Letter of compliance/Occupancy | | | 8/4/2017 | | DONE |
|
|
|
|
Telephone call | | | 8/4/2017 | | DONE |
|
|
|
Amanda Mock called requested a copy of the c of o so emailed it to her
|
BLD-Final | 7/27/2017 | 7/28/2017 | 7/28/2017 | P | PASS |
Jim Storey
|
|
|
PLEASE CALL ARON PRIOR ###-#### Phone #: ###-#### Inspection requested via web by Aron Mock
|
DOC - Permit Finaled | 7/28/2017 | 7/28/2017 | 7/28/2017 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 5/18/2017 | 5/18/2017 | 5/18/2017 | P | PASS |
Jim Storey
|
|
|
plans are in the fireplace, call Aron with any questions // Aron Phone #: ###-####
|
BLD-Framing/Rough-in | 5/18/2017 | 5/18/2017 | 5/18/2017 | P | PASS |
Jim Storey
|
|
|
plans are in the fireplace, call Aron with any questions // Aron Phone #: ###-####
|
BLD-Framing/Rough-in | 5/12/2017 | 5/12/2017 | 5/12/2017 | P | PART |
Jim Storey
|
|
|
Aron Phone #: ###-#### truss support 2nd floor // ok to insulate
|
BLD-Wall Bracing | 4/24/2017 | 4/25/2017 | 4/25/2017 | P | PASS |
Dave Hannah
|
|
|
Aron Phone #: ###-####
|
BLD-Foundation | 4/4/2017 | 4/4/2017 | 4/4/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 4/4/2017 | 4/4/2017 | 4/4/2017 | P | CANC |
Jim Storey
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron Inspection cancelled via mobile web on Tuesday, April 04, 2017.
|
BLD-Footing | 4/3/2017 | 4/3/2017 | 4/3/2017 | P | PASS |
Jim Storey
|
|
|
Ricordo Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/27/2017 | | DONE |
|
|
|
|
Telephone call | | | 3/23/2017 | | DONE |
|
|
|
notified customer that permit is ready
|
OVERRIDE | | | 3/22/2017 | | |
|
|
|
|
Plan assigned to (AJS) | 3/21/2017 | 3/21/2017 | 3/22/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed
|
1st review completed | | | 3/22/2017 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Meeting | | | 3/22/2017 | | DONE |
|
|
|
Aron came in to talk to the plan reviewer about some changes to the drawings
|
Routing - PLAN CHECK | 3/22/2017 | | 3/22/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 3/22/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/22/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/22/2017 | | DONE |
Christina Prado
|
|
|
Homeowner RP & GC, all requirements met
|
Inspection Record Card- Bld | | | 3/22/2017 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 3/14/2017 | | 3/22/2017 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Emailed applicant and left phone message.-
Aron, I have completed the plan review for the above permit. Please coordinate with your drafter to have all of the construction requirements incorporated into your drawings set. The drawings do not need to be stamped by the engineer however the construction changes need to be put on the plans.
Once those changes have been made to the drawings please bring in 2 sets of all revised sheets to be incorporated into the drawing package.
Thank you
|
Plan assigned to (BJM) | 3/15/2017 | 3/15/2017 | 3/21/2017 | | DEFR |
Brian McGowan
|
|
|
Due 3-24
|
Plan assigned to (LEG) Tisha | 3/13/2017 | | 3/15/2017 | | DEFR |
Tisha Gallop
|
|
|
|
Route to Impact Fee Review | 3/13/2017 | 3/16/2017 | 3/14/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of all new news permit requested for now.
|
Routing - MECHANICAL | 3/13/2017 | | 3/14/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 3/13/2017 | | 3/13/2017 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - PUBLIC WORKS | | | 3/13/2017 | | PASS |
|
|
|
|
Routing - Addressing | 3/13/2017 | | 3/13/2017 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/13/2017 | | DONE |
|
|
|
|
Intake Approval | | | 3/13/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/13/2017 | | DONE |
|
|
|
|
Application received | | 3/13/2017 | | | |
|
|
|
|