BLD-Final | 5/4/2017 | 5/5/2017 | 5/5/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sheila Meyers
|
DOC - Permit Finaled | 5/5/2017 | 5/5/2017 | 5/5/2017 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 4/18/2017 | 4/20/2017 | 4/20/2017 | A | PASS |
Mike Jordan
|
|
|
Inspection requested via web by Sheila Meyers
|
BLD-Framing/Rough-in | 4/18/2017 | 4/19/2017 | 4/18/2017 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Sheila Meyers Inspection cancelled from web by: Sheila Meyers
|
BLD-Footing | 4/14/2017 | 4/17/2017 | 4/17/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sheila Meyers
|
Routing Walk-In (Zoning) | 3/15/2017 | 3/15/2017 | 3/15/2017 | A | PASS |
Nicolette Womack
|
|
|
|
Routing Walk-In (BLD) | 3/15/2017 | 3/15/2017 | 3/15/2017 | A | PASS |
David Ferguson
|
|
|
|
Plan assigned to (DAF) | 3/15/2017 | 3/15/2017 | 3/15/2017 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 3/15/2017 | | 3/15/2017 | | PASS |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 3/15/2017 | | DONE |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 3/15/2017 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/15/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/15/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/15/2017 | | DONE |
|
|
|
|
1st review completed | | | 3/15/2017 | | DONE |
David Ferguson
|
|
|
|
Application received | | 3/15/2017 | | | |
|
|
|
|