BLD-Final | 6/7/2019 | 6/10/2019 | 6/10/2019 | A | PASS |
Mike Jordan
|
|
|
Call when you head this way. Phone #: ###-#### Inspection requested via web by Bob Thornton. All issues resolved. OK for perm occ.
|
DOC - Permit Finaled | | | 6/10/2019 | | DONE |
|
|
|
final passed 6-10-19
|
Letter of compliance/Occupancy | | | 6/10/2019 | | DONE |
|
|
|
|
BLD-Final | 5/9/2019 | 5/10/2019 | 5/10/2019 | A | PART |
Mike Jordan
|
|
|
Call when you head this way. Phone #: ###-#### Inspection requested via web by Bob Thornton. Ok for temp occ. Needs tempered glazing on side light and provide toilet flusher on turning side.
|
FIRE-Final Inspection | 5/9/2019 | 5/9/2019 | 5/9/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.. Exit signs have been replaced. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
FIRE-Final Inspection | 5/1/2019 | 5/2/2019 | 5/2/2019 | A | FAIL |
Troy Cobbley
|
|
|
Repair the exit signs and provide the exit discharge light as per plans. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Framing/Rough-in | 2/5/2019 | 2/6/2019 | 2/6/2019 | A | PASS |
Mike Jordan
|
|
|
Bob Phone #: ###-####-please call when on way. LVL header or new opening.
|
BLD-Framing/Rough-in | 1/10/2019 | 1/10/2019 | 1/10/2019 | P | PASS |
Mike Jordan
|
|
|
Bob Phone #: ###-####. Interior steel stud and wood framed walls, lintels and headers mercedes recieing area.
|
CHANGE STATUS TO (ISS) | | | 11/2/2018 | | DONE |
|
|
|
plan mod
|
Inspection Record Card- Bld | | | 11/2/2018 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 7/19/2018 | 7/20/2018 | 7/20/2018 | A | PASS |
Mike Jordan
|
|
|
Bob Phone #: ###-####. Interior steel stud framed walls and hardlids ok at service lounge/service writers area.
|
OVERRIDE | | | 7/20/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 7/20/2018 | | DONE |
|
|
|
PLAN MOD
|
Routing - FIRE | 7/13/2018 | 7/13/2018 | 7/19/2018 | | PASS |
Erika Akin
|
|
|
Attached revised plan mod comments
|
Plan assigned to (JAR) | 6/14/2018 | 6/14/2018 | 7/19/2018 | | DONE |
Julie Romig
|
|
|
07/19 - 2nd Rev - 1st Rev Comp - Plan mod - Lyle Pearson
|
Routing - PLAN CHECK | 7/13/2018 | | 7/17/2018 | | PASS |
Julie Romig
|
|
|
|
Routing - Design Review | 7/13/2018 | | 7/16/2018 | | PASS |
Katelyn Menuge
|
|
|
DRH18-00298
|
Routing - FIRE | 6/22/2018 | 6/22/2018 | 6/28/2018 | | FAIL |
Erika Akin
|
|
|
Attached review to case and emailed architect
|
Routing - PLAN CHECK | 6/22/2018 | | 6/28/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 6/22/2018 | | 6/25/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 6/22/2018 | | 6/25/2018 | | PASS |
Bill VanDegrift
|
|
|
no review required
|
Routing - Design Review | 6/22/2018 | | 6/22/2018 | | FAIL |
Katelyn Menuge
|
|
|
Changes to what was approved through Design Review require a modification of DRH16-00388. Please submit a new Design Review application to process the modifications.
