Print Occupancy Form | | | 4/27/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 4/27/2018 | | DONE |
|
|
|
|
Second Notice | | 3/24/2018 | 4/10/2018 | | DONE |
|
|
|
mailed 4-11-18
|
First Notice | 3/12/2018 | 3/12/2018 | 3/14/2018 | | DONE |
Brandon Shaw
|
|
|
Mailed 3-15-18
|
BLD-Final | 3/12/2018 | 3/12/2018 | 3/12/2018 | P | PASS |
Brandon Shaw
|
|
|
Early afternoon - Brent Phone #: ###-####
|
DOC - Permit Finaled | 3/12/2018 | 3/12/2018 | 3/12/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 3/6/2018 | 3/7/2018 | 3/7/2018 | P | FAIL |
Jim Storey
|
|
|
call for lock box code// Brent Phone #: ###-#### remove door #18/ handrail bothsides of stair w/returns
|
FIRE-Final Inspection | 3/6/2018 | 3/7/2018 | 3/7/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
call for lock box code// Brent Phone #: ###-####
|
Print Occupancy Form | | | 3/6/2018 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 12/22/2017 | 12/22/2017 | 12/22/2017 | P | PASS |
Jim Storey
|
|
|
Phone #: 2087136400 >> Inspection requested via mobile web by Brent
|
BLD-Framing/Rough-in | 12/7/2017 | 12/8/2017 | 12/8/2017 | A | NR |
Jim Storey
|
|
|
Phone #: 2087136400 >> Inspection requested via mobile web by Brent need ele
|
BLD-Framing/Rough-in | 12/7/2017 | 12/7/2017 | 12/7/2017 | A | PART |
Mike Jordan
|
|
|
New header ok. Complete all fire blocking and electrical rough in inspection, recall when completed.
|
BLD-Framing/Rough-in | 10/13/2017 | 10/17/2017 | 10/17/2017 | P | NR |
Jim Storey
|
|
|
Brett Phone #: ###-#### onf
|
Issue PAID IN FULL permit | | | 8/24/2017 | | DONE |
|
|
|
|
Expiration Notice | 8/16/2017 | 9/7/2017 | 8/16/2017 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 5/9/2017 | | |
|
|
|
|
Plan assigned to (JAR) | 4/6/2017 | 4/6/2017 | 5/9/2017 | | DONE |
Julie Romig
|
|
|
1st Review Complete. DUE 05/03 - L3 Gold Star Realty ePlan
|
Routing - PLAN CHECK | 5/5/2017 | | 5/9/2017 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/9/2017 | | DONE |
|
|
|
Need RP, - met 8-24
GC Form - met 8-24
and Revised Cert of Value met - 8-24
|
Routing - MECHANICAL | 5/5/2017 | | 5/8/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 5/2/2017 | 5/5/2017 | 5/3/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 5/2/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 4/6/2017 | | 5/2/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 4/6/2017 | | 5/1/2017 | | PASS |
Julie Romig
|
|
|
Structural passed in ePlanReview.
|
Routing - Design Review | 4/6/2017 | | 4/12/2017 | | PASS |
Sarah Schafer
|
|
|
With additional office space in the basement the site will still meet the parking requirements.
|
Routing - FIRE | 4/6/2017 | 4/6/2017 | 4/7/2017 | | PASS |
Katie Marron
|
|
|
Basic Life Safety. No comments required.
|
Routing - Erosion and Sediment | 4/6/2017 | | 4/6/2017 | | PASS |
Melissa Jannusch
|
|
|
Waiver letter approved
|
Plan Reviewer's activity | | | 4/6/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Randy,Please make sure that you reach out to ACHD for review on this change of use/occupancy. If additional fees are due they will need to be paid or paid when the permit is issued. If no fees are do please submit the documentation from ACDH as such.
Thank you
Adele Schaffeld-Griffin
Assistant Building Official / Plan Review Manager
Planning & Development Services Department
City of Boise - 150 N. Capitol Blvd.
P.O. Box 500
Boise, ID 83701
Office ###-####
Email – aschaffeldgriffin@cityofboise.org
“Building Boise Together.”
|
Routing - Addressing | 4/6/2017 | | 4/6/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/6/2017 | | 4/6/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 4/6/2017 | | 4/6/2017 | | FAIL |
Troy James
|
|
|
|
Intake Approval | | | 4/6/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
pre screen approved by Julie, applicant informed Major TI
|
Intake Approval | | | 3/27/2017 | | FAIL |
Julie Romig
|
|
|
Need the following: 1. Site specific fire flow at hydrants letter;
2. Erosion Control & Sediment Plan and Narrative;
3. Lighting plan and fixture schedule;
4. Lighting compliance COMcheck.
|
Intake Approval | | | 3/15/2017 | | FAIL |
Julie Romig
|
|
|
Major TI, not minor due to additional square footage of building
Need: 304 form, 520 checklist, Structural Calcs/Plans
Possibly need 310, depending on structural design
Rotate sheets so horizontal
|
Application received | | | 3/13/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 13 2017 9:42AM
|