BLD-Final | 11/17/2017 | 11/17/2017 | 11/17/2017 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
DOC - Permit Finaled | 11/17/2017 | 11/17/2017 | 11/17/2017 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 9/25/2017 | 9/26/2017 | 9/26/2017 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Framing/Rough-in | 9/25/2017 | 9/26/2017 | 9/26/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Framing/Rough-in | 9/19/2017 | 9/19/2017 | 9/20/2017 | P | CANC |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Wall Bracing | 8/17/2017 | 8/18/2017 | 8/18/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Wall Bracing | 8/12/2017 | 8/14/2017 | 8/14/2017 | A | FAIL |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman used staples/ plan ref. no staples
|
BLD-Foundation | 6/22/2017 | 6/22/2017 | 6/23/2017 | P | PART |
Jim Storey
|
|
|
Joe Phone #: ###-####
|
BLD-Footing | 6/20/2017 | 6/20/2017 | 6/20/2017 | P | PASS |
Brandon Shaw
|
|
|
James Phone #: ###-####-please verify that the setbacks-neighbor says to close to her property lines-
|
Issue PAID IN FULL permit | | | 6/5/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 5/30/2017 | | |
|
|
|
|
Plan assigned to (LEG) Tisha | 5/19/2017 | | 5/30/2017 | | DONE |
Tisha Gallop
|
|
|
2nd review 5/22 (f/p floor/foundation)
|
Plan resubmittals received | | | 5/30/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/30/2017 | | 5/30/2017 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/30/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/30/2017 | | DONE |
|
|
|
met
|
Routing - Design Review | 5/22/2017 | | 5/23/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLAN CHECK | 5/22/2017 | | 5/22/2017 | | FAIL |
Tisha Gallop
|
|
|
per Troy James new manual J not requried
|
Plan assigned to (DAF) | 4/3/2017 | 4/3/2017 | 5/19/2017 | | DEFR |
David Ferguson
|
|
|
(1st done) due 4/14 - Andrea failed and structural faile due to design change per Planning and wall bracing problems.
deferred to Tisha 5/19/17
|
Plan resubmittals received | | | 5/19/2017 | | DONE |
|
|
|
|
1st review completed | | | 4/19/2017 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 4/3/2017 | | 4/19/2017 | | FAIL |
David Ferguson
|
|
|
|
Routing - MECHANICAL | 4/3/2017 | | 4/5/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 4/3/2017 | 4/6/2017 | 4/4/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (AJS) | 4/3/2017 | 4/3/2017 | 4/3/2017 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/3/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 4/3/2017 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/3/2017 | | DONE |
Christina Prado
|
|
|
|
Routing - Addressing | 4/3/2017 | | 4/3/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/3/2017 | | 4/3/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 3/31/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 31 2017 1:14PM
|