Letter of compliance/Occupancy | | | 6/18/2018 | | DONE |
|
|
|
|
Zoning Approval | 6/14/2018 | 6/14/2018 | 6/14/2018 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Final | 6/11/2018 | 6/11/2018 | 6/11/2018 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Greg Strong
|
DOC - Permit Finaled | 6/11/2018 | 6/11/2018 | 6/11/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 6/6/2018 | 6/8/2018 | 6/11/2018 | P | CANC |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Greg Strong
|
BLD-Energy code compliance | 1/11/2018 | 1/12/2018 | 1/12/2018 | A | PASS |
Brandon Shaw
|
|
|
Framing corrections- sat
|
BLD-Framing/Rough-in | 1/4/2018 | 1/5/2018 | 1/8/2018 | A | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Greg Strong c/n on site ok to insulate
|
BLD-Wall cover | 12/13/2017 | 12/14/2017 | 12/13/2017 | A | CANC |
Dave Hannah
|
|
|
Phone #: ###-#### x208 >> Inspection requested via web by Greg Strong Inspection cancelled from web by: Greg Strong
|
BLD-Wall Bracing | 10/16/2017 | 10/17/2017 | 10/17/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: 2087247999 >> Inspection requested via mobile web by Corey Ure
|
BLD-Foundation | 9/14/2017 | 9/18/2017 | 9/18/2017 | P | PASS |
Dave Hannah
|
|
|
Entry Walls Phone #: ###-#### Inspection requested via web by Greg Strong
|
BLD-Footing | 9/13/2017 | 9/13/2017 | 9/15/2017 | P | PASS |
Brandon Shaw
|
|
|
Entry Footings Phone #: ###-#### Inspection requested via web by Greg Strong
|
BLD-Foundation | 9/14/2017 | 9/15/2017 | 9/14/2017 | P | CANC |
Dave Hannah
|
|
|
Entry Foundation Walls Phone #: ###-#### >> Inspection requested via web by Greg Strong Inspection cancelled from web by: Greg Strong
|
CHANGE STATUS TO (ISS) | | | 7/14/2017 | | DONE |
|
|
|
Plan Mod
|
Plan assigned to (BJM) | 6/30/2017 | 6/30/2017 | 7/10/2017 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 6/30/2017 | | 7/10/2017 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/10/2017 | | DONE |
|
|
|
DO NOT REISSUE - plan modificaiton fee due
|
BLD-Concrete | 6/29/2017 | 6/30/2017 | 6/30/2017 | P | PASS |
Dave Hannah
|
|
|
Footing/Slab Combo Pour Phone #: ###-#### Inspection requested via web by Greg Strong
|
BLD-Concrete | 6/28/2017 | 6/29/2017 | 6/29/2017 | P | CANC |
Brandon Shaw
|
|
|
this is for a slab pour with integral footings. Please inspect as late as possible - thank-you Phone #: ###-#### Inspection requested via web by Greg Strong
|
Plan Modification Accepted | | | 6/29/2017 | | DONE |
|
|
|
Plan mod workflow started to change basement window to egress compliant
|
BLD-Foundation | 5/30/2017 | 6/1/2017 | 6/1/2017 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Greg Strong
|
BLD-Footing | 5/16/2017 | 5/16/2017 | 5/16/2017 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Greg Strong
|
BLD-Footing | 4/24/2017 | 4/24/2017 | 4/24/2017 | A | CANC |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Inspection Record Card- Bld | | | 4/18/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/18/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 4/6/2017 | | |
|
|
|
|
Plan assigned to (DAF) | 3/22/2017 | 3/22/2017 | 4/6/2017 | | DONE |
David Ferguson
|
|
|
(1st done) due 3/31
|
Routing - PLAN CHECK | 4/6/2017 | | 4/6/2017 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/6/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/6/2017 | | DONE |
|
|
|
|
Routing - PLANNING | 4/5/2017 | | 4/5/2017 | | PASS |
Leon Letson
|
|
|
|
Routing - Design Review | 4/5/2017 | | 4/5/2017 | | PASS |
Andrea Tuning
|
|
|
|
1st review completed | | | 3/31/2017 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 3/14/2017 | | 3/31/2017 | | FAIL |
David Ferguson
|
|
|
|
Routing - PLANNING | 3/14/2017 | | 3/31/2017 | | FAIL |
Andrea Tuning
|
|
|
|
Plan assigned to (LEG) Tisha | 3/14/2017 | | 3/22/2017 | | DEFR |
Tisha Gallop
|
|
|
3/31 L2 Townhouse
|
Routing PW Grading-Hillside | 3/14/2017 | | 3/17/2017 | | CANC |
Jason C. Taylor
|
|
|
NOT A HILLSIDE PROJECT. JCT
|
Routing - Erosion and Sediment | 3/14/2017 | | 3/17/2017 | | PASS |
Andy J. Long
|
|
|
All ESC permits for 10 SFHs in Tablerock Subdivision are approved. ESC plan and SWPPP submitted under ESC16-00945 during subdivision development. Same RP designated.
|
Routing - MECHANICAL | 3/14/2017 | | 3/17/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 3/14/2017 | 3/17/2017 | 3/15/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of all new news permit requested for now.
|
Routing - FIRE | 3/14/2017 | 3/14/2017 | 3/15/2017 | | PASS |
Katie Marron
|
|
|
Plans were reviewed for FD Access and hydrant availability.
|
Routing - Addressing | 3/14/2017 | | 3/15/2017 | | PASS |
Laura Hunter
|
|
|
Updated address to 2349 E Warm Springs Ave
|
Routing - PUBLIC WORKS | 3/14/2017 | | 3/14/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/14/2017 | | DONE |
|
|
|
|
Intake Approval | | | 3/14/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/14/2017 | | DONE |
|
|
|
|
Application received | | 3/13/2017 | | | |
|
|
|
|
Application received | | 3/13/2017 | | | |
|
|
|
|