Permit Information
Permit NumberBLD17-00926
StatusFinaled
Name EKC INC
Site Address 4125 S EAGLESON RD
Project NameHeartland Express
Customer Number 
ePlanReviewYes
Description
(HEARTLAND EXPRESS) Permit for the construction of a 4,639 sq. ft. addition to an existing 5,636 sq. ft. building. Work consists of new pre-engineered addition which will house an inspection pit and wash bay. Project includes demolition of an existing out building,a new site approach and new paving. The existing interior at the truck drivers lounge and office area will be remodeled as well. This building is not fire sprinklered. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 2/22/20182/21/2018 DONE
This permit finaled on the web by Cecyle Brock
First Notice 1/18/20182/12/2018 DONE
Mailed 2-13-18
PubWorks Occupancy Approval1/8/20181/8/20181/8/2018 DONE
DetailsTiffany Lowery
Permanent Occupancy  1/8/2018 DONE
BLD-Final1/3/20181/4/20181/4/2018APASS
DetailsJim Storey
Dale Phone #: ###-####
FIRE-Final Inspection1/3/20181/4/20181/4/2018APASS
DetailsTroy Cobbley
Life safety passed. Per fire dept the second gate Opticon is functional.

Dale Phone #: ###-####
FIRE-Final Inspection12/28/201712/29/201712/29/2017PCANC
DetailsJim Page
Inspection request cancelled per conversation with Dale Phone #: ###-####, inspection request will be rescheduled for a later date.
BLD-Final12/28/201712/29/201712/29/2017PCANC
DetailsBrandon Shaw
Dale Phone #: ###-####
BLD-Final12/21/201712/22/201712/22/2017PFAIL
DetailsJim Storey
Dale Phone #: ###-#### need fire sign off
FIRE-Final Inspection12/21/201712/22/201712/22/2017PCANC
DetailsJim Page
South side gate opticon sensor tested okay with fire department, other gate was still being worked on, fire department was not able to test other sensor. Inspection request will need to be rescheduled when other sesnor can be tested. This inspection request is cancelled.
Zoning Approval12/18/201712/18/201712/18/2017 DONE
DetailsAndrea Tuning
Temporary Occupancy11/22/20172/20/201811/22/2017 DONE
DetailsChristina Prado
Zoning Approval Temp11/22/201711/22/201711/22/2017 DONE
DetailsAndrea Tuning
Bond has been provided for landscaping, paving and street improvements.
BLD-Final11/14/201711/15/201711/15/2017PPART
DetailsJim Storey
dale Phone #: ###-#### office/lounge only ok for temp.
FIRE-Final Inspection11/14/201711/15/201711/15/2017APART
DetailsTroy Cobbley
A temp for life safety is ok with Scott until both opticon systems at the two gates have been tested.

dale Phone #: ###-####
PubWorks Temp Occupancy Appr11/15/201711/15/201711/15/2017 DONE
DetailsTiffany Lowery
BLD-Framing/Rough-in9/26/20179/27/20179/27/2017APASS
DetailsJim Storey
metal framing // Dale Phone #: ###-####
BLD-Ceiling Grid Inspection9/15/20179/18/20179/18/2017APASS
DetailsJim Storey
Dale Phone #: ###-####
BLD-Framing/Rough-in8/10/20178/10/20178/10/2017PPASS
DetailsJim Storey
Dale Phone #: ###-#### trusses added per plan west of exstining bldg.
BLD-Footing8/3/20178/4/20178/4/2017APART
DetailsBrandon Shaw
9/10am-Dale Phone #: ###-####
BLD-Framing/Rough-in8/1/20178/2/20178/2/2017APASS
DetailsJim Storey
Dale Phone #: ###-#### pending trades
BLD-Other7/25/20177/26/20177/26/2017APASS
DetailsJim Storey
Dale-CMU Block Phone #: ###-####cmu and 3 hr wall progrestion of gyp ok to cover
BLD-Framing/Rough-in7/17/20177/17/20177/17/2017PPASS
DetailsJim Storey
coreboard in attic ok pending 5/8 layers
BLD-Framing/Rough-in7/17/20177/17/20177/17/2017PNH
DetailsJim Storey
dale Phone #: ###-####no access left message
BLD-Footing6/28/20176/29/20176/29/2017APART
DetailsBrandon Shaw
Dale Phone #: ###-####
Lower section of inspection pit
BLD-Footing6/22/20176/23/20176/23/2017APART
DetailsJim Storey
Dale-rebar Phone #: ###-####wip si on site
Print Occupancy Form  6/12/2017 DONE
Issue PAID IN FULL permit  6/12/2017 DONE
(F) Reprint permit  6/12/2017 DONE
Plan resubmittals received  6/9/2017 DONE
resubmittals received 2 sheets of # 4 Shear-gave to Brian McGowan
OVERRIDE  6/7/2017  
Plan assigned to (CDM)4/20/20174/20/20176/7/2017 PASS
DetailsCarl D Madsen
1st Comp. 5/20 Heartland express
Routing Off Site - STRUCTURAL5/23/2017 6/7/2017 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  6/7/2017 DONE
Permit Ready to Issue  6/7/2017 DONE
DetailsChristina Prado
****only need ACHD We Got the RP, GC & rev cert of val***Need ACHD, RP, GC Form & Revised Certificate of value for issuance
Routing - Design Review6/6/2017 6/6/2017 PASS
DetailsAndrea Tuning
Routing - PLAN CHECK5/23/2017 6/3/2017 PASS
DetailsCarl D Madsen
Routing - FIRE5/23/20175/23/20175/26/2017 PASS
DetailsScott Arellano
Attached plan review report to plans.
Routing - Design Review5/23/2017 5/24/2017 FAIL
DetailsAndrea Tuning
Install terminal planters at the terminus of all parkign rows. Provide the required Class II tree and groundcover within each of the terminal planters.

