Print Statement | | | 3/26/2018 | | DONE |
|
|
|
|
Second Notice | | 2/22/2018 | 3/14/2018 | | DONE |
|
|
|
mailed 3-15-18
|
First Notice | | 1/27/2018 | 2/12/2018 | | DONE |
|
|
|
Mailed 2-13-18
|
Permanent Occupancy | | | 1/17/2018 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 1/10/2018 | 1/10/2018 | 1/11/2018 | P | PASS |
Dave Hannah
|
|
|
Ryan Phone #: ###-####
|
FIRE-Final Inspection | 1/9/2018 | 1/10/2018 | 1/10/2018 | A | PASS |
Jim Page
|
|
|
Previously noted items have been repaired. Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguisher is in place with a current inspection tag. Final life fire safety inspection for area of work complete.
|
FIRE-Final Inspection | 1/8/2018 | 1/9/2018 | 1/9/2018 | A | FAIL |
Jim Page
|
|
|
Replace concealed fire sprinkler escutcheons that were painted after installation. Provide fire sprinkler in data closet.
|
BLD-Framing/Rough-in | 10/25/2017 | 10/26/2017 | 10/27/2017 | P | PASS |
Dave Hannah
|
|
|
Seth Minnis Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/6/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/6/2017 | | DONE |
|
|
|
|
Telephone call | | | 8/31/2017 | | DONE |
|
|
|
Left a message for Brad informing him this permit is going to expire in ten days. Told him if he would like he may send a request for a 180 day extension if he would like. Left permit number, my email and phone number
|
Expiration Notice | 8/16/2017 | 9/7/2017 | 8/16/2017 | | DONE |
Brittany Hill
|
|
|
|
Route to Impact Fee Review | 6/21/2017 | 6/24/2017 | 7/4/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (JG) | 6/8/2017 | 6/8/2017 | 6/28/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 6/21 L2 Okland Construction T.I. ePlan
|
Routing - PLAN CHECK | 6/22/2017 | | 6/28/2017 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/28/2017 | | DONE |
Christina Prado
|
|
|
All met 9/5/17 // need GC and rev cert of val
|
Routing - PLAN CHECK | 6/8/2017 | | 6/21/2017 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 6/21/2017 | | DONE |
Javier Guzman
|
|
|
|
Routing - FIRE | 6/8/2017 | 6/8/2017 | 6/8/2017 | | PASS |
Katie Marron
|
|
|
Separate Fire Permits will be required. No additional comments required.
|
Intake Approval | | | 6/8/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie approved pre screen
|
Routing - Addressing | 6/8/2017 | | 6/8/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/8/2017 | | 6/8/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 3/13/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 13 2017 2:46PM
|