Print Statement | | | 4/23/2018 | | DONE |
|
|
|
sent 1st late notice 4/24/18
|
Print Statement | | | 12/18/2017 | | DONE |
|
|
|
|
First Notice | 11/14/2017 | 11/14/2017 | 12/12/2017 | | DONE |
Mike Jordan
|
|
|
Mailed 12-13-17
|
BLD-Final | 11/14/2017 | 11/14/2017 | 11/14/2017 | P | PASS |
Mike Jordan
|
|
|
tyler Phone #: ###-####
|
DOC - Permit Finaled | 11/14/2017 | 11/14/2017 | 11/14/2017 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 11/14/2017 | 11/14/2017 | 11/14/2017 | P | PASS |
Jim Page
|
|
|
Previously noted items have been repaired, final life fire safety inspection passed/complete.
|
FIRE-Final Inspection | 10/20/2017 | 10/20/2017 | 10/20/2017 | P | FAIL |
Jim Page
|
|
|
Install addressing on exterior of building. In-duct detector needs to be tested for HVAC unti shutdown. Double key deadbolt with indicator or lever type door hardware needs to be installed in place of the thumbturn deadbolt assembly currently in place.
|
PubWorks Occupancy Approval | 10/19/2017 | 10/19/2017 | 10/19/2017 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 10/19/2017 | 10/19/2017 | 10/19/2017 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Ceiling Grid Inspection | 9/29/2017 | 9/29/2017 | 9/29/2017 | P | PASS |
Mike Jordan
|
|
|
Quiten Phone #: ###-####
|
BLD-Framing/Rough-in | 8/28/2017 | 8/28/2017 | 8/28/2017 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Energy code compliance | 8/28/2017 | 8/28/2017 | 8/28/2017 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 8/23/2017 | 8/23/2017 | 8/23/2017 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. Interior steel stud framed walls ok.
|
BLD-Framing/Rough-in | 8/15/2017 | 8/16/2017 | 8/16/2017 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. Kickers on parapet.
|
BLD-Final | 8/10/2017 | 8/11/2017 | 8/11/2017 | A | CANC |
Mike Jordan
|
|
|
roof deck & part seal-(later morning)John Phone #: ###-####
|
BLD-Framing/Rough-in | 8/11/2017 | 8/11/2017 | 8/11/2017 | A | PASS |
Mike Jordan
|
|
|
roof deck & part seal-(later morning)John Phone #: ###-####. Roof decking ok.
|
BLD-Other | 8/7/2017 | 8/7/2017 | 8/7/2017 | P | PASS |
Mike Jordan
|
|
|
Steel and Glue beam- John Phone #: ###-####. Glue lam beams to column connections, Steel stud exterior walls and parapet.
|
BLD-Foundation | 7/6/2017 | 7/7/2017 | 7/7/2017 | P | DEFR |
Mike Jordan
|
|
|
Rebar // Chet Phone #: ###-####. Special inspector on site. South stemwall and east concrete wall. Placement in progress when arrived on site.
|
BLD-Foundation | 6/29/2017 | 6/30/2017 | 6/30/2017 | A | PASS |
Mike Jordan
|
|
|
Concrete @8:30 - Chet Phone #: ###-####
|
BLD-Foundation | 6/28/2017 | 6/28/2017 | 6/28/2017 | P | PART |
Mike Jordan
|
|
|
Rebar // John Phone #: ###-####. Interior column pad footings. work in progress on installing rebar mat for west concrete wall, interior form was in place.
|
BLD-Other | 6/27/2017 | 6/28/2017 | 6/28/2017 | A | PART |
Mike Jordan
|
|
|
exterior wall rebar // John Phone #: ###-####. Work in progress on constructiing rebar mats. Will place mat and form on one side then call for inspection prior to placing 2nd. form.
|
BLD-Foundation | 6/27/2017 | 6/27/2017 | 6/27/2017 | P | DEFR |
Mike Jordan
|
|
|
Rebar ... pour at 2 // John Phone #: ###-####. Pending special inspection.
|
BLD-Foundation | 6/23/2017 | 6/26/2017 | 6/26/2017 | P | PASS |
Mike Jordan
|
|
|
3pm concrete Rebar // Chett Phone #: ###-####. Perimeter footings ok.
