FIRE-Final Inspection | 10/18/2017 | 10/19/2017 | 10/19/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Matthew Phone #: ###-####
|
BLD-Final | 9/11/2017 | 9/13/2017 | 9/13/2017 | P | NR |
Mike Jordan
|
|
|
Matt Phone #: ###-####. Fire/life/safety final failed.
|
FIRE-Final Inspection | 9/11/2017 | 9/12/2017 | 9/12/2017 | P | FAIL |
Troy Cobbley
|
|
|
No city approved plans on site. I spoke to Matt and deferred him to plan review, (Carl) on the use of security grills, thumbturn dead bolts and 2x4's. I noted that the fire extinguisher was expired.
Matt Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/29/2017 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 3/13/2017 | | DONE |
|
|
|
All Met
|
Print Occupancy Form | | | 3/13/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/13/2017 | | DONE |
|
|
|
|
Telephone call | | | 3/13/2017 | | DONE |
|
|
|
Left a message for Matthew informing him that this permit is ready to be picked up and which ever tech he sees will go over the required inspections for occupancy
|
Plan assigned to (DAF) | 3/7/2017 | 3/7/2017 | 3/11/2017 | | DONE |
David Ferguson
|
|
|
due 3/13 - occupancy eval
|
Routing - PLAN CHECK | | | 3/11/2017 | | PASS |
David Ferguson
|
|
|
|
1st review completed | | | 3/11/2017 | | DONE |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 3/11/2017 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/11/2017 | | DONE |
|
|
|
|
Routing - FIRE | 3/7/2017 | 3/7/2017 | 3/8/2017 | | PASS |
Katie Marron
|
|
|
Magazines (as defined by the IFC i.e, safe boxes not individual cartridges) shall meet the requirements of IFC 5604.5.1.
|
Plans ACCEPTED BY PLAN TECH | | | 3/7/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 3/7/2017 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/7/2017 | | DONE |
Christina Prado
|
|
|
|
Application received | | 3/7/2017 | | | |
|
|
|
|