Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD17-00514
StatusFinaled
Name DAYSTAR EXCAVATION
Site Address 4495 S CURTIS RD
Project NameBoise Transfer Station Repair
Customer Number 
ePlanReviewYes
Description
(BOISE TRANSFER STATION REPARI) Special Inspection required per attached 310 form. Permit for repair of a concrete wall and replacement of slab per engineered plans and calculations. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice7/12/20177/12/20178/10/2017 DONE
DetailsMike Jordan
Mailed 8-11-17
BLD-Final7/11/20177/12/20177/12/2017PPASS
DetailsMike Jordan
Louise Phone #: ###-####
DOC - Permit Finaled7/12/20177/12/20177/12/2017PPASS
DetailsMike Jordan
FIRE-Final Inspection7/11/20177/12/20177/12/2017APASS
DetailsTroy Cobbley
life safety passed
BLD-Final7/10/20177/11/20177/11/2017PNR
DetailsMike Jordan
Lewis Bean Phone #: ###-####. Needs fire/life/safety final first.
BLD-Foundation6/13/20176/14/20176/14/2017PPASS
DetailsDave Hannah
Lewis Phone #: ###-####
BLD-Foundation5/9/20175/10/20175/10/2017PPASS
DetailsMike Jordan
Lewis Phone #: ###-####
Issue PAID IN FULL permit  4/26/2017 DONE
Inspection Record Card- Bld  4/26/2017 DONE
OVERRIDE  3/29/2017  
Plan assigned to (AJS)3/24/20173/24/20173/29/2017 PASS
DetailsAdele J Schaffeld-Griffin
(Apr 5 - 15 days) Boise Transfer Station Repair
Routing - PLAN CHECK3/28/2017 3/29/2017 PASS
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL3/28/2017 3/29/2017 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  3/29/2017 DONE
Permit Ready to Issue  3/29/2017 DONE
*** MET *** Need RP, GC Form and Revised Cert of Value
Plan assigned to (CJW)3/16/20173/16/20173/24/2017 DEFR
DetailsCarl Westfall
(Apr 5 - 15 days) Boise Transfer Station Repair
Routing - PLAN CHECK3/16/2017 3/24/2017 FAIL
DetailsAdele J Schaffeld-Griffin
pending structural
1st review completed  3/24/2017 DONE
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL3/16/2017 3/24/2017 FAIL
DetailsAdele J Schaffeld-Griffin
Routing PW Environmental3/16/2017 3/21/2017 PASS
DetailsRick Christenson
Routing - Erosion and Sediment3/16/2017 3/17/2017 PASS
DetailsAndy J. Long
ESC plan waiver approved.
Routing - FIRE3/16/20173/16/20173/16/2017 PASS
DetailsKatie Marron
no comments required
Routing PW Drainage3/16/2017 3/16/2017 PASS
DetailsBrian Murphy
Intake Approval  3/16/2017 PASS
DetailsCarl D Madsen
Carl M approved pre screen, fees paid verified
Routing - Addressing3/16/2017 3/16/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS3/16/2017 3/16/2017 PASS
DetailsRachael Beierle
Routing - Design Review3/16/2017 3/16/2017 PASS
DetailsSarah Schafer
Changes approved through building permit application.
Intake Approval  3/13/2017 FAIL
Please re-upload the plan sheets that are in a packet as individual sheets.
Application received  3/6/2017 DONE
Application submitted via PDS Online on Mar 6 2017 5:40PM