Second Notice | | 2/22/2018 | 2/21/2018 | | DONE |
|
|
|
This permit finaled on the web by Cecyle Brock
|
First Notice | | 1/18/2018 | 2/12/2018 | | DONE |
|
|
|
Mailed 2-13-18
|
PubWorks Occupancy Approval | 1/8/2018 | 1/8/2018 | 1/8/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 1/8/2018 | | DONE |
|
|
|
|
BLD-Final | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | PASS |
Jim Storey
|
|
|
Dale Phone #: ###-####
|
FIRE-Final Inspection | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Per fire dept the second gate Opticon is functional.
Dale Phone #: ###-####
|
FIRE-Final Inspection | 12/28/2017 | 12/29/2017 | 12/29/2017 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with Dale Phone #: ###-####, inspection request will be rescheduled for a later date.
|
BLD-Final | 12/28/2017 | 12/29/2017 | 12/29/2017 | P | CANC |
Brandon Shaw
|
|
|
Dale Phone #: ###-####
|
BLD-Final | 12/21/2017 | 12/22/2017 | 12/22/2017 | P | FAIL |
Jim Storey
|
|
|
Dale Phone #: ###-#### need fire sign off
|
FIRE-Final Inspection | 12/21/2017 | 12/22/2017 | 12/22/2017 | P | CANC |
Jim Page
|
|
|
South side gate opticon sensor tested okay with fire department, other gate was still being worked on, fire department was not able to test other sensor. Inspection request will need to be rescheduled when other sesnor can be tested. This inspection request is cancelled.
|
Zoning Approval | 12/18/2017 | 12/18/2017 | 12/18/2017 | | DONE |
Andrea Tuning
|
|
|
|
Temporary Occupancy | 11/22/2017 | 2/20/2018 | 11/22/2017 | | DONE |
Christina Prado
|
|
|
|
Zoning Approval Temp | 11/22/2017 | 11/22/2017 | 11/22/2017 | | DONE |
Andrea Tuning
|
|
|
Bond has been provided for landscaping, paving and street improvements.
|
BLD-Final | 11/14/2017 | 11/15/2017 | 11/15/2017 | P | PART |
Jim Storey
|
|
|
dale Phone #: ###-#### office/lounge only ok for temp.
|
FIRE-Final Inspection | 11/14/2017 | 11/15/2017 | 11/15/2017 | A | PART |
Troy Cobbley
|
|
|
A temp for life safety is ok with Scott until both opticon systems at the two gates have been tested.
dale Phone #: ###-####
|
PubWorks Temp Occupancy Appr | 11/15/2017 | 11/15/2017 | 11/15/2017 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Framing/Rough-in | 9/26/2017 | 9/27/2017 | 9/27/2017 | A | PASS |
Jim Storey
|
|
|
metal framing // Dale Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/15/2017 | 9/18/2017 | 9/18/2017 | A | PASS |
Jim Storey
|
|
|
Dale Phone #: ###-####
|
BLD-Framing/Rough-in | 8/10/2017 | 8/10/2017 | 8/10/2017 | P | PASS |
Jim Storey
|
|
|
Dale Phone #: ###-#### trusses added per plan west of exstining bldg.
|
BLD-Footing | 8/3/2017 | 8/4/2017 | 8/4/2017 | A | PART |
Brandon Shaw
|
|
|
9/10am-Dale Phone #: ###-####
|
BLD-Framing/Rough-in | 8/1/2017 | 8/2/2017 | 8/2/2017 | A | PASS |
Jim Storey
|
|
|
Dale Phone #: ###-#### pending trades
|
BLD-Other | 7/25/2017 | 7/26/2017 | 7/26/2017 | A | PASS |
Jim Storey
|
|
|
Dale-CMU Block Phone #: ###-####cmu and 3 hr wall progrestion of gyp ok to cover
|
BLD-Framing/Rough-in | 7/17/2017 | 7/17/2017 | 7/17/2017 | P | PASS |
Jim Storey
|
|
|
coreboard in attic ok pending 5/8 layers
|
BLD-Framing/Rough-in | 7/17/2017 | 7/17/2017 | 7/17/2017 | P | NH |
Jim Storey
|
|
|
dale Phone #: ###-####no access left message
|
BLD-Footing | 6/28/2017 | 6/29/2017 | 6/29/2017 | A | PART |
Brandon Shaw
|
|
|
Dale Phone #: ###-#### Lower section of inspection pit
|
BLD-Footing | 6/22/2017 | 6/23/2017 | 6/23/2017 | A | PART |
Jim Storey
|
|
|
Dale-rebar Phone #: ###-####wip si on site
|
Print Occupancy Form | | | 6/12/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/12/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/12/2017 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/9/2017 | | DONE |
|
|
|
resubmittals received 2 sheets of # 4 Shear-gave to Brian McGowan
|
OVERRIDE | | | 6/7/2017 | | |
|
|
|
|
Plan assigned to (CDM) | 4/20/2017 | 4/20/2017 | 6/7/2017 | | PASS |
Carl D Madsen
|
|
|
1st Comp. 5/20 Heartland express
|
Routing Off Site - STRUCTURAL | 5/23/2017 | | 6/7/2017 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/7/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/7/2017 | | DONE |
Christina Prado
|
|
|
****only need ACHD We Got the RP, GC & rev cert of val***Need ACHD, RP, GC Form & Revised Certificate of value for issuance
|
Routing - Design Review | 6/6/2017 | | 6/6/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLAN CHECK | 5/23/2017 | | 6/3/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - FIRE | 5/23/2017 | 5/23/2017 | 5/26/2017 | | PASS |
Scott Arellano
|
|
|
Attached plan review report to plans.
