BLD-Final | 2/6/2018 | 2/6/2018 | 2/6/2018 | P | PASS |
Brandon Shaw
|
|
|
Rolo Phone #: ###-####
|
DOC - Permit Finaled | 2/6/2018 | 2/6/2018 | 2/6/2018 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 1/26/2018 | 1/26/2018 | 1/26/2018 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Other | 12/14/2017 | 12/14/2017 | 12/14/2017 | P | PASS |
Brandon Shaw
|
|
|
Soffit inspection
|
BLD-Framing/Rough-in | 10/24/2017 | 10/24/2017 | 10/24/2017 | P | PASS |
Brandon Shaw
|
|
|
Rolo Phone #: ###-####
|
BLD-Framing/Rough-in | 10/23/2017 | 10/23/2017 | 10/23/2017 | P | FAIL |
Dave Hannah
|
|
|
Rolo Phone #: ###-#### no plans on site
|
BLD-Framing/Rough-in | 10/6/2017 | 10/9/2017 | 10/9/2017 | A | CANC |
Brandon Shaw
|
|
|
Rolo Phone #: ###-####
|
BLD-Energy code compliance | 10/6/2017 | 10/9/2017 | 10/9/2017 | A | CANC |
Brandon Shaw
|
|
|
Rolo Phone #: ###-####
|
BLD-Wall Bracing | 10/4/2017 | 10/4/2017 | 10/4/2017 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Wall Bracing | 10/3/2017 | 10/4/2017 | 10/4/2017 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Brad McJunkin
|
BLD-Foundation | 8/2/2017 | 8/2/2017 | 8/3/2017 | P | PASS |
Brandon Shaw
|
|
|
These will be ready at 3p Phone #: ###-#### Inspection requested via web by Kyle Seick
|
(F) Reprint permit | | | 8/3/2017 | | DONE |
|
|
|
|
BLD-Footing | 7/28/2017 | 7/31/2017 | 7/31/2017 | A | PASS |
Brandon Shaw
|
|
|
Please inspect late morning. Phone #: ###-#### Inspection requested via web by Kyle Seick
|
Issue PAID IN FULL permit | | | 7/28/2017 | | DONE |
|
|
|
|
PubWorks Subgrade Approval | 6/30/2017 | 6/30/2017 | 6/30/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####
|
OVERRIDE | | | 5/10/2017 | | |
|
|
|
|
Permit Ready to Issue | | | 5/10/2017 | | DONE |
Christina Prado
|
|
|
All requirements met for issuance
|
Plan assigned to (JG) | 4/24/2017 | 4/24/2017 | 5/9/2017 | | PASS |
Javier Guzman
|
|
|
5/10 L2 SFD ePlan
|
1st review completed | | | 5/9/2017 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/21/2017 | | 5/9/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing PW Grading-Hillside | 4/21/2017 | | 5/2/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Route to Impact Fee Review | 4/21/2017 | 4/24/2017 | 4/24/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | 4/21/2017 | 4/21/2017 | 4/24/2017 | | PASS |
Katie Marron
|
|
|
Plans were reviewed for fd access, hydrant availability and defensible space.
|
Routing - Erosion and Sediment | 4/21/2017 | | 4/24/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Valid PD and RP. Site preparation inspection required.
|
Pending Assignment by AJS | 4/21/2017 | | 4/24/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/21/2017 | | DONE |
|
|
|
|
Intake Approval | | | 4/21/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/21/2017 | | DONE |
|
|
|
|
Routing - MECHANICAL | 4/21/2017 | | 4/21/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 4/21/2017 | | 4/21/2017 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - Addressing | 4/21/2017 | | 4/21/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/21/2017 | | 4/21/2017 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 3/28/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 28 2017 8:43AM
|