Letter of compliance/Occupancy | | | 10/17/2018 | | DONE |
|
|
|
emailed to jlmaybon@gmail.com per request from Highland Homes
|
BLD-Final | 1/29/2018 | 1/29/2018 | 1/29/2018 | P | PASS |
Tony Young
|
|
|
John Phone #: ###-####
|
DOC - Permit Finaled | 1/29/2018 | 1/29/2018 | 1/29/2018 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 1/26/2018 | 1/29/2018 | 1/29/2018 | A | PEND |
Tony Young
|
|
|
John Phone #: ###-####
|
Elevation Cert Rec'd-Final | | | 1/29/2018 | | DONE |
|
|
|
|
BLD-Energy code compliance | 11/9/2017 | 11/9/2017 | 11/10/2017 | P | PASS |
Tony Young
|
|
|
Call about elvation // Curtis Phone #: ###-####,, ok on elevation cert via e-mail
|
BLD-Energy code compliance | 11/3/2017 | 11/6/2017 | 11/6/2017 | A | FAIL |
Tony Young
|
|
|
Curtis Phone #: ###-####,, needs flood plain elevation cert prior to frame approval
|
BLD-Framing/Rough-in | 10/31/2017 | 11/1/2017 | 11/1/2017 | P | PASS |
Brandon Shaw
|
|
|
Curtis Phone #: ###-####
|
Plan Modification Accepted | | | 10/9/2017 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 10/9/2017 | | 10/9/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Footing | 8/7/2017 | 8/8/2017 | 8/8/2017 | A | PASS |
Tony Young
|
|
|
slab grade-curtis Phone #: ###-####
|
BLD-Foundation | 8/2/2017 | 8/3/2017 | 8/3/2017 | A | PASS |
Tony Young
|
|
|
Slab on grade, rigid insulation - Curtis Phone #: ###-####
|
BLD-Energy code compliance | 8/2/2017 | 8/2/2017 | 8/2/2017 | P | PASS |
Tony Young
|
|
|
Slab on grade, rigid insulation - Curtis Phone #: ###-####
|
BLD-Foundation | 7/6/2017 | 7/6/2017 | 7/6/2017 | P | PASS |
Brandon Shaw
|
|
|
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
BLD-Footing | 7/3/2017 | 7/3/2017 | 7/3/2017 | P | PART |
Mike Jordan
|
|
|
Alvaro Phone #: ###-####
|
OVERRIDE | | | 6/5/2017 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/5/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/5/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/5/2017 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Plan assigned to (CDM) | 6/1/2017 | 6/1/2017 | 6/3/2017 | | PASS |
Carl D Madsen
|
|
|
Assigned to DAF resubmittals
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/3/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/24/2017 | | 6/3/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PUBLIC WORKS | 5/20/2017 | | 6/3/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plan assigned to (DAF) | 4/11/2017 | 4/11/2017 | 6/1/2017 | | DEFR |
David Ferguson
|
|
|
(1st done) due 4/24 Need engineering for tall walls and select headers and shear walls.
|
Routing PW Flood Plain | 5/26/2017 | | 5/26/2017 | | PASS |
Jason C. Taylor
|
|
|
NOTE:
Prior to receiving a framing inspection an additional Elevation Certificate based upon actual construction shall be submitted to and approved by the Boise City Public Works Floodplain Coordinator. Jason Taylor ###-####
Prior to recieving Final Occupancy a third elevation certificate based upon actual construction shall be submitted to and approved by the Boise City Public Works Floodplain Coordinator. Jason Taylor ###-####
|
Routing - PLAN CHECK | 5/20/2017 | | 5/23/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Flood Plain | 5/23/2017 | | 5/23/2017 | | FAIL |
Jason C. Taylor
|
|
|
See notes in eplan. JCT
|
Routing PW Flood Plain | 4/25/2017 | | 5/1/2017 | | FAIL |
Jason C. Taylor
|
|
|
see changemarks in eplan. JCT
|
1st review completed | | | 4/25/2017 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 4/11/2017 | | 4/25/2017 | | FAIL |
David Ferguson
|
|
|
|
Route to Impact Fee Review | 4/11/2017 | 4/14/2017 | 4/12/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 4/11/2017 | | 4/12/2017 | | PASS |
Troy James
|
|
|
|
Plan assigned to (AJS) | 4/11/2017 | 4/11/2017 | 4/11/2017 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLANNING | 4/11/2017 | | 4/11/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 4/11/2017 | | 4/11/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/11/2017 | | 4/11/2017 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/11/2017 | | DONE |
|
|
|
|
Intake Approval | | | 4/11/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/11/2017 | | DONE |
|
|
|
|
Intake Approval | | | 4/10/2017 | | FAIL |
|
|
|
Need manual J's, Need the checklist filled out completely. (All blanks are to be filled in with setbacks, sheet numbers etc.) Also each drawing needs to be uploaded individually. Thanks
|
Application received | | | 4/4/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 4 2017 10:11AM
|