completed | | | 3/28/2017 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 3/10/2017 | | 3/28/2017 | | FAIL |
David Ferguson
|
|
|
|
Plan assigned to (LEG) Tisha | 3/10/2017 | | 3/15/2017 | | DEFR |
Tisha Gallop
|
|
|
|
Routing PW Grading-Hillside | 3/10/2017 | | 3/14/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Route to Impact Fee Review | 3/10/2017 | 3/13/2017 | 3/13/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of all new news permit requested for now.
|
Routing - Erosion and Sediment | 3/10/2017 | | 3/13/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Valid RP and PD designated. ESC site preparation inspection REQUIRED.
|
Routing - FIRE | 3/10/2017 | 3/10/2017 | 3/10/2017 | | PASS |
Katie Marron
|
|
|
Plans were reviewed for FD Access, hydrant availability and defensible space.
|
Routing - MECHANICAL | 3/10/2017 | | 3/10/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 3/10/2017 | | 3/10/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 3/10/2017 | | 3/10/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/10/2017 | | 3/10/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/10/2017 | | DONE |
|
|
|
|
Intake Approval | | | 3/10/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/10/2017 | | DONE |
|
|
|
|
Intake Approval | | | 3/9/2017 | | FAIL |
|
|
|
***met*** Need ESC Narrative, ResCheck and wall section/r-value
|
Telephone call | | | 3/9/2017 | | DONE |
|
|
|
called Dave-i need him to show me where some of the items are that failed in the 1st pre screen. I amy just be missing them-left him a message to callo me back
|
Application received | | | 3/6/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 6 2017 4:25PM
|