Print Statement | | | 3/29/2018 | | DONE |
|
|
|
|
Third Notice | | 2/17/2018 | 3/14/2018 | | DONE |
|
|
|
Mailed 3-15-18
|
Third Notice | | 1/16/2018 | 2/12/2018 | | DONE |
|
|
|
Mailed 2-13-18
|
Second Notice | | 12/22/2017 | 1/11/2018 | | DONE |
|
|
|
Mailed 1-12-18
|
First Notice | 12/8/2017 | 12/8/2017 | 12/12/2017 | | DONE |
Jim Sly
|
|
|
Mailed 12-13-17
|
BLD-Final | 12/7/2017 | 12/8/2017 | 12/8/2017 | P | PASS |
Jim Sly
|
|
|
Ready for Final on Core and Shell. Also note that a request for Final on BLD-02486 (TI space) in same building for afternoon was submitted. Allows for one visit to see both at same time. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Mark Steen
|
DOC - Permit Finaled | 12/8/2017 | 12/8/2017 | 12/8/2017 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 12/6/2017 | 12/7/2017 | 12/7/2017 | P | PASS |
Troy Cobbley
|
|
|
Bldg shell fire/life safety passed. Contractor is going to provide fire dept access signage tomorrow. WIll be verified with the T.I. final inspection
|
Zoning Approval | 12/4/2017 | 12/4/2017 | 12/4/2017 | | PASS |
Katelyn Menuge
|
|
|
Design Review DRH16-00547
|
BLD-Footing | 9/19/2017 | 9/20/2017 | 9/21/2017 | P | CANC |
Mike Jordan
|
|
|
We anticipate being ready for inspection around 3pm Wednesday and plan to pour trash enclosure ftgs. Thursday am. Note, MTI checked sub grade ok. Thanks Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls
|
BLD-Framing/Rough-in | 9/14/2017 | 9/15/2017 | 9/15/2017 | A | PART |
Jim Sly
|
|
|
Framing riser room, thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls Riser Room....OK
|
BLD-Wall cover | 9/6/2017 | 9/7/2017 | 9/7/2017 | A | PASS |
Mike Jordan
|
|
|
Exterior insulation Phone #: ###-#### Inspection requested via web by Kareen Falls
|
BLD-Energy code compliance | 9/7/2017 | 9/7/2017 | 9/7/2017 | A | PASS |
Mike Jordan
|
|
|
Exterior insulation Phone #: ###-#### Inspection requested via web by Kareen Falls. remainder of building ok.
|
BLD-Wall cover | 8/30/2017 | 8/31/2017 | 8/31/2017 | P | PART |
Mike Jordan
|
|
|
ELec Insp to be requested for Thurs am North ext. wall ready for early afternoon Insp Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. North wall.
|
BLD-Conference | 8/10/2017 | 8/10/2017 | 8/10/2017 | A | FAIL |
Bill VanDegrift
|
|
|
needs to address backwater valve on sewer before paving
|
BLD-Concrete | 8/2/2017 | 8/3/2017 | 8/3/2017 | P | PASS |
Mike Jordan
|
|
|
SOG scheduled to pour 350 yds. 4am Friday. MTI to inspect and test concrete. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Vapor barrier ok.
|
BLD-Foundation | 7/19/2017 | 7/21/2017 | 7/21/2017 | A | DEFR |
Mike Jordan
|
|
|
MTI scheduled to Insp rebar and concrete at lines 1 west ; A. Concrete scheduled for 1:00pm. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Ok pending special inspection.
|
BLD-Footing | 7/19/2017 | 7/20/2017 | 7/20/2017 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Footing | 7/18/2017 | 7/19/2017 | 7/19/2017 | A | DEFR |
Mike Jordan
|
|
|
MTI scheduled for rebar Insp and concrete testing. Grid line A ftgs scheduled for concrete at 1pm Wed., thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Will have special inspection.
|
BLD-Footing | 7/13/2017 | 7/17/2017 | 7/17/2017 | A | PASS |
Mike Jordan
|
|
|
MTI to Insp rebar and test concrete at line 2 west. Concrete scheduled for noon Monday. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Footings on gridlines 1 and 2 from grids A to H. Will have special inspection.
|
BLD-Foundation | 7/13/2017 | 7/14/2017 | 7/14/2017 | A | PASS |
Mike Jordan
|
|
|
Concrete scheduled noon Friday. MTI to Insp rebar and test concrete. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. South Stemwall.
|
BLD-Foundation | 7/10/2017 | 7/11/2017 | 7/12/2017 | P | PART |
Jim Sly
|
|
|
Concrete scheduled for 9am Wed, July 12th with MTI special Insp of rebar and concrete testing. Thanks Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls OK pending MTI special inspection, tests and approvals.
|
BLD-Footing | 7/6/2017 | 7/7/2017 | 7/7/2017 | A | PART |
Brandon Shaw
|
|
|
Line 2, spread footings
|
BLD-Footing | 7/5/2017 | 7/6/2017 | 7/6/2017 | A | PART |
Mike Jordan
|
|
|
Concrete scheduled for 10:30am Thursday. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. South footing, concrete placement started when arried on site. Special inspetor onn site.