|
Routing - PUBLIC WORKS | 6/22/2018 | | 6/22/2018 | | PASS |
Morgan Webb
|
|
|
|
Plan Modification Accepted | | | 6/14/2018 | | DONE |
|
|
|
plan mod accepted in e plan-changes to new wiring#104, retain existing strips by office #103, relocated windows in #4, new door #115, new HM window #119 & nbew doors #109/108-new sheets submitted A1.10, A1.1, A1.2, A1.3, A3.0, A4.0, A5.0, A5.1, A7.0, P8.0 (?), E1.0, E1.2, E1.3, M2.1 & M(?)2.2-assigned to JAR
|
BLD-Footing | 4/27/2018 | 4/30/2018 | 4/30/2018 | P | PASS |
Mike Jordan
|
|
|
Late afternoon please. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Footing | 4/26/2018 | 4/27/2018 | 4/27/2018 | A | CANC |
Mike Jordan
|
|
|
MTI epoxy bolt at 8:00 am. Concrete is scheduled for noon. Phone #: ###-#### >> Inspection requested via web by Bob Thornton Inspection cancelled from web by: Bob Thornton
|
BLD-Foundation | 4/24/2018 | 4/25/2018 | 4/25/2018 | A | PASS |
Mike Jordan
|
|
|
Pour foundation wall at 10:00 am Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Footing | 4/24/2018 | 4/24/2018 | 4/24/2018 | P | PASS |
Mike Jordan
|
|
|
Plans indicate no inspection required. Is that correct? Phone #: ###-#### Inspection requested via web by Bob Thornton
|
Issue PAID IN FULL permit | | | 4/12/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/12/2018 | | DONE |
|
|
|
|
Extend Review Timeline | | | 4/4/2018 | | DONE |
|
|
|
Final Approved 180 day extension per Adele. See documents
|
Expiration Notice | 3/26/2018 | 4/16/2018 | 3/26/2018 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 3/20/2018 | | |
|
|
|
|
Routing - FIRE | 3/15/2018 | 3/15/2018 | 3/20/2018 | | PASS |
Scott Arellano
|
|
|
90 Min Fire Door added to plan sheet A1.1
|
Plan assigned to (JAR) | 4/14/2017 | 4/14/2017 | 3/20/2018 | | DONE |
Julie Romig
|
|
|
**1st Rev Comp - 4th Rev Rec'd 03/15 - L3 Lyle Pearson Mercedes Remodel
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2018 | | DONE |
|
|
|
|
Telephone call | | | 3/20/2018 | | DONE |
|
|
|
NEED
RP
GC FORM
REVISED VALUE
|
Permit Ready to Issue | | | 3/20/2018 | | DONE |
Christina Prado
|
|
|
all have been met-NEED
RP - met
GC FORM - met
REVISED VALUE - met
|
Routing - PLAN CHECK | 3/15/2018 | | 3/20/2018 | | PASS |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 2/16/2018 | | 2/28/2018 | | FAIL |
Julie Romig
|
|
|
3rd Review
|
Routing - FIRE | 2/16/2018 | 2/16/2018 | 2/26/2018 | | PASS |
Scott Arellano
|
|
|
Attached revised comments to case
|
Extend Review Timeline | | | 11/17/2017 | | DONE |
|
|
|
1st Approved 180 day extension per Adele. See documents
|
Routing - PLAN CHECK | 8/15/2017 | | 8/15/2017 | | FAIL |
Julie Romig
|
|
|
See ePlanReview for Corrections. Changemark report sent to Damon Beard.
|
Routing - FIRE | 8/11/2017 | 8/11/2017 | 8/11/2017 | | FAIL |
Scott Arellano
|
|
|
Emailed architect updated Fire Plan Review report comments. Outstanding issue of Fire Flow deficiency has not been remedied.
|
Route to Impact Fee Review | 5/20/2017 | 5/23/2017 | 5/22/2017 | | PASS |
Marissa Taylor
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 5/20/2017 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 4/14/2017 | | 5/20/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 4/14/2017 | | 5/12/2017 | | PASS |
Julie Romig
|
|
|
Approved per ePlanReview
|
Routing - FIRE | 4/14/2017 | 4/14/2017 | 4/20/2017 | | FAIL |
Scott Arellano
|
|
|
Emailed architect plan review report. Attached report to case.
|
Routing PW Drainage | 4/17/2017 | | 4/20/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 4/14/2017 | | 4/20/2017 | | PASS |
Sarah Schafer
|
|
|
Approver per DRH16-00388
|
Routing - Erosion and Sediment | 4/14/2017 | | 4/18/2017 | | PASS |
Melissa Jannusch
|
|
|
Waiver approved
|
Routing - MECHANICAL | 4/14/2017 | | 4/17/2017 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 4/14/2017 | | 4/17/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/14/2017 | | 4/17/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 4/14/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Pre screen passed Carl M, fees verified
|
Application received | | | 4/7/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 7 2017 8:25AM
|
Intake Approval | | | 4/7/2017 | | FAIL |
|
|
|
4/7/17 Carl Madsen
Please provide the following items.
1. A minimum of a ESC waiver letter or an ESC plan is required to be submitted.
2. There are exterior modifications being made to the building please provide a site plan and plan clearly designating Fire department access roadways, hydrants etc.
3. the code sheet indicates fire wall but the floor plan indicated a fire barrier. Please show consistency between the sheets.
4. It appears that the are of work is taking a previously unenclosed area and enclosing it with new walls and glazing. Please provide an envelope compliance form or provide a prescriptive list for energy compliance.
|