BLD-Final | 7/12/2017 | 7/12/2017 | 7/12/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2085156235 >> Inspection requested via mobile web by Brian Rodriguez
|
DOC - Permit Finaled | 7/12/2017 | 7/12/2017 | 7/12/2017 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 6/2/2017 | 6/2/2017 | 6/2/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2085156235 >> Inspection requested via mobile web by Brian Rodriguez
|
BLD-Framing/Rough-in | 6/2/2017 | 6/2/2017 | 6/2/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2085156235 >> Inspection requested via mobile web by Brian Rodriguez
|
(F) Reprint permit | | | 6/2/2017 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 5/31/2017 | 5/31/2017 | 5/31/2017 | P | FAIL |
Mike Jordan
|
|
|
Phone #: 2085156235 >> Inspection requested via mobile web by Brian Rodriguez . Need fire place rough in inspection. Strap double top plate break at racked wall at peak and provide additional stud. Provide double 2x6 under 2ply at exterior wall in front bedroom. Correction notice posted. ok to insulate.
|
BLD-Wall Bracing | 5/19/2017 | 5/19/2017 | 5/19/2017 | P | PASS |
Mike Jordan
|
|
|
Zane Phone #: ###-####
|
BLD-Foundation | 4/27/2017 | 4/28/2017 | 4/28/2017 | A | PART |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo lira
|
BLD-Footing | 4/26/2017 | 4/27/2017 | 4/27/2017 | A | PART |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo lira
|
BLD-Footing | 4/26/2017 | 4/26/2017 | 4/26/2017 | P | NR |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo lira
|
Issue PAID IN FULL permit | | | 4/17/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 4/12/2017 | | |
|
|
|
|
Plan assigned to (DAF) | 3/28/2017 | 3/28/2017 | 4/12/2017 | | DONE |
David Ferguson
|
|
|
due 4/10
|
1st review completed | | | 4/12/2017 | | DONE |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 4/12/2017 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/12/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/12/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/12/2017 | | DONE |
|
|
|
MET
|
Routing - PLAN CHECK | 3/28/2017 | | 4/12/2017 | | PASS |
David Ferguson
|
|
|
|
Routing - MECHANICAL | | | 3/28/2017 | | PASS |
Troy James
|
|
|
|
Pending Assignment by AJS | 3/23/2017 | | 3/28/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Route to Impact Fee Review | 3/23/2017 | 3/26/2017 | 3/24/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 3/23/2017 | | 3/24/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 3/23/2017 | | 3/23/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 3/23/2017 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/23/2017 | | DONE |
|
|
|
|
Intake Approval | | | 3/23/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/23/2017 | | DONE |
|
|
|
|
Application received | | 3/23/2017 | | | |
|
|
|
|