Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD17-00891
StatusFinaled
Name Jeff Treadwell
Site Address 4940 E MILL STATION DR Unit: 104
Project NameWisteria Salon
Customer Number 
ePlanReviewNo
Description
(WISTERIA SALON – SOUTHEAST CORNER OF BUILDING – EXPANSION INTO ADJACENT AREA) This building does not have a fire sprinkler system. To expand an existing beauty salon having a floor area of about 1,400 square feet into an adjacent 525 square foot area. After the expansion, this tenant space will have a total floor area of about 1,925 square feet. Work is to include a new opening in an existing interior nonbearing wall, a new low height chase wall for plumbing, an exhaust fan ducted to the outside, and three hair wash stations. This permit is intended to establish a Certificate of Occupancy for the entire expanded tenant space. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  11/13/2018 DONE
Second Notice 10/22/201811/9/2018 DONE
mailed 11-12
First Notice 9/14/201810/12/2018 DONE
Plan Reviewer's activity  9/4/2018 DONE
Drawings taken to Records
Permanent Occupancy  9/4/2018 DONE
BLD-Final8/31/20189/4/20188/31/2018APASS
DetailsAdele J Schaffeld-Griffin
Angela Phone #: ###-####
FIRE-Final Inspection8/31/20188/31/20188/31/2018PPASS
DetailsTroy Cobbley
Angela Phone #: ###-####
BLD-Conference5/8/20185/9/20185/9/2018APEND
DetailsBrandon Shaw
As per phone conversation with Jeff, framing to continue at a later time
BLD-Aging Inspection5/8/20185/8/20185/8/2018 CANC
DetailsBrandon Shaw
BLD-Aging Inspection5/7/20185/7/20185/8/2018 CANC
DetailsBrandon Shaw
Issue PAID IN FULL permit  6/22/2017 DONE
CHANGE STATUS TO (RDY)  6/21/2017 DONE
need gc form from teneant
Plan resubmittals received  6/20/2017 DONE
received one copy of existing floor plan with plumbing fixtures and letter from tenent explaining two sinks were removed for this scope of work. Routed issue and office set to PW.
Routing - PUBLIC WORKS6/20/2017 6/20/2017 PASS
DetailsRachael Beierle
CHANGE STATUS TO (REV)  6/20/2017 DONE
rerouted to PW
Telephone call  6/6/2017 DONE
customer called-i told him he needed a letter from the parcel owner saying he could pick the dpermit up and the parcel owner needs to fill out the GC form
Route to Impact Fee Review6/2/20176/5/20176/5/2017 PASS
DetailsMarissa Taylor
Review requested for Commercial Permit
Plan assigned to (CJW)4/28/20174/28/20176/5/2017 PASS
DetailsCarl Westfall
(1st done) (May 8 - 7 days) (2 sheets) Wisteria Salon
Routing - PLAN CHECK6/2/2017 6/5/2017 DONE
DetailsCarl Westfall
Routing complete
PLANS/APPL TAKEN TO FRONT DESK  6/5/2017 DONE
Permit Ready to Issue  6/5/2017 DONE
Need GC Form and Revised Cert of Value
Print Occupancy Form  6/5/2017 DONE
Telephone call  6/5/2017 DONE
called Doug-he said they may not be doing project after all but someone will call if they want the permit withdrawn
1st review completed  6/2/2017 PASS
Routing - FIRE5/30/2017 6/2/2017 PASS
DetailsScott Arellano
Approved as shown. One new extinguisher is shown in the new expansion area. No separate plan review comments attached to case.
Routing - PLAN CHECK5/1/2017 5/30/2017 PASS
DetailsCarl Westfall
Approved with attached code notes
Telephone call  5/23/2017 DONE
customer called to see if plans were ready-i told him they needed to go thru plumbing and building plan reviews-he's oidng to do the owrk so i told him we had to have the 302 and a little filled out by the parcel owner and we would also need a 306 form
Routing - MECHANICAL  5/1/2017 PASS
Routing - PLUMBING5/1/2017 5/1/2017 PASS
DetailsBill VanDegrift
Routing - PUBLIC WORKS4/28/2017 5/1/2017 PASS
DetailsMorgan Webb
Routing - Addressing4/28/2017 4/28/2017 PASS
DetailsLaura Hunter
Suite 104
Plans ACCEPTED BY PLAN TECH  4/28/2017 DONE
Intake Approval  4/28/2017 PASS
Recd Pcfee & Taken To Pln CK  4/28/2017 DONE
Application received  4/3/2017 DONE
Application submitted via PDS Online on Apr 3 2017 11:23AM
Intake Approval  4/3/2017 FAIL
DetailsJulie Romig
Application will be routed as a Major TI due to the increase in tenant area. Submit completed Form #520 Checklist and all applicable documents including but not limited to the following items (new application is not needed): 1. Site specific fire flow at hydrants letter. 2. Mechanical plans showing ventilation for nail station (including existing HVAC). 3. Plumbing plans must be stamped and signed by Idaho licensed engineer unless written approval is given by Plumbing/Mechanical inspector. Contact Bill Vandegrift at ###-#### for approval.