Information based on query as of Monday, June 24, 2024.
Permit Information
Permit NumberBLD17-00669
StatusFinaled
Name LAYTON CONSTRUCTION
Site Address 8727 W ARDENE ST
Project NameGriffin Creek Bldg - Shell
Customer NumberESC17-00270
ePlanReviewYes
Description
(GRIFFIN CREEK OFFICE BUILDING – NEW BUILDING SHELL AND CORE – THREE TENANT SPACES) (DRH16-00398) This building does not have a fire sprinkler system. To construct a 5,165 square foot office building having 3 tenant spaces. Work is to include concrete footings, concrete foundations, concrete piers at perimeter columns, concrete slab on grade, tube steel columns, moment frames using wide flange beams and wide flange columns, glu-lam beams, steel roof deck, parapet braces, insulation installed on top of the roof deck, a single ply roofing membrane, primary and overflow roof drains, exterior steel stud walls with cavity and continuous insulation, 1-hr fire-resistance-rated West exterior wall and parapet due to proximity to the West property line, two uninsulated concrete exterior walls, an exterior steel awning at the building entry, exterior windows, exterior door, interior nonbearing walls, interior windows and doors, suspended acoustical ceiling, gypsum board ceilings, walnut wood ceiling, two shared toilet rooms accessible to the disabled, millwork, and finishes. Special Inspection is required for concrete, anchors post installed in hardened concrete, and structural steel (including bolting and welding). A trash enclosure will also be constructed under this permit. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. This permit does not establish a Certificate of Occupancy for any portion of this building or for any tenant. A separate permit is required to establish a Certificate of Occupancy for each individual tenant. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  4/23/2018 DONE
sent 1st late notice 4/24/18
Print Statement  12/18/2017 DONE
First Notice11/14/201711/14/201712/12/2017 DONE
DetailsMike Jordan
Mailed 12-13-17
BLD-Final11/14/201711/14/201711/14/2017PPASS
DetailsMike Jordan
tyler Phone #: ###-####
DOC - Permit Finaled11/14/201711/14/201711/14/2017PPASS
DetailsMike Jordan
FIRE-Final Inspection11/14/201711/14/201711/14/2017PPASS
DetailsJim Page
Previously noted items have been repaired, final life fire safety inspection passed/complete.
FIRE-Final Inspection10/20/201710/20/201710/20/2017PFAIL
DetailsJim Page
Install addressing on exterior of building. In-duct detector needs to be tested for HVAC unti shutdown. Double key deadbolt with indicator or lever type door hardware needs to be installed in place of the thumbturn deadbolt assembly currently in place.
PubWorks Occupancy Approval10/19/201710/19/201710/19/2017 DONE
DetailsTiffany Lowery
Zoning Approval10/19/201710/19/201710/19/2017 DONE
DetailsAndrea Tuning
BLD-Ceiling Grid Inspection9/29/20179/29/20179/29/2017PPASS
DetailsMike Jordan
Quiten Phone #: ###-####
BLD-Framing/Rough-in8/28/20178/28/20178/28/2017PPASS
DetailsMike Jordan
John Phone #: ###-####
BLD-Energy code compliance8/28/20178/28/20178/28/2017PPASS
DetailsMike Jordan
John Phone #: ###-####
BLD-Framing/Rough-in8/23/20178/23/20178/23/2017PPASS
DetailsMike Jordan
John Phone #: ###-####. Interior steel stud framed walls ok.
BLD-Framing/Rough-in8/15/20178/16/20178/16/2017APASS
DetailsMike Jordan
John Phone #: ###-####. Kickers on parapet.
BLD-Final8/10/20178/11/20178/11/2017ACANC
DetailsMike Jordan
roof deck & part seal-(later morning)John Phone #: ###-####
BLD-Framing/Rough-in8/11/20178/11/20178/11/2017APASS
DetailsMike Jordan
roof deck & part seal-(later morning)John Phone #: ###-####. Roof decking ok.
BLD-Other8/7/20178/7/20178/7/2017PPASS
DetailsMike Jordan
Steel and Glue beam- John Phone #: ###-####. Glue lam beams to column connections, Steel stud exterior walls and parapet.
BLD-Foundation7/6/20177/7/20177/7/2017PDEFR
DetailsMike Jordan
Rebar // Chet Phone #: ###-####. Special inspector on site. South stemwall and east concrete wall. Placement in progress when arrived on site.
BLD-Foundation6/29/20176/30/20176/30/2017APASS
DetailsMike Jordan
Concrete @8:30 - Chet Phone #: ###-####
BLD-Foundation6/28/20176/28/20176/28/2017PPART
DetailsMike Jordan
Rebar // John Phone #: ###-####. Interior column pad footings. work in progress on installing rebar mat for west concrete wall, interior form was in place.
BLD-Other6/27/20176/28/20176/28/2017APART
DetailsMike Jordan
exterior wall rebar // John Phone #: ###-####. Work in progress on constructiing rebar mats. Will place mat and form on one side then call for inspection prior to placing 2nd. form.
BLD-Foundation6/27/20176/27/20176/27/2017PDEFR
DetailsMike Jordan
Rebar ... pour at 2 // John Phone #: ###-####. Pending special inspection.
BLD-Foundation6/23/20176/26/20176/26/2017PPASS
DetailsMike Jordan
3pm concrete Rebar // Chett Phone #: ###-####. Perimeter footings ok.
