First Notice | | 9/24/2017 | 9/27/2017 | | DONE |
|
|
|
This permit finaled on the web by derek cooper
|
BLD-Final | 9/14/2017 | 9/14/2017 | 9/14/2017 | P | PASS |
Jim Storey
|
|
|
Hugo Phone #: ###-####
|
Permanent Occupancy | | | 9/14/2017 | | DONE |
|
|
|
|
BLD-Final | 9/8/2017 | 9/12/2017 | 9/12/2017 | P | FAIL |
Mike Jordan
|
|
|
hugo Phone #: ###-####. Install all missing glazing and provide lock indicator on main doors.
|
FIRE-Final Inspection | 9/8/2017 | 9/11/2017 | 9/11/2017 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 8/24/2017 | 8/25/2017 | 8/25/2017 | P | NR |
Mike Jordan
|
|
|
Call half hour before // Hugo Phone #: ###-####
|
FIRE-Final Inspection | 8/24/2017 | 8/25/2017 | 8/25/2017 | A | FAIL |
Troy Cobbley
|
|
|
Need the project related fire sprinkler permit addressed, need door hardware installed, exit signs and emergency lights tested, fire extinguishers mounted, suite number mounted
|
BLD-Ceiling Grid Inspection | 8/3/2017 | 8/4/2017 | 8/4/2017 | A | PASS |
Mike Jordan
|
|
|
Hughgo Phone #: ###-####
|
BLD-Conference | 8/1/2017 | 8/1/2017 | 8/1/2017 | P | PART |
Mike Jordan
|
|
|
Hugo-please call to meet Phone #: ###-####. Ceiling grid ok. wants to drop borders, needs elec. rough in inspection prior to placing border tile.
|
BLD-Framing/Rough-in | 6/8/2017 | 6/9/2017 | 6/9/2017 | A | PASS |
Dave Hannah
|
|
|
Call half hour before // Hugo Phone #: ###-####
|
BLD-Framing/Rough-in | 6/1/2017 | 6/1/2017 | 6/1/2017 | P | NR |
Jim Sly
|
|
|
Huga Phone #: ###-#### Framing appears OK..........Need Electr. Rough- In Approval.
|
Issue PAID IN FULL permit | | | 5/17/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/17/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 4/15/2017 | 4/18/2017 | 4/17/2017 | | PASS |
Tonya Wallace
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 4/17/2017 | | DONE |
Christina Prado
|
|
|
Need GC form & revised certificate of value for issuance
|
Plan assigned to (CJW) | 3/22/2017 | 3/22/2017 | 4/15/2017 | | PASS |
Carl Westfall
|
|
|
** (Apr 12 - 15 days) (25 sheets) Coldwell Banker Commercial
|
Routing - PLAN CHECK | 3/22/2017 | | 4/15/2017 | | PASS |
Carl Westfall
|
|
|
|
1st review completed | | | 4/15/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/15/2017 | | DONE |
|
|
|
|
Routing - MECHANICAL | 3/22/2017 | | 3/28/2017 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 3/22/2017 | 3/22/2017 | 3/23/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Intake Approval | | | 3/22/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie approved pre screen ,notifed applicant of major routing for 1st time tenant build out
|
Routing - Addressing | 3/22/2017 | | 3/22/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/22/2017 | | 3/22/2017 | | PASS |
Rachael Beierle
|
|
|
CONTACT WEST BOISE SEWER FOR PERMIT
|
Application received | | | 3/20/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 20 2017 1:55PM
|
Intake Approval | | | 3/20/2017 | | FAIL |
Julie Romig
|
|
|
Pre-screen #1: Major TI not minor due to first time tenant build-out in new core/shell bldg; Need 520 Major TI Checklist; Need to show riser locations.
|