First Notice | | 5/19/2018 | 6/5/2018 | | DONE |
|
|
|
This permit finaled on the web by David Rogers
|
BLD-Final | 5/7/2018 | 5/9/2018 | 5/9/2018 | A | PASS |
Tony Young
|
|
|
Call for keycode access if before 8:15 am, or otherwise should be open. Thanks. Phone #: ###-#### Inspection requested via web by David Rogers
|
Print Occupancy Form | | | 5/9/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 5/9/2018 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/3/2018 | 5/4/2018 | 5/4/2018 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, no fire sprinkler, no fire alarms, fire exitnguishers are in place with current inspection tags, final life fire safety inspetion complete.
Final Fire Re-inspection. Call for door access if not open. Thanks. Phone #: ###-#### Inspection requested via web by David Rogers
|
FIRE-Final Inspection | 4/16/2018 | 4/18/2018 | 4/18/2018 | A | FAIL |
Jim Page
|
|
|
Provide sticker on main east entry reading "Door to remain unlocked while occupied". Provide fire extinguishers with current inspection tags throughout tenant space including mezzanine. Provide emergency lighting to include exit discharge landings and exit signs per city approved drawings (Notated city approved plans with red ink). North exit door in gym area requires panic hardware (Notated city approved plans with red ink). Provide single action door hardware (Notated city approved drawings with red ink the exterior doors requiring single action door hardware). Provide occupant load sign for gym area.
|
Print Occupancy Form | | | 3/5/2018 | | DONE |
|
|
|
|
BLD-Aging Inspection | 2/7/2018 | 2/7/2018 | 2/8/2018 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 2/6/2018 | 2/6/2018 | 2/7/2018 | | PEND |
Tony Young
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/21/2017 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 12/14/2017 | 12/14/2017 | 12/15/2017 | | PASS |
Carl Westfall
|
|
|
x Plan mod - T3 Gym
|
Routing - PLAN CHECK | 12/14/2017 | | 12/15/2017 | | PASS |
Carl Westfall
|
|
|
|
Plan Reviewer's activity | | | 12/15/2017 | | PASS |
Carl Westfall
|
|
|
Plan mod approved
|
Permit Ready to Issue | | | 12/15/2017 | | DONE |
Christina Prado
|
|
|
All requirements met for Plan Mod
DO NOT RE-ISSUE - change status to ISS after fees paid in full
|
Plan Modification Accepted | | | 12/14/2017 | | DONE |
Christina Prado
|
|
|
Plan Mod to change the orientation of the ADA ramp
|
BLD-Final | 11/6/2017 | 11/7/2017 | 11/7/2017 | A | NR |
Tony Young
|
|
|
Call for garage code access Phone #: ###-#### Inspection requested via web by David Rogers,, needs trades finals,, need job finished
|
BLD-Framing/Rough-in | 9/22/2017 | 9/25/2017 | 9/25/2017 | A | PART |
Tony Young
|
|
|
Look to see if we can get approval to cover wall. Electrical and plumbing inspections have passed. Mechanical is all overhead on existing system and is still in process, so hoping wall cover can proceed. Call for access code. Thanks! Phone #: ###-#### Inspection requested via web by David Rogers,, walls ok to cover
|
BLD-Wall cover | 8/25/2017 | 8/29/2017 | 8/29/2017 | P | PASS |
Tony Young
|
|
|
Call half hour before // Garett Phone #: ###-####,, 2nd layer ok
|
BLD-Wall cover | 8/28/2017 | 8/29/2017 | 8/29/2017 | A | PASS |
Tony Young
|
|
|
Call half hour before // Garett Phone #: ###-####,, work in progress,, ok so far
|
BLD-Framing/Rough-in | 8/24/2017 | 8/25/2017 | 8/25/2017 | A | PART |
Tony Young
|
|
|
Call half hour before // Garett Phone #: ###-####,, studs in place on firewall,, 1st layer is work in progress,, ok
|
(F) Reprint permit | | | 8/24/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/24/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/22/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/22/2017 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 4/6/2017 | 4/6/2017 | 8/18/2017 | | PASS |
Carl Westfall
|
|
|
(3rd done) (Apr 26 - 15 days) (6 sheets) T3 Gym Remodel
|
Routing Off Site - STRUCTURAL | 8/8/2017 | | 8/18/2017 | | PASS |
Carl Westfall
|
|
|
Jan Welch (Stapley Engineering)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/18/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/18/2017 | | DONE |
|
|
|
Need GC Form and Revised Cert of Value
|
Routing - PLAN CHECK | 8/2/2017 | | 8/8/2017 | | PASS |
Carl Westfall
|
|
|
Routing for 2nd review was delayed because the assigned Plans Examiner was gone on vacation and because ePlanReview was not available because of an upgrade when he came back. He was gone on Aug 2, 3, and 4 (Wed, Thurs, Fri) but was back on Aug. 5 (Saturday). He could have routed it on Saturday had ePlanReview been available.
