Second Notice | | 7/21/2018 | 7/23/2018 | | DONE |
|
|
|
This permit finaled on the web by Justin Dauby
|
First Notice | 7/5/2018 | 7/5/2018 | 7/11/2018 | | DONE |
Jim Storey
|
|
|
mailed 7-12-18
|
BLD-Final | 7/5/2018 | 7/5/2018 | 7/5/2018 | P | PASS |
Jim Storey
|
|
|
Mark ###-####
|
DOC - Permit Finaled | 7/5/2018 | 7/5/2018 | 7/5/2018 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 6/22/2018 | 6/25/2018 | 6/25/2018 | P | NR |
Jim Storey
|
|
|
Mark--call 30 mins before, will need to pick up access card at front door Phone #: ###-#### ele pending
|
FIRE-Final Inspection | 6/21/2018 | 6/22/2018 | 6/22/2018 | P | PASS |
Jim Page
|
|
|
Final life fire safety inspection for scope of work complete.
Mark-please call 30 mins before Phone #: ###-####
|
FIRE-Final Inspection | 6/7/2018 | 6/8/2018 | 6/8/2018 | P | CANC |
Troy Cobbley
|
|
|
Mark Phone #: ###-####
|
Permit Ready to Issue | | | 6/7/2018 | | DONE |
|
|
|
as per Carl M ok to change status to iss
|
CHANGE STATUS TO (ISS) | | | 6/7/2018 | | DONE |
|
|
|
as per Carl M-ok to change status to iss
|
Routing - Design Review | 1/25/2018 | | 1/25/2018 | | PASS |
Sarah Schafer
|
|
|
Approved per CZC18-00007.
|
Routing - PLAN CHECK | 1/25/2018 | | 1/25/2018 | | PASS |
Carl D Madsen
|
|
|
|
FIRE-Conference | 9/20/2017 | 9/20/2017 | 9/20/2017 | P | DONE |
Troy Cobbley
|
|
|
Mark and I discussed the security features on the new door in the exit corridor. I also discussed this with Carl Madsen in plan review. This door will need to meet all of the requirements in the IFC and IBC for Access Controled Egress Doors which includes the sensor. The Training Room needs two exits and this door causes issues with the secondary exiting from the Training Room per Carl. So plans will need to be re-submitted to plan review for possible approval of a different exiting system
|
FIRE-Conference | 8/16/2017 | 8/17/2017 | 8/17/2017 | A | DONE |
Jim Page
|
|
|
Fire conference complete
|
FIRE-Conference | 8/16/2017 | 8/16/2017 | 8/16/2017 | P | CANC |
Jim Page
|
|
|
Fire conference rescheduled for 17AUG2017, this request is cancelled.
|
Plan assigned to (DAF) | 3/21/2017 | 3/21/2017 | 4/6/2017 | | DONE |
David Ferguson
|
|
|
(1st done) due 4/3 - L2 Pacific Source TI - 1st FL TI ePlan
|
Routing - PLAN CHECK | 4/6/2017 | | 4/6/2017 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/6/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/6/2017 | | DONE |
|
|
|
Needs; GC Form & Revised Cert of Value
|
Issue PAID IN FULL permit | | | 4/6/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/6/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/5/2017 | | 4/5/2017 | | FAIL |
David Ferguson
|
|
|
|
Route to Impact Fee Review | 4/4/2017 | 4/7/2017 | 4/4/2017 | | PASS |
Tonya Wallace
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 3/21/2017 | | 4/4/2017 | | FAIL |
David Ferguson
|
|
|
|
1st review completed | | | 4/4/2017 | | DONE |
David Ferguson
|
|
|
|
Routing - FIRE | 3/21/2017 | 3/21/2017 | 3/22/2017 | | PASS |
Katie Marron
|
|
|
comments attached to case.
|
Intake Approval | | | 3/21/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 3/21/2017 | | 3/21/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/21/2017 | | 3/21/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 3/16/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 16 2017 2:06PM
|