Second Notice | | 8/20/2017 | 8/18/2017 | | DONE |
|
|
|
This permit finaled on the web by James Thomas
|
First Notice | 7/26/2017 | 7/26/2017 | 8/10/2017 | | DONE |
Mike Jordan
|
|
|
Mailed 8-11-17
|
BLD-Final | 7/25/2017 | 7/26/2017 | 7/26/2017 | P | PASS |
Mike Jordan
|
|
|
Cameran Phone #: ###-####
|
DOC - Permit Finaled | 7/26/2017 | 7/26/2017 | 7/26/2017 | P | PASS |
Mike Jordan
|
|
|
All issues resolved. Flush bolts approved by plsn review.
|
BLD-Final | 7/16/2017 | 7/17/2017 | 7/17/2017 | P | PEND |
Mike Jordan
|
|
|
Please call Nic a half-hour before inspection. Phone #: ###-#### Inspection requested via web by Nic van Diepen. Architect to provide letter to building official for possible alternate for flush mounted locks on B occ. with 68 occupant load. Everything else ok.
|
FIRE-Final Inspection | 7/16/2017 | 7/17/2017 | 7/17/2017 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
BLD-Framing/Rough-in | 5/12/2017 | 5/12/2017 | 5/12/2017 | P | PASS |
Dave Hannah
|
|
|
Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen
|
FIRE-Conference | 5/5/2017 | 5/8/2017 | 5/8/2017 | P | DONE |
Troy Cobbley
|
|
|
Conference to discuss existing mag lock installation at door #17. Please call Nic a half-hour before arriving. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen
|
BLD-Footing | 5/1/2017 | 5/2/2017 | 5/2/2017 | A | PASS |
Mike Jordan
|
|
|
Please call Nic 1/2 hr before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen. Interior ncolumn pad footings ok.
|
BLD-Conference | 4/28/2017 | 5/1/2017 | 5/1/2017 | A | DONE |
Mike Jordan
|
|
|
Please call Nic 1/2hr before estimated arrival at site. Conference to discuss access for inspection of nailing. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen
|
Issue PAID IN FULL permit | | | 4/20/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/20/2017 | | DONE |
|
|
|
|
Plan assigned to (JG) | 3/14/2017 | 3/14/2017 | 3/28/2017 | | PASS |
Javier Guzman
|
|
|
3/27 L2 Rosewood Apartments Clubhouse ePlan
|
Routing - PLAN CHECK | 3/14/2017 | | 3/28/2017 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 3/28/2017 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/28/2017 | | DONE |
Christina Prado
|
|
|
All requirements met 3/30/17 C_P //// Need Gc and rev cert of val
|
Routing - Addressing | 3/14/2017 | | 3/15/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/14/2017 | | 3/15/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 3/14/2017 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 3/13/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 13 2017 1:11PM
|
Intake Approval | | | 3/13/2017 | | FAIL |
David Ferguson
|
|
|
The 6 plan sheets beginning with ID are not stamped, signed and dated.
|