Third Notice | | 4/15/2018 | 5/1/2018 | | DONE |
|
|
|
|
Third Notice | | 3/19/2018 | 4/10/2018 | | DONE |
|
|
|
mailed 4-11-18
|
Second Notice | | 2/22/2018 | 3/14/2018 | | DONE |
|
|
|
Mailed 3-15-18
|
First Notice | | 1/15/2018 | 2/12/2018 | | DONE |
|
|
|
Mailed 2-13-18
|
Print Occupancy Form | | | 1/5/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/5/2018 | | DONE |
|
|
|
|
BLD-Final | 1/2/2018 | 1/3/2018 | 1/3/2018 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jim Williams
|
FIRE-Final Inspection | 12/28/2017 | 1/2/2018 | 1/2/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection for area of work complete.
|
CHANGE STATUS TO (ISS) | | | 12/28/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/28/2017 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 10/4/2017 | 10/4/2017 | 10/12/2017 | | PASS |
Carl Westfall
|
|
|
(1st done) Plan mod - ICRM
|
Plan Reviewer's activity | | | 10/12/2017 | | DONE |
|
|
|
Routing completed
|
Permit Ready to Issue | | | 10/12/2017 | | DONE |
|
|
|
DO NOT REISSUE- PLAN MOD #2 (added additional 5k value)
|
Routing - FIRE | 10/10/2017 | | 10/11/2017 | | PASS |
Scott Arellano
|
|
|
No review required
|
Plan Modification Accepted | | | 10/10/2017 | | DONE |
|
|
|
Workflow in ePlanReview received
|
Routing - PLAN CHECK | 10/10/2017 | | 10/10/2017 | | PASS |
Carl Westfall
|
|
|
|
Plan Modification Accepted | | | 10/4/2017 | | DONE |
Christina Prado
|
|
|
Plan Mod #2 for med gas piping updates
|
CHANGE STATUS TO (ISS) | | | 9/12/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/12/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/30/2017 | | DONE |
Christina Prado
|
|
|
All requirements met for Plan Mod
DO NOT RE-IEEUE PERMIT, change status to ISS once all fees are paid
|
Plan assigned to (CJW) | 8/18/2017 | 8/18/2017 | 8/29/2017 | | PASS |
Carl Westfall
|
|
|
plan mod
|
Plan Reviewer's activity | | | 8/29/2017 | | DONE |
|
|
|
Plan mod approved
|
Routing - PLAN CHECK | 8/25/2017 | | 8/29/2017 | | PASS |
Carl Westfall
|
|
|
Sink added
|
Routing - PUBLIC WORKS | 8/25/2017 | | 8/28/2017 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PLUMBING | 8/25/2017 | | 8/25/2017 | | PASS |
Bill VanDegrift
|
|
|
added/relocated fixtures
If dishwasher is for sterile purposes indirect waste will be required.
|
Plan Modification Accepted | | | 8/22/2017 | | DONE |
|
|
|
Drawings uploaded
|
Plan Modification Accepted | | | 8/18/2017 | | DONE |
Christina Prado
|
|
|
Plan Mod to add a wall mount, accessible sink with soap & paper towel dispenser into collection room 132
|
BLD-Energy code compliance | 8/1/2017 | 8/2/2017 | 8/3/2017 | P | PART |
Dave Hannah
|
|
|
Insulation vapor barrier for perimeter top down drywall.
Thanks Phone #: ###-#### Inspection requested via web by Jim Williams
|
Issue PAID IN FULL permit | | | 6/21/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/21/2017 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 5/2/2017 | 5/2/2017 | 6/19/2017 | | PASS |
Carl Westfall
|
|
|
(1st donei) (May 22 - 15 days) (50 sheets) ICRM
|
Routing - PLAN CHECK | 6/14/2017 | | 6/19/2017 | | PASS |
Carl Westfall
|
|
|
2nd IBC plan review approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/19/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/19/2017 | | DONE |
|
|
|
**all met 6/19/17 leg** Need revised cert of value, GC form, **MET** and ACHD
|
Routing - FIRE | 6/14/2017 | | 6/15/2017 | | PASS |
Katie Marron
|
|
|
Revised report attached to case.
|
Routing - MECHANICAL | 6/14/2017 | | 6/15/2017 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 6/14/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 6/10/2017 | 6/13/2017 | 6/12/2017 | | PASS |
Marissa Taylor
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 5/2/2017 | | 6/10/2017 | | FAIL |
Carl Westfall
|
|
|
Revised drawings requested
|
Plan resubmittals requested | | | 6/10/2017 | | DONE |
|
|
|
|
1st review completed | | | 6/10/2017 | | DONE |
|
|
|
|
Routing PW Environmental | 5/3/2017 | | 5/11/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Solid Waste | 5/3/2017 | | 5/9/2017 | | PASS |
Evan Carpenter
|
|
|
Solid waste is OK as planned.
|
Routing - Erosion and Sediment | 5/2/2017 | | 5/4/2017 | | PASS |
Andy J. Long
|
|
|
No new permit, see ESC16-01612 for permit coverage
|
Routing PW Sewer Design | 5/3/2017 | | 5/4/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
No Review Required.
|
Routing - Design Review | 5/2/2017 | | 5/4/2017 | | PASS |
Sarah Schafer
|
|
|
|
Routing - FIRE | 5/2/2017 | 5/2/2017 | 5/3/2017 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
Routing - MECHANICAL | 5/2/2017 | | 5/3/2017 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 5/2/2017 | | 5/3/2017 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 5/2/2017 | | 5/3/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/2/2017 | | 5/3/2017 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 5/2/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Javier approved pre screen, verified fees paid
|
Intake Approval | | | 4/6/2017 | | FAIL |
Javier Guzman
|
|
|
Please provide the following and upload or revise:
1. Please upload Planning & Zoning letter of approval modification of Design Review (DRH17-00123 as stated in checklist)
2. Please sign Lighting compliance COMcheck on plan sheet #E502
|
Application received | | | 3/30/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 30 2017 7:23PM
|