Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberBLD17-00853
StatusFinaled
Name SYRINGA CONSTRUCTION OF IDAHO LLC
Site Address 1909 N 15TH ST
Project Name 
Customer NumberBLD16-03632 DEMO
ePlanReviewNo
Description
See DRH16-00473 - Permit for the construction of a new 2,335 sq. ft., two story (first story 1,551 sq. ft., second story 784 sq. ft.) single family dwelling with 4 bedrooms, 2.5 bathrooms, approximately 154 sq. ft. of covered patio/porch and a 528 sq. ft. detached garage per the approved plans and any notations. Prescriptive Energy Code is proposed. R-1CH zoning and setbacks per planning. **BJM**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/28/201710/3/201710/3/2017PPASS
DetailsJim Storey
Final for C of O. Garage code is 0713. Key to home is on the window sill in the garage. Thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson
DOC - Permit Finaled10/3/201710/3/201710/3/2017PPASS
DetailsJim Storey
BLD-Other9/28/201710/2/201710/2/2017PCANC
DetailsDave Hannah
Historic Review for Certificate of Appropriateness needed. Please send out Historic Staff and issue the Certificate. thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson
Zoning Approval10/2/201710/2/201710/2/2017 PASS
DetailsTed Vanegas
Meeting  10/2/2017 DONE
as per Dave Hannah need HD inspection-called Ted V and he is going out to do the inspetion today
BLD-Wall cover7/7/20177/10/20177/10/2017APASS
DetailsTony Young
Hi -- Need a Sheetrock Sheer inspection please. Phone #: ###-#### Inspection requested via web by Steve Hanson
BLD-Framing/Rough-in7/3/20177/3/20177/3/2017APASS
DetailsMike Jordan
BLD-Energy code compliance6/28/20176/29/20176/29/2017PNR
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Steve Hanson. Framing corrections not made. No cover.
BLD-Framing/Rough-in6/26/20176/27/20176/27/2017APART
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Steve Hanson ok to insulate c/n on site
BLD-Wall Bracing6/12/20176/13/20176/13/2017APASS
DetailsTony Young
BLD-Wall Bracing6/9/20176/12/20176/12/2017APEND
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Steve Hanson blocking installed
BLD-Wall Bracing6/7/20176/9/20176/9/2017ANR
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Steve Hanson
Plan Modification Accepted  6/9/2017 DONE
new manual j report
Routing - MECHANICAL6/9/2017 6/9/2017 PASS
DetailsTroy James
resubmitted manual j report
BLD-Foundation4/30/20175/1/20175/1/2017ADONE
DetailsTony Young
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo lira
BLD-Footing4/27/20174/28/20174/28/2017APASS
DetailsTony Young
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo lira,, house and garage ok
Inspection Record Card- Bld  4/25/2017 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  4/25/2017 DONE
DetailsChristina Prado
Routing Walk-In (BLD)4/4/20174/4/20174/18/2017PDONE
DetailsBrian McGowan
Plan assigned to (BJM)4/3/20174/3/20174/18/2017 DONE
DetailsBrian McGowan
Due 4-12 - FAil - Site Plan needs to be updated, several beams and point loads need to be provided. Garage needs to be flipped.
Routing - PLAN CHECK4/18/2017 4/18/2017 PASS
DetailsBrian McGowan
Case Summary (BLD)  4/18/2017 DONE
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  4/18/2017 DONE
DetailsBrian McGowan
Permit Ready to Issue  4/18/2017 DONE
DetailsChristina Prado
Parcel must be consolidated and updated prior to issuance.
Inspection Record Card- Bld  4/18/2017 DONE
Telephone call  4/18/2017 DONE
DetailsChristina Prado
Called Steve to advise permit cannot be issued until Parcel is consolidated. Fees are being updated to reflect proper credits for SFD demolition (BLD16-03632)
Plan resubmittals received  4/13/2017  
DetailsChristina Prado
Received two sets of revised plan sheets marked Cover, Foundation, Upper Floor, Main FLoor, Elevations & Electrical; Plans stamped and taken to BJM for review
1st review completed  4/12/2017 FAIL
DetailsBrian McGowan
Site Plan needs to be updated, several beams and point loads need to be provided. GArage needs to be flipped.
Routing - MECHANICAL4/12/2017 4/12/2017 PASS
DetailsTroy James
Routing - PLAN CHECK4/10/2017 4/12/2017 FAIL
DetailsBrian McGowan
Site Plan needs to be updated, several beams and point loads need to be provided. GArage needs to be flipped.
Routing - MECHANICAL  4/10/2017 FAIL
DetailsTroy James
emailed corrections to mechanical contractor
Routing - PLANNING3/31/2017 4/4/2017 PASS
DetailsTed Vanegas
Routing - Design Review  4/4/2017 PASS
DetailsTed Vanegas
Plan assigned to (AJS)3/30/20173/30/20174/3/2017 DEFR
DetailsAdele J Schaffeld-Griffin
Route to Impact Fee Review3/30/20174/2/20173/31/2017 PASS
DetailsTonya Wallace
Initial residential review of new SFD permits requested for now.
Routing - Addressing3/30/2017 3/31/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS3/31/2017 3/31/2017 PASS
DetailsMorgan Webb
Plans ACCEPTED BY PLAN TECH  3/30/2017 DONE
Intake Approval  3/30/2017 PASS
Recd Pcfee & Taken To Pln CK  3/30/2017 DONE
BLD-Energy code compliance6/29/20176/30/2017 P 
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Steve Hanson
Application received 3/30/2017