Bicycle parking shall not be located within a parking stall. The applicant may extend the planter island and concrete into this area as long as it is protected and will not become vehicular parking in the future.
Route to Impact Fee Review5/20/20175/23/20175/22/2017 PASS
DetailsMarissa Taylor
Review requested for Commercial Permit
1st review completed  5/20/2017 FAIL
Routing - PLAN CHECK4/20/2017 5/20/2017 FAIL
DetailsCarl D Madsen
Routing PW Drainage4/20/2017 5/11/2017 PASS
DetailsBrian Murphy
Routing Off Site - STRUCTURAL4/20/2017 5/3/2017 FAIL
DetailsCarl D Madsen
Telephone call  4/27/2017 DONE
DetailsScott Arellano
Spoke with Architect, Brian Ellsworth. Discussed requirements for the required Opticom system at the north access gate and manual access at the south gate for the purpose of accessing the nearest available fire hydrant.
Routing PW Environmental4/20/2017 4/26/2017 PASS
DetailsRick Christenson
Per no maintenance in inspection bay. If maintenance will be performed interceptor SO-2 needs to be a Flammable Liquids approved interceptor.
Routing - FIRE4/20/20174/20/20174/25/2017 FAIL
DetailsScott Arellano
Attached report to csae. Emailed plan review comments to architect.
Routing - Erosion and Sediment4/20/2017 4/24/2017 PASS
DetailsAndy J. Long
ESC plan narrative and site map approved. Will need to designate RP upon contract reward. Site preparation inspection required.
Routing - MECHANICAL4/20/2017 4/24/2017 PASS
DetailsTroy James
approved with redlines
Routing - PLANNING4/20/2017 4/24/2017 PASS
DetailsCody Riddle
Approved by DR. No review required.
Routing - PLANNING Land Div4/20/2017 4/20/2017 PASS
DetailsTodd Tucker
Routing - Addressing4/20/2017 4/20/2017 PASS
DetailsLaura Hunter
Correct address to 4125 S Eagleson Rd
Routing - PUBLIC WORKS4/20/2017 4/20/2017 PASS
DetailsRachael Beierle
Routing - Design Review4/20/2017 4/20/2017 FAIL
DetailsAndrea Tuning
Routing - PLUMBING4/20/2017 4/20/2017 PASS
DetailsBill VanDegrift
Page P-1.0
1) vent interceptor tank not the piping upstream
2) 3" vent required downstream of the interceptor and vent through the roof individually.
3) floor plan shows a sink in the breakroon by the water heater area.
Intake Approval  4/20/2017 PASS
Intake Approval  4/6/2017 FAIL
DetailsJavier Guzman
Please provide the following and upload or revise:
1. Please upload an Erosion & Sediment Control (ESC) Narrative. Narrative must be designed for the specific project, and be prepared and signed by a plan designer certified by Boise City. (you stated deferred submission which is not allowed for ESC plans, ESC plans shall be submitted)
2. Please sign and date the Building envelope COMcheck analysis
3. Please upload the engineered building file named “Sealed Permit Drawings” that were uploaded in the small documents and upload them into the drawings file individually not as a packet. (please refer to ePlan submittals standards for other upload requirements found at http://pds.cityofboise.org/media/105041/electronicstandards.pdf)
4. Please upload the engineered building file named “Truck Wash Shop” that were uploaded in the small documents and upload them into the drawings file individually not as a packet. (please refer to ePlan submittals standards for other upload requirements found at http://pds.cityofboise.org/media/105041/electronicstandards.pdf)
Application received  4/5/2017 DONE
Application submitted via PDS Online on Apr 5 2017 2:13PM