BLD-Final | 10/25/2017 | 10/31/2017 | 10/31/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 10/31/2017 | 10/31/2017 | 10/31/2017 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 10/27/2017 | 10/27/2017 | 10/27/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Energy code compliance | 8/18/2017 | 8/22/2017 | 8/22/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 8/15/2017 | 8/18/2017 | 8/18/2017 | A | FAIL |
Brandon Shaw
|
|
|
See correction notice OK to insulate
|
BLD-Wall Bracing | 7/26/2017 | 7/27/2017 | 7/27/2017 | A | PASS |
Brandon Shaw
|
|
|
Gelarmo Phone #: ###-####
|
BLD-Footing | 5/4/2017 | 5/4/2017 | 5/4/2017 | P | PASS |
Brandon Shaw
|
|
|
Pat Phone #: ###-####
|
PubWorks Subgrade Approval | 5/4/2017 | 5/4/2017 | 5/4/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 4/17/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 4/13/2017 | | |
|
|
|
|
Plan assigned to (AJS) | 3/21/2017 | 3/21/2017 | 4/13/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st Review Completed Due 3-27 Level 2
|
Inspection Record Card- Bld | | | 4/13/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/13/2017 | | DONE |
|
|
|
|
Telephone call | | | 4/13/2017 | | DONE |
|
|
|
called Josh and left vm
|
Case Summary (BLD) | | | 4/13/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/13/2017 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 4/13/2017 | | 4/13/2017 | | PASS |
Morgan Webb
|
|
|
|
Permit Ready to Issue | | | 4/13/2017 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 3/27/2017 | | 4/10/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
1st review completed | | | 3/28/2017 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 3/27/2017 | | 3/28/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Plan assigned to (BJM) | 3/8/2017 | 3/8/2017 | 3/21/2017 | | DEFR |
Brian McGowan
|
|
|
Due 3-27 Level 2
|
Plan resubmittals received | | | 3/21/2017 | | DONE |
Christina Prado
|
|
|
Received three sets of Finished Lot Grading Plan sheets (G1); Plans stamped and taken to Plan Review for routing
|
Routing - FIRE | 3/14/2017 | 3/8/2017 | 3/14/2017 | | PASS |
Scott Arellano
|
|
|
No Comments.
|
Routing - Erosion and Sediment | 3/13/2017 | | 3/14/2017 | | PASS |
Andy J. Long
|
|
|
pre-approved ESC plan waiver for East Valley hillside approved.
|
Route to Impact Fee Review | 3/8/2017 | 3/11/2017 | 3/13/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of all new news permit requested for now.
|
Routing PW Grading-Hillside | 3/8/2017 | | 3/13/2017 | | FAIL |
Jason C. Taylor
|
|
|
Need revised grading plans. JCT
|
Routing - PUBLIC WORKS | 3/13/2017 | | 3/13/2017 | | FAIL |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 3/13/2017 | | 3/13/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 3/13/2017 | | 3/13/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 3/8/2017 | | 3/8/2017 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/8/2017 | | DONE |
|
|
|
|
Intake Approval | | | 3/8/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/8/2017 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 3/8/2017 | | 3/8/2017 | | DEFR |
Tisha Gallop
|
|
|
Latigo 16A
|
Routing PW Sewer Rating | 3/8/2017 | | 3/8/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | 3/8/2017 | | | |
|
|
|
|