Issue PAID IN FULL permit  6/20/2017 DONE
Inspection Record Card- Bld  6/20/2017 DONE
OVERRIDE  6/16/2017  
Plan assigned to (CJW)3/24/20173/24/20176/16/2017 PASS
DetailsCarl Westfall
(4th done) (Apr 27 - 25 days) (53 sheets) Griffin Creek Office Building
Plan resubmittals received  6/16/2017 DONE
Routing - PLAN CHECK6/16/2017 6/16/2017 PASS
DetailsCarl Westfall
Drawings approved
PLANS/APPL TAKEN TO FRONT DESK  6/16/2017 DONE
Permit Ready to Issue  6/16/2017 DONE
Need ACHD, **met** GC Form and Revised Cert of Value (esc is with grading)
Plan resubmittals received  6/14/2017 DONE
Routing - PLAN CHECK6/14/2017 6/14/2017 FAIL
DetailsCarl Westfall
Item #4 not resolved
Plan resubmittals requested  6/14/2017 DONE
Plan resubmittals requested  6/13/2017 DONE
Routing PW Drainage6/2/2017 6/12/2017 PASS
DetailsBrian Murphy
Routing Off Site - STRUCTURAL6/2/2017 6/9/2017 PASS
DetailsCarl Westfall
Jan Welch (Stapley)
Routing - PLAN CHECK6/1/2017 6/7/2017 FAIL
DetailsCarl Westfall
Revised drawings required
Routing - MECHANICAL6/2/2017 6/5/2017 PASS
DetailsTroy James
parapet west wall lowered to 16'
Routing PW Sewer Design6/2/2017 6/5/2017 PASS
DetailsKyle S. Rosenmeyer
Existing service used for new building. Other existing service left as per previous requirements to buildings developing on Ardene St.
Routing - Design Review6/2/2017 6/2/2017 PASS
DetailsAndrea Tuning
Plan resubmittals received  6/1/2017 DONE
Drawings routed on 6-2-17
Route to Impact Fee Review5/20/20175/23/20175/22/2017 PASS
DetailsMarissa Taylor
Review requested for Commercial Permit
Routing - PLAN CHECK3/24/2017 5/20/2017 FAIL
DetailsCarl Westfall
1st review done
1st review completed  5/20/2017 DONE
Exceeded time frame by 12 days
Plan resubmittals requested  5/20/2017 DONE
Routing Off Site - STRUCTURAL3/24/2017 4/7/2017 FAIL
DetailsCarl Westfall
Jan Welch
Routing - FIRE3/24/20173/24/20173/29/2017 PASS
DetailsKatie Marron
Comments attached to case.
Routing PW Drainage3/27/2017 3/28/2017 FAIL
DetailsBrian Murphy
NEED DRAIAGE REPORT , O AND M, DETAIL SHEET APDDX J
Routing PW Street Lights3/27/2017 3/28/2017 PASS
DetailsTom Marshall
Routing - MECHANICAL3/24/2017 3/28/2017 FAIL
DetailsTroy James
Routing - PLUMBING3/24/2017 3/28/2017 PASS
DetailsBill VanDegrift
1) vent lavs and drinking fountain
2) 3" min. vent from restroom to VTR
3) DCVA required on water service
Routing - PLANNING Land Div3/24/2017 3/27/2017 PASS
DetailsTodd Tucker
Routing - Addressing3/24/2017 3/27/2017 PASS
DetailsLaura Hunter
Added Suites 110, 120, and 130
Routing - PUBLIC WORKS3/24/2017 3/27/2017 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment3/24/2017 3/27/2017 PASS
DetailsMelissa Jannusch
Daily street sweeping, DI protection, construction entrance, fiber wattles around the perimeter. RP TBD
Routing - Design Review3/24/2017 3/27/2017 FAIL
DetailsAndrea Tuning
Replace the Armstrong Maple trees with sLorraine Sweetgums.
Routing PW Sewer Design3/27/2017 3/27/2017 FAIL
DetailsKyle S. Rosenmeyer
Disconnect and plug unused sewer service at the sewer main in Ardene Street. Call Boise Public Works 48 hours prior to work starting to obtain plug permit and schedule inspection.
Intake Approval  3/24/2017 PASS
DetailsAdele J Schaffeld-Griffin
Pre screen approved by Javier
Intake Approval  3/20/2017 FAIL
DetailsJavier Guzman
Please provide and upload the following documents. (Incomplete submittals will not be accepted.):
1. Structural calculations are required to be stamped, signed and dated by an Idaho licensed engineer
2. Soils and geotech report for support of the structure stamped and signed by an Idaho licensed engineer
3. Soils and geotech report for infiltration systems stamped and signed by an Idaho licensed civil engineer, geologist, or soil scientist
4. Verification of Legal Lot or Parcel form signed and approved by PDS Subdivision Staff
5. Site specific fire flow at hydrants letter from Suez Water or other public water provider. Include static pressure if sprinklers are to be installed.
6. Erosion & Sediment Control (ESC) Narrative. Narrative must be designed for the specific project, and be prepared and signed by a plan designer certified by Boise City.
7. Planning & Zoning letter(s) of approval or Conditional Use Permit (CUP), Design Review Permit (DRH) and/or other approval documents
8. Form #310 – Statement of Special Inspections must be completed by the design engineer
Application received  3/16/2017 DONE
Application submitted via PDS Online on Mar 16 2017 4:20PM