|
Issue PAID IN FULL permit | | | 6/20/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/20/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 6/16/2017 | | |
|
|
|
|
Plan assigned to (CJW) | 3/24/2017 | 3/24/2017 | 6/16/2017 | | PASS |
Carl Westfall
|
|
|
(4th done) (Apr 27 - 25 days) (53 sheets) Griffin Creek Office Building
|
Plan resubmittals received | | | 6/16/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/16/2017 | | 6/16/2017 | | PASS |
Carl Westfall
|
|
|
Drawings approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/16/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/16/2017 | | DONE |
|
|
|
Need ACHD, **met** GC Form and Revised Cert of Value (esc is with grading)
|
Plan resubmittals received | | | 6/14/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/14/2017 | | 6/14/2017 | | FAIL |
Carl Westfall
|
|
|
Item #4 not resolved
|
Plan resubmittals requested | | | 6/14/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 6/13/2017 | | DONE |
|
|
|
|
Routing PW Drainage | 6/2/2017 | | 6/12/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing Off Site - STRUCTURAL | 6/2/2017 | | 6/9/2017 | | PASS |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Routing - PLAN CHECK | 6/1/2017 | | 6/7/2017 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - MECHANICAL | 6/2/2017 | | 6/5/2017 | | PASS |
Troy James
|
|
|
parapet west wall lowered to 16'
|
Routing PW Sewer Design | 6/2/2017 | | 6/5/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
Existing service used for new building. Other existing service left as per previous requirements to buildings developing on Ardene St.
|
Routing - Design Review | 6/2/2017 | | 6/2/2017 | | PASS |
Andrea Tuning
|
|
|
|
Plan resubmittals received | | | 6/1/2017 | | DONE |
|
|
|
Drawings routed on 6-2-17
|
Route to Impact Fee Review | 5/20/2017 | 5/23/2017 | 5/22/2017 | | PASS |
Marissa Taylor
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 3/24/2017 | | 5/20/2017 | | FAIL |
Carl Westfall
|
|
|
1st review done
|
1st review completed | | | 5/20/2017 | | DONE |
|
|
|
Exceeded time frame by 12 days
|
Plan resubmittals requested | | | 5/20/2017 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/24/2017 | | 4/7/2017 | | FAIL |
Carl Westfall
|
|
|
Jan Welch
|
Routing - FIRE | 3/24/2017 | 3/24/2017 | 3/29/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing PW Drainage | 3/27/2017 | | 3/28/2017 | | FAIL |
Brian Murphy
|
|
|
NEED DRAIAGE REPORT , O AND M, DETAIL SHEET APDDX J
|
Routing PW Street Lights | 3/27/2017 | | 3/28/2017 | | PASS |
Tom Marshall
|
|
|
|
Routing - MECHANICAL | 3/24/2017 | | 3/28/2017 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 3/24/2017 | | 3/28/2017 | | PASS |
Bill VanDegrift
|
|
|
1) vent lavs and drinking fountain
2) 3" min. vent from restroom to VTR
3) DCVA required on water service
|
Routing - PLANNING Land Div | 3/24/2017 | | 3/27/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 3/24/2017 | | 3/27/2017 | | PASS |
Laura Hunter
|
|
|
Added Suites 110, 120, and 130
|
Routing - PUBLIC WORKS | 3/24/2017 | | 3/27/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 3/24/2017 | | 3/27/2017 | | PASS |
Melissa Jannusch
|
|
|
Daily street sweeping, DI protection, construction entrance, fiber wattles around the perimeter. RP TBD
|
Routing - Design Review | 3/24/2017 | | 3/27/2017 | | FAIL |
Andrea Tuning
|
|
|
Replace the Armstrong Maple trees with sLorraine Sweetgums.
|
Routing PW Sewer Design | 3/27/2017 | | 3/27/2017 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Disconnect and plug unused sewer service at the sewer main in Ardene Street. Call Boise Public Works 48 hours prior to work starting to obtain plug permit and schedule inspection.
|
Intake Approval | | | 3/24/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Pre screen approved by Javier
|
Intake Approval | | | 3/20/2017 | | FAIL |
Javier Guzman
|
|
|
Please provide and upload the following documents. (Incomplete submittals will not be accepted.):
1. Structural calculations are required to be stamped, signed and dated by an Idaho licensed engineer
2. Soils and geotech report for support of the structure stamped and signed by an Idaho licensed engineer
3. Soils and geotech report for infiltration systems stamped and signed by an Idaho licensed civil engineer, geologist, or soil scientist
4. Verification of Legal Lot or Parcel form signed and approved by PDS Subdivision Staff
5. Site specific fire flow at hydrants letter from Suez Water or other public water provider. Include static pressure if sprinklers are to be installed.
6. Erosion & Sediment Control (ESC) Narrative. Narrative must be designed for the specific project, and be prepared and signed by a plan designer certified by Boise City.
7. Planning & Zoning letter(s) of approval or Conditional Use Permit (CUP), Design Review Permit (DRH) and/or other approval documents
8. Form #310 – Statement of Special Inspections must be completed by the design engineer
|
Application received | | | 3/16/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 16 2017 4:20PM
|