|
Plan resubmittals received | | | 8/2/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 7/17/2017 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 7/11/2017 | | 7/14/2017 | | FAIL |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Routing - PLAN CHECK | 7/7/2017 | | 7/11/2017 | | PASS |
Carl Westfall
|
|
|
Pending approval by Structural
|
Routing - MECHANICAL | 7/11/2017 | | 7/11/2017 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 7/7/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 5/24/2017 | 5/27/2017 | 5/25/2017 | | PASS |
Marissa Taylor
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 5/24/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 5/24/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/6/2017 | | 5/24/2017 | | FAIL |
Carl Westfall
|
|
|
Completed the 1st review. (15 days or 3 weeks over time frame)
|
Routing - Design Review | 4/6/2017 | | 4/12/2017 | | PASS |
Sarah Schafer
|
|
|
Approved per CZC17-00085
|
Routing Off Site - STRUCTURAL | 4/6/2017 | | 4/10/2017 | | FAIL |
Carl Westfall
|
|
|
Jan Welch (Stapley Engineering)
|
Routing - FIRE | 4/6/2017 | 4/6/2017 | 4/6/2017 | | PASS |
Katie Marron
|
|
|
Basic Life Safety. No comments required.
|
Intake Approval | | | 4/6/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie completed pre screen, verified fees paid
|
Plan Reviewer's activity | | | 4/6/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Greg, Please make sure that you reach out to ACHD for review on this change of use/occupancy. If additional fees are due they will need to be paid or paid when the permit is issued. If no fees are do please submit the documentation from ACDH as such.
Thank you
|
Routing - MECHANICAL | 4/6/2017 | | 4/6/2017 | | FAIL |
Troy James
|
|
|
|
Routing - Addressing | 4/6/2017 | | 4/6/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/6/2017 | | 4/6/2017 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 4/5/2017 | | FAIL |
Julie Romig
|
|
|
Provide the following information on the mechanical plans:
1. Mechanical plans require Mechanical Engineer stamp/signature or written approval from Mechanical Plans Examiner allowing architect to sign. Contact Troy James at ###-#### with questions/for approval.
2. Mechanical ComCheck for new heater (and any other new heating/cooling equipment).
3. Mechanical heating & cooling load calculations for new heater (and any other new equipment).
4. Due to change of occupancy from warehouse to gym, show how ventilation requirements for gym are met w/existing system.
|
Plan Reviewer's activity | | | 4/5/2017 | | |
|
|
|
Route to Mechanical
|
Intake Approval | | | 3/17/2017 | | FAIL |
Julie Romig
|
|
|
Need the following: Zoning Certificate; Structural calculations for stair guardrail and landing; Lighting Compliance COMcheck - cannot be a deferred submittal
|
Application received | | | 3/10/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 10 2017 3:12PM
|