BLD-Final | 12/18/2017 | 12/20/2017 | 12/20/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 12/20/2017 | 12/20/2017 | 12/20/2017 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Aging Inspection | 12/15/2017 | 12/15/2017 | 12/20/2017 | | DONE |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 12/19/2017 | 12/19/2017 | 12/19/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department Jason Taylor ###-####.
|
BLD-Aging Inspection | 12/14/2017 | 12/14/2017 | 12/14/2017 | | PEND |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Energy code compliance | 7/28/2017 | 8/2/2017 | 8/2/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 7/28/2017 | 7/31/2017 | 7/31/2017 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Other | 7/13/2017 | 7/13/2017 | 7/13/2017 | P | PASS |
Brandon Shaw
|
|
|
Fire- Soffit- Clint Phone #: ###-####
|
BLD-Wall Bracing | 7/12/2017 | 7/12/2017 | 7/12/2017 | P | PASS |
Brandon Shaw
|
|
|
Luna Phone #: ###-####
|
BLD-Footing | 5/25/2017 | 5/26/2017 | 5/26/2017 | P | PASS |
Brandon Shaw
|
|
|
Chris Phone #: ###-####
|
PubWorks Subgrade Approval | 5/25/2017 | 5/25/2017 | 5/25/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 5/16/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/16/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/16/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 5/11/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 4/13/2017 | 4/13/2017 | 5/11/2017 | | DONE |
Brian McGowan
|
|
|
due 4/13 sfd TAHOE PRIORITY - Failed in Hillside and top of fnd/ftg need to be specified
|
Routing - PLAN CHECK | 5/11/2017 | | 5/11/2017 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/11/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 5/11/2017 | | DONE |
|
|
|
all met
|
Routing PW Grading-Hillside | 5/5/2017 | | 5/5/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Plan assigned to (DAF) | 3/28/2017 | 3/28/2017 | 4/13/2017 | | DEFR |
David Ferguson
|
|
|
due 4/13 sfd TAHOE PRIORITY
|
1st review completed | | | 4/13/2017 | | FAIL |
Brian McGowan
|
|
|
Hillside requires top of foundation and footing be specified on foundation plan.
|
Routing - PLAN CHECK | 4/13/2017 | | 4/13/2017 | | FAIL |
Brian McGowan
|
|
|
Top of foundation and top of footing elevation needs to be specified.
|
Routing PW Grading-Hillside | 3/27/2017 | | 4/10/2017 | | FAIL |
Jason C. Taylor
|
|
|
see changemarks in eplan. JCT
|
Routing - FIRE | 3/27/2017 | 3/27/2017 | 3/29/2017 | | PASS |
Katie Marron
|
|
|
Plans were reviewed for FD access, hydrant availability and defensible space.
|
Routing - Erosion and Sediment | 3/27/2017 | | 3/29/2017 | | PASS |
Melissa Jannusch
|
|
|
Waiver ok.
|
Route to Impact Fee Review | 3/27/2017 | 3/30/2017 | 3/28/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (AJS) | 3/27/2017 | 3/27/2017 | 3/28/2017 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - MECHANICAL | 3/27/2017 | | 3/28/2017 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 3/27/2017 | | 3/28/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 3/27/2017 | | 3/27/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 3/27/2017 | | 3/27/2017 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/27/2017 | | DONE |
|
|
|
|
Intake Approval | | | 3/27/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/27/2017 | | DONE |
|
|
|
|
Application received | | | 3/21/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 21 2017 10:59AM
|
Routing - PLAN CHECK | 3/27/2017 | | | | |
Brian McGowan
|
|
|
|