|
Routing - Design Review | 5/23/2017 | | 5/24/2017 | | FAIL |
Andrea Tuning
|
|
|
Install terminal planters at the terminus of all parkign rows. Provide the required Class II tree and groundcover within each of the terminal planters.
Bicycle parking shall not be located within a parking stall. The applicant may extend the planter island and concrete into this area as long as it is protected and will not become vehicular parking in the future.
|
Route to Impact Fee Review | 5/20/2017 | 5/23/2017 | 5/22/2017 | | PASS |
Marissa Taylor
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 5/20/2017 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 4/20/2017 | | 5/20/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Drainage | 4/20/2017 | | 5/11/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing Off Site - STRUCTURAL | 4/20/2017 | | 5/3/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Telephone call | | | 4/27/2017 | | DONE |
Scott Arellano
|
|
|
Spoke with Architect, Brian Ellsworth. Discussed requirements for the required Opticom system at the north access gate and manual access at the south gate for the purpose of accessing the nearest available fire hydrant.
|
Routing PW Environmental | 4/20/2017 | | 4/26/2017 | | PASS |
Rick Christenson
|
|
|
Per no maintenance in inspection bay. If maintenance will be performed interceptor SO-2 needs to be a Flammable Liquids approved interceptor.
|
Routing - FIRE | 4/20/2017 | 4/20/2017 | 4/25/2017 | | FAIL |
Scott Arellano
|
|
|
Attached report to csae. Emailed plan review comments to architect.
|
Routing - Erosion and Sediment | 4/20/2017 | | 4/24/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan narrative and site map approved. Will need to designate RP upon contract reward. Site preparation inspection required.
|
Routing - MECHANICAL | 4/20/2017 | | 4/24/2017 | | PASS |
Troy James
|
|
|
approved with redlines
|
Routing - PLANNING | 4/20/2017 | | 4/24/2017 | | PASS |
Cody Riddle
|
|
|
Approved by DR. No review required.
|
Routing - PLANNING Land Div | 4/20/2017 | | 4/20/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 4/20/2017 | | 4/20/2017 | | PASS |
Laura Hunter
|
|
|
Correct address to 4125 S Eagleson Rd
|
Routing - PUBLIC WORKS | 4/20/2017 | | 4/20/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 4/20/2017 | | 4/20/2017 | | FAIL |
Andrea Tuning
|
|
|
|
Routing - PLUMBING | 4/20/2017 | | 4/20/2017 | | PASS |
Bill VanDegrift
|
|
|
Page P-1.0
1) vent interceptor tank not the piping upstream
2) 3" vent required downstream of the interceptor and vent through the roof individually.
3) floor plan shows a sink in the breakroon by the water heater area.
|
Intake Approval | | | 4/20/2017 | | PASS |
|
|
|
|
Intake Approval | | | 4/6/2017 | | FAIL |
Javier Guzman
|
|
|
Please provide the following and upload or revise:
1. Please upload an Erosion & Sediment Control (ESC) Narrative. Narrative must be designed for the specific project, and be prepared and signed by a plan designer certified by Boise City. (you stated deferred submission which is not allowed for ESC plans, ESC plans shall be submitted)
2. Please sign and date the Building envelope COMcheck analysis
3. Please upload the engineered building file named “Sealed Permit Drawings” that were uploaded in the small documents and upload them into the drawings file individually not as a packet. (please refer to ePlan submittals standards for other upload requirements found at http://pds.cityofboise.org/media/105041/electronicstandards.pdf)
4. Please upload the engineered building file named “Truck Wash Shop” that were uploaded in the small documents and upload them into the drawings file individually not as a packet. (please refer to ePlan submittals standards for other upload requirements found at http://pds.cityofboise.org/media/105041/electronicstandards.pdf)
|
Application received | | | 4/5/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 5 2017 2:13PM
|