|
BLD-Footing | 6/30/2017 | 7/5/2017 | 7/5/2017 | A | CANC |
Mike Jordan
|
|
|
Concrete scheduled at noon. Thanks Phone #: ###-#### >> Inspection requested via web by Kareen Falls Inspection cancelled from web by: Kareen Falls
|
BLD-Footing | 6/28/2017 | 6/29/2017 | 6/29/2017 | A | PART |
Mike Jordan
|
|
|
Steel anticipated in place by 10:00am. Concrete scheduled at noon. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Work in progress on fotings on gridlineQ grids 1 to 3, grid 1 from grids o to Q and grid 1 from grid M to Q.
|
BLD-Footing | 6/27/2017 | 6/28/2017 | 6/28/2017 | P | NR |
Mike Jordan
|
|
|
3:30 pm is best. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls
|
BLD-Footing | 6/15/2017 | 6/16/2017 | 6/16/2017 | P | NR |
Jim Storey
|
|
|
Mark Steen is onsite Superintedent contact. Phone #: ###-#### Inspection requested via web by Kareen Falls
|
Issue PAID IN FULL permit | | | 6/14/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/14/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 5/17/2017 | | |
|
|
|
|
Routing - PLAN CHECK | 5/9/2017 | | 5/17/2017 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/17/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/17/2017 | | DONE |
Christina Prado
|
|
|
Need ACHD Only as of 5/22/17 C_P /// need revised cert of value, ACHD, RP and GC
|
Plan assigned to (CJW) | 4/3/2017 | | 5/17/2017 | | PASS |
Carl Westfall
|
|
|
(1st done) (May 11 - 30 days) (54 sheets) Victory Building
|
Routing Off Site - STRUCTURAL | 5/10/2017 | | 5/16/2017 | | PASS |
Carl Westfall
|
|
|
Route to Cory Harelson (KPFF)
|
Routing PW Street Lights | 5/10/2017 | | 5/10/2017 | | PASS |
Tom Marshall
|
|
|
route to TDM
|
Routing PW Drainage | 5/10/2017 | | 5/10/2017 | | PASS |
Brian Murphy
|
|
|
route to BGM
|
Plan resubmittals received | | | 5/9/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/5/2017 | | 5/8/2017 | | FAIL |
Carl Westfall
|
|
|
Had to rename revised sheets so that they would version right. Did not address either item. Sent it back to the applicant without routing it to other agencies. Route to TDM and BGM and KPFF.
|
Plan resubmittals requested | | | 5/8/2017 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/5/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 5/1/2017 | 5/4/2017 | 5/2/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 5/1/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 5/1/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/31/2017 | | 5/1/2017 | | FAIL |
Carl Westfall
|
|
|
See the IBC plan review report
|
Routing Off Site - STRUCTURAL | 3/31/2017 | | 4/14/2017 | | PASS |
Carl Westfall
|
|
|
Cory Harelson (KPFF)
|
Routing PW Environmental | 4/3/2017 | | 4/14/2017 | | PASS |
Rick Christenson
|
|
|
On-site inspections once completed.
|
Routing - Design Review | 3/31/2017 | | 4/12/2017 | | PASS |
Sarah Schafer
|
|
|
Received easement agreements today. They are located in the DRH16-547 case file.
|
Routing PW Sewer Design | 4/3/2017 | | 4/10/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Drainage | 4/3/2017 | | 4/5/2017 | | FAIL |
Brian Murphy
|
|
|
APDEX J AND P. LINE 2 FEET FROM GRADING
|
Routing - Erosion and Sediment | 3/31/2017 | | 4/5/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan and site map provided. Site preparation inspection required. Valid PD, need to designate RP.
|
Routing - PLANNING Land Div | 3/31/2017 | | 4/4/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing PW Solid Waste | 4/3/2017 | | 4/4/2017 | | PASS |
Evan Carpenter
|
|
|
Solid waste is OK as planned.
|
Routing - FIRE | 3/31/2017 | 3/31/2017 | 4/3/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - Addressing | 3/31/2017 | | 4/3/2017 | | PASS |
Laura Hunter
|
|
|
Updated address to 7552 W Victory Rd
|
Routing - PUBLIC WORKS | 3/31/2017 | | 4/3/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Street Lights | 4/3/2017 | | 4/3/2017 | | FAIL |
Tom Marshall
|
|
|
|
Routing - MECHANICAL | 3/31/2017 | | 4/3/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 3/31/2017 | | 4/3/2017 | | PASS |
Bill VanDegrift
|
|
|
trunk lines ok, per plans and ISPC
|
Routing - PLANNING | 3/31/2017 | | 4/3/2017 | | PASS |
Cody Riddle
|
|
|
Approved by DRH. No review required.
|
Intake Approval | | | 3/31/2017 | | PASS |
|
|
|
|
Intake Approval | | | 3/28/2017 | | FAIL |
Julie Romig
|
|
|
Missing Geotech report.; Rotate Sundance-Consolidation-ROS10170116 drawing; Rotate Victory-New Parcel Number; Stamp and Sign Erosion Control Plan EC-101; Rename MB plans with sheet number & description per City of Boise naming conventions; Remove "Not for Construction" on L1.
|
Application received | | | 3/23/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 23 2017 11:05AM
|