Print Statement | | | 7/18/2017 | | DONE |
|
|
|
|
First Notice | | 6/25/2017 | 7/12/2017 | | DONE |
|
|
|
Mailed 7-13-17
|
Permanent Occupancy | | | 6/15/2017 | | DONE |
|
|
|
|
Zoning Approval | 6/14/2017 | 6/14/2017 | 6/14/2017 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Final | 6/12/2017 | 6/13/2017 | 6/13/2017 | P | PASS |
Jim Storey
|
|
|
Brent Phone #: ###-#### no racking
|
FIRE-Final Inspection | 6/12/2017 | 6/13/2017 | 6/13/2017 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection for building is complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
FIRE-Final Inspection | 6/8/2017 | 6/9/2017 | 6/9/2017 | A | FAIL |
Troy Cobbley
|
|
|
Need fire extinguisher at office and an exit sign in the office at the main entry doors, need exit signs as per plans and discussion in the warehouse area, needs missing door installed and panic hardware.
|
FIRE-Final Inspection | 6/1/2017 | 6/2/2017 | 6/2/2017 | P | FAIL |
Jim Page
|
|
|
Fire life safety cannot be completed for this permit until the fire sprinkler/fire alarm (FIR16-00724 for fire alarm and FIR16-00705 for fire sprinkler) permits for core and shell are complete as well as the BLD (BLD16-02176) permit for core and shell is complete. After core and shell permits are passed then the FIR permit (FIR17-00190) for fire sprinklers associated with this project will need to be completed before life fire safey inspection can be performed.
|
BLD-Ceiling Grid Inspection | 5/31/2017 | 5/31/2017 | 5/31/2017 | P | PASS |
Dave Hannah
|
|
|
Brent Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/17/2017 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 5/17/2017 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 4/5/2017 | 4/5/2017 | 5/16/2017 | | PASS |
Carl Westfall
|
|
|
(2nd done) (Apr 25 - 15 days) (38 sheets) PODS
|
Routing - PLAN CHECK | 5/11/2017 | | 5/16/2017 | | PASS |
Carl Westfall
|
|
|
Approved by Structural
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/16/2017 | | DONE |
|
|
|
***Met 5-16-17 can***Need GC Form and Revised Cert of Value
|
Route to Impact Fee Review | 5/11/2017 | 5/14/2017 | 5/15/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 5/11/2017 | | 5/12/2017 | | PASS |
Katie Marron
|
|
|
Revised report attached to case.
|
Routing Off Site - STRUCTURAL | 5/11/2017 | | 5/12/2017 | | PASS |
Carl Westfall
|
|
|
Chris Holladay (AHJ)
|
1st review completed | | | 5/11/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 5/11/2017 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/11/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/5/2017 | | 5/11/2017 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing Off Site - STRUCTURAL | 4/5/2017 | | 4/14/2017 | | FAIL |
Carl Westfall
|
|
|
Chris Holladay (AHJ)
|
Routing PW Environmental | 4/5/2017 | | 4/14/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 4/5/2017 | | 4/10/2017 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - FIRE | 4/5/2017 | 4/5/2017 | 4/6/2017 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
Routing - PLUMBING | 4/5/2017 | | 4/5/2017 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 4/5/2017 | | 4/5/2017 | | PASS |
Laura Hunter
|
|
|
Added suite number 110
|
Routing - PUBLIC WORKS | 4/5/2017 | | 4/5/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 4/5/2017 | | 4/5/2017 | | PASS |
Andy J. Long
|
|
|
See ESC16-00843 for coverage on Beechcraft Building. No new permit required
|
Intake Approval | | | 4/5/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
JAR completed pre screen and fees paid, Julie informed applicant this 1st time build out is a Major TI
|
Routing - Design Review | 4/5/2017 | | 4/5/2017 | | PASS |
Andrea Tuning
|
|
|
|
Intake Approval | | | 4/4/2017 | | FAIL |
Julie Romig
|
|
|
Provide U-factor for new door
|
Intake Approval | | | 4/3/2017 | | FAIL |
Julie Romig
|
|
|
Major Tenant Improvement, not a Minor. Submit Form 520 Checklist and all applicable documents including but not limited to the following items:
1. Site specific fire flow at hydrants letter
2. Structural calcs, foundation plans, wall framing/bracing - indicated on checklist but not attached.
3. Building envelope compliance for new door (U-factor & SHGC)
|
Application received | | | 3/30/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 30 2017 10:29AM
|