BLD-Final | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | PASS |
Dave Hannah
|
|
|
Fire alarms have been changed to combo alarms. Call if any problema Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
|
DOC - Permit Finaled | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 3/6/2018 | 3/6/2018 | 3/6/2018 | P | PEND |
Dave Hannah
|
|
|
Call if any problems. Homeowners are on site Phone #: ###-#### Inspection requested via web by Timothy Beaudoin needs co2 detectors
|
Zoning Approval | 2/27/2018 | 2/27/2018 | 2/27/2018 | | DONE |
Ted Vanegas
|
|
|
|
BLD-Final | 2/2/2018 | 2/5/2018 | 2/6/2018 | A | NR |
Dave Hannah
|
|
|
Call Tim if at issues Phone #: ###-#### Inspection requested via web by Timothy Beaudoin needs mec and zoning finals
|
BLD-Final | 2/2/2018 | 2/2/2018 | 2/2/2018 | P | DEFR |
Jim Storey
|
|
|
Call Tim if at issues Phone #: ###-#### Inspection requested via web by Timothy Beaudoin out of time
|
BLD-Energy code compliance | 9/1/2017 | 9/1/2017 | 9/1/2017 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Wall cover | 8/31/2017 | 9/1/2017 | 9/1/2017 | A | PASS |
Dave Hannah
|
|
|
Thank you Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
|
BLD-Wall cover | 8/31/2017 | 8/31/2017 | 8/31/2017 | P | NR |
Dave Hannah
|
|
|
Franklin building supply is currently insulating. If possible....please inspect later in the day.
Thanks
Tim Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
|
BLD-Framing/Rough-in | 8/29/2017 | 8/29/2017 | 8/29/2017 | A | PASS |
Brandon Shaw
|
|
|
Call Tim if any problems Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
|
Plan Modification Accepted | | | 8/23/2017 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 8/23/2017 | | 8/23/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 8/15/2017 | 8/15/2017 | 8/15/2017 | P | PASS |
Tony Young
|
|
|
Call Tim if any problems Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
|
Routing - MECHANICAL | 7/25/2017 | | 7/25/2017 | | PASS |
Troy James
|
|
|
New manual j report
|
BLD-Footing | 6/29/2017 | 6/30/2017 | 6/30/2017 | A | PASS |
Dave Hannah
|
|
|
Call Tim if any problems Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
|
OVERRIDE | | | 6/29/2017 | | |
|
|
|
|
Routing Walk-In (BLD) | 6/29/2017 | 6/29/2017 | 6/29/2017 | A | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 6/29/2017 | | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 6/29/2017 | | 6/29/2017 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/29/2017 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 6/29/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/29/2017 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 6/28/2017 | 6/28/2017 | 6/28/2017 | P | PASS |
Katelyn Menuge
|
|
|
Plan Modification Approved
|
Routing Walk-In (BLD) | 6/28/2017 | 6/28/2017 | 6/28/2017 | P | FAIL |
Brian McGowan
|
|
|
Must have accurate plans of what he is proposing. Site plan, foundation plan, floor plan, elevations, structure, stair section required.
|
BLD-Foundation | 6/11/2017 | 6/12/2017 | 6/12/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
|
BLD-Foundation | 6/5/2017 | 6/5/2017 | 6/5/2017 | P | PASS |
Brandon Shaw
|
|
|
Call Tim if any problems Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
|
OVERRIDE | | | 6/5/2017 | | |
|
|
|
|
Routing Walk-In (BLD) | 6/5/2017 | 6/5/2017 | 6/5/2017 | A | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 6/5/2017 | | 6/5/2017 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 6/5/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/5/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/5/2017 | | DONE |
|
|
|
|
BLD-Foundation | 4/20/2017 | 4/20/2017 | 4/20/2017 | P | PART |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron already poured
|
BLD-Foundation | 4/12/2017 | 4/13/2017 | 4/13/2017 | P | NR |
Brandon Shaw
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 4/11/2017 | 4/12/2017 | 4/12/2017 | A | DONE |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Plan Reviewer's activity | | | 4/7/2017 | | DONE |
|
|
|
phone call from Tim Beaudoin. Encountered subgrade problems on site when excavated. Soil under addition was not adequate for support of foundation. See geotech eng. letter attached in documents for method of stabilization.
|
BLD-Footing | 4/5/2017 | 4/5/2017 | 4/5/2017 | P | FAIL |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron subgrade is to wet to place on ground is pumbing
|
BLD-Footing | 3/27/2017 | 3/28/2017 | 3/28/2017 | A | PART |
Tony Young
|
|
|
Tim is on site. Call if any issues Phone #: ###-#### Inspection requested via web by Timothy Beaudoin,, interior under floor footings,, ok,, work in progress
|
OVERRIDE | | | 3/27/2017 | | |
|
|
|
|
Routing Walk-In (Zoning) | 3/27/2017 | 3/27/2017 | 3/27/2017 | A | PASS |
Katelyn Menuge
|
|
|
Please see scope of work. No walls to be moved within 5' north interior side setback. DRH17-00798.
|
Routing Walk-In (BLD) | 3/27/2017 | 3/27/2017 | 3/27/2017 | A | PASS |
Tisha Gallop
|
|
|
|
Plan assigned to (LEG) Tisha | 3/27/2017 | | 3/27/2017 | | DONE |
Tisha Gallop
|
|
|
|
1st review completed | | | 3/27/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/27/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/27/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/27/2017 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 3/27/2017 | | DONE |
Christina Prado
|
|
|
|
Application received | | 3/27/2017 | | | |
|
|
|
|