BLD-Final | 12/26/2017 | 12/28/2017 | 12/28/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 12/28/2017 | 12/28/2017 | 12/28/2017 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 12/28/2017 | 12/28/2017 | 12/28/2017 | | DONE |
Jason C. Taylor
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Final | 12/26/2017 | 12/27/2017 | 12/26/2017 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall Inspection cancelled from web by: Clint Wall
|
BLD-Energy code compliance | 10/20/2017 | 10/23/2017 | 10/23/2017 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 10/16/2017 | 10/19/2017 | 10/19/2017 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall c/n posted fire blk joist bottom chord broken at hanger in garage. ok to insulate
|
BLD-Other | 10/3/2017 | 10/3/2017 | 10/3/2017 | P | PASS |
Brandon Shaw
|
|
|
Soffit - Luna Phone #: ###-####
|
BLD-Wall Bracing | 10/3/2017 | 10/3/2017 | 10/3/2017 | P | PASS |
Brandon Shaw
|
|
|
Luna Phone #: ###-####
|
BLD-Foundation | 6/25/2017 | 6/26/2017 | 6/26/2017 | P | PASS |
Brandon Shaw
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
BLD-Footing | 6/22/2017 | 6/23/2017 | 6/23/2017 | P | PASS |
Brandon Shaw
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
PubWorks Subgrade Approval | 6/23/2017 | 6/23/2017 | 6/23/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 6/14/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/14/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 6/13/2017 | | |
|
|
|
|
Plan assigned to (DAF) | 3/28/2017 | 3/28/2017 | 6/13/2017 | | PASS |
David Ferguson
|
|
|
(1st done) due 4/13 review complete - failed hillside
|
Routing - PLAN CHECK | 6/8/2017 | | 6/13/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PUBLIC WORKS | 6/8/2017 | | 6/13/2017 | | PASS |
Rachael Beierle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/13/2017 | | DONE |
|
|
|
All Met
|
Routing PW Grading-Hillside | 3/27/2017 | | 6/9/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PLAN CHECK | 3/27/2017 | | 4/15/2017 | | PASS |
David Ferguson
|
|
|
|
1st review completed | | | 4/15/2017 | | DONE |
David Ferguson
|
|
|
|
Routing - FIRE | 3/27/2017 | 3/27/2017 | 3/29/2017 | | PASS |
Katie Marron
|
|
|
Plans were reviewed for FD Access, hydrant availability and defensible space. Per Subdivisons CC&R, common space located adjacent to this property shall be maintained by the HOA.
|
Routing - Erosion and Sediment | 3/27/2017 | | 3/29/2017 | | PASS |
Andy J. Long
|
|
|
Waiver letter ok.
|
Routing - MECHANICAL | 3/27/2017 | | 3/29/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 3/27/2017 | 3/30/2017 | 3/28/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (AJS) | 3/27/2017 | 3/27/2017 | 3/28/2017 | | CANC |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PUBLIC WORKS | 3/27/2017 | | 3/28/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/27/2017 | | DONE |
|
|
|
|
Intake Approval | | | 3/27/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/27/2017 | | DONE |
|
|
|
|
Routing - PLANNING | 3/27/2017 | | 3/27/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 3/27/2017 | | 3/27/2017 | | PASS |
Laura Hunter
|
|
|
|
Application received | | | 3/24/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 24 2017 8:34AM
|