CHANGE STATUS TO (ISS) | | | 6/20/2017 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (JAR) | 5/19/2017 | 5/19/2017 | 6/19/2017 | | DONE |
Julie Romig
|
|
|
06/16 - Plan Mod - Cancer Center of Idaho ePlan
|
Routing - PLAN CHECK | 5/26/2017 | | 6/19/2017 | | PASS |
Julie Romig
|
|
|
Plan Modification Resubmit
|
Permit Ready to Issue | | | 6/19/2017 | | DONE |
|
|
|
do not re-issue
|
Routing PW Environmental | | | 5/24/2017 | | PASS |
Rick Christenson
|
|
|
REPLACING CT MACHINE
|
Routing - PLAN CHECK | 5/24/2017 | | 5/24/2017 | | FAIL |
Julie Romig
|
|
|
Plan Mod - Need revised drawings showing both original plans and plan modifications on same sheet.
|
Routing - PUBLIC WORKS | 5/22/2017 | | 5/23/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plan Modification Accepted | | | 5/19/2017 | | DONE |
|
|
|
Remove and replace existing CT machine with a newer model
|
BLD-Other | 5/5/2017 | 5/8/2017 | 5/8/2017 | A | PASS |
Mike Jordan
|
|
|
Rebar inspection - Joe Phone #: ###-####. Reinforcement in slab ok.
|
Issue PAID IN FULL permit | | | 4/25/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/25/2017 | | DONE |
|
|
|
|
Telephone call | | | 4/24/2017 | | DONE |
|
|
|
called Katie to see if she wanted us to send her the permit to sign and she could send back-she said someone is coming in to pick it up
|
Route to Impact Fee Review | 4/18/2017 | 4/21/2017 | 4/19/2017 | | PASS |
Tonya Wallace
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 4/19/2017 | | |
Christina Prado
|
|
|
**MET BLH 4-24-17** Need GC Form & Revised Certificate of Value for issuance
|
Plan assigned to (JAR) | 4/12/2017 | 4/12/2017 | 4/18/2017 | | DONE |
Julie Romig
|
|
|
1st Review Complete. DUE 04/18 - L1 Cancer Center of Idaho ePlan
|
Routing - PLAN CHECK | 4/12/2017 | | 4/18/2017 | | PASS |
Julie Romig
|
|
|
|
1st review completed | | | 4/18/2017 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/18/2017 | | DONE |
|
|
|
|
Routing PW Environmental | 4/12/2017 | | 4/14/2017 | | PASS |
Rick Christenson
|
|
|
|
Intake Approval | | | 4/12/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 4/12/2017 | | 4/12/2017 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 4/12/2017 | | 4/12/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/12/2017 | | 4/12/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 4/8/2017 | | FAIL |
Julie Romig
|
|
|
Need Mechanical compliance COMcheck for new heating/cooling unit
Need heating and cooling load calculations for new heating/cooling unit
|
Application received | | | 4/7/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 7 2017 9:38AM
|