Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD17-00542
StatusFinaled
Name IVY DESIGNS LLC
Site Address 1607 N 7TH ST
Project Name 
Customer Number 
ePlanReviewNo
Description
Permit to add sliding glass doors to existing garage and vault the existing ceiling. Also, replace the stairs, landing and handrails on the back of the house. The work will be completed per the approved plans, attached engineering and local codes. **DAF**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/25/20175/26/20175/26/2017APASS
DetailsTony Young
Greg Phone #: ###-####,, wood added to guardrail to close openings to meet code now,, ok
DOC - Permit Finaled5/26/20175/26/20175/26/2017PPASS
DetailsTony Young
BLD-Conference5/24/20175/25/20175/25/2017APEND
DetailsTony Young
Greg Phone #: ###-####
BLD-Final5/24/20175/24/20175/25/2017PPART
DetailsTony Young
Greg Phone #: ###-####,, needs guardrail to meet code
Zoning Approval5/24/20175/24/20175/24/2017 PASS
DetailsTed Vanegas
BLD-Framing/Rough-in5/9/20175/9/20175/9/2017PPASS
DetailsTony Young
Deck framing for landing and stairs, on westside of existing house. 1" trek material will be applied to top and sides. Phone #: ###-#### Inspection requested via web by greg bauer
BLD-Footing5/1/20175/2/20175/3/2017PPART
DetailsTony Young
Footings for deck landing Phone #: ###-#### Inspection requested via web by greg bauer
BLD-Footing5/2/20175/2/20175/2/2017APART
DetailsTony Young
Footings for deck landing Phone #: ###-#### Inspection requested via web by greg bauer
BLD-Framing/Rough-in4/13/20174/14/20174/14/2017PPASS
DetailsBrandon Shaw
Final on framing, corner wall/post. Phone #: ###-#### Inspection requested via web by greg bauer
BLD-Other4/11/20174/12/20174/12/2017APASS
DetailsTony Young
Insulation installation. If you need to see insulation before drywall. Phone #: ###-#### Inspection requested via web by greg bauer
BLD-Footing4/10/20174/11/20174/11/2017APASS
DetailsDave Hannah
New footing to level area where new sliding doors are being installed. Phone #: ###-#### Inspection requested via web by greg bauer
BLD-Framing/Rough-in4/6/20174/7/20174/7/2017APASS
DetailsJim Sly
Rough in for everything except corner post, so i want to install insulation. Phone #: ###-#### Inspection requested via web by greg bauer
Everyting except corner post and New Footing.
BLD-Conference3/22/20173/23/20173/23/2017PPART
DetailsTony Young
Review framing at peck prior to collar tie installation Phone #: ###-#### Inspection requested via web by greg bauer,, wip
BLD-Conference3/21/20173/22/20173/22/2017APART
DetailsTony Young
Review framing at peck prior to collar tie installation Phone #: ###-#### Inspection requested via web by greg bauer/// work in progress,, ok,, engineer is watching also
BLD-Other3/20/20173/21/20173/21/2017APART
DetailsTony Young
Review framing at peck prior to collar tie installation Phone #: ###-#### Inspection requested via web by greg bauer//, work in progress,, opening up the roof area,, ok to procede
BLD-Conference3/20/20173/20/20173/20/2017PPEND
DetailsTony Young
Review framing at peck prior to collar tie installation Phone #: ###-#### Inspection requested via web by greg bauer
Routing Walk-In (Zoning)3/8/20173/8/20173/8/2017PPASS
Details
Routing Walk-In (BLD)3/8/20173/8/20173/8/2017PPASS
DetailsDavid Ferguson
Plan assigned to (DAF)3/8/20173/8/20173/8/2017 DONE
DetailsDavid Ferguson
Routing - PLAN CHECK3/8/2017 3/8/2017 PASS
DetailsDavid Ferguson
Inspection Record Card- Bld  3/8/2017 DONE
DetailsDavid Ferguson
Case Summary (BLD)  3/8/2017 DONE
DetailsDavid Ferguson
PLANS/APPL TAKEN TO FRONT DESK  3/8/2017 DONE
Permit Ready to Issue  3/8/2017 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  3/8/2017 DONE
DetailsChristina Prado
1st review completed  3/8/2017 DONE
DetailsDavid Ferguson
Application received 3/8/2017