PubWorks Occupancy Approval | 2/13/2020 | 2/13/2020 | 2/13/2020 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 8/23/2019 | | DONE |
|
|
|
|
BLD-Final | 8/22/2019 | 8/22/2019 | 8/22/2019 | P | PASS |
Brandon Shaw
|
|
|
John Phone #: ###-####
|
DOC - Permit Finaled | 8/22/2019 | 8/22/2019 | 8/22/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 8/16/2019 | 8/16/2019 | 8/19/2019 | P | PEND |
Dave Hannah
|
|
|
John Phone #: ###-#### needs returns on hand rails
|
PubWorks Temp Occupancy Appr | 6/4/2019 | 6/4/2019 | 6/4/2019 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 5/30/2019 | 5/30/2019 | 5/30/2019 | | PASS |
Katelyn Menuge
|
|
|
|
FIRE-Final Inspection | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are in placed and will be inspected as discussed. Final life fire safety inspection complete.
John Phone #: ###-####
|
Print Occupancy Form | | | 3/25/2019 | | DONE |
|
|
|
|
BLD-Energy code compliance | 8/9/2018 | 8/9/2018 | 8/9/2018 | P | PASS |
Dave Hannah
|
|
|
John-1st and 2nd floor Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 8/8/2018 | | DONE |
|
|
|
Plan Mod
|
OVERRIDE | | | 8/7/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 7/23/2018 | 7/23/2018 | 8/7/2018 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - Plan Mod #3 Warm Springs - add hose bibb & drain
|
Routing - PLAN CHECK | 8/2/2018 | | 8/7/2018 | | PASS |
Julie Romig
|
|
|
|
Permit Ready to Issue | | | 8/7/2018 | | DONE |
|
|
|
Plan Mod approved
DO NOT REISSUE
(Change this permit and BLD17-02955 to issued status once plan mod fee have been paid)
|
Routing - PLUMBING | 8/6/2018 | | 8/6/2018 | | PASS |
Bill VanDegrift
|
|
|
Public works has approved the floor drain location.
|
Routing - PUBLIC WORKS | 8/2/2018 | | 8/2/2018 | | PASS |
Morgan Webb
|
|
|
PROVIDED HINGED GRATE AND VANDAL PROOF SCREWS FOR FLOOR DRAIN
|
Routing - PLAN CHECK | 7/23/2018 | | 7/31/2018 | | FAIL |
Julie Romig
|
|
|
Plan Mod #3 pending approval by plumbing and public works.
|
BLD-Energy code compliance | 7/30/2018 | 7/30/2018 | 7/30/2018 | P | PASS |
Dave Hannah
|
|
|
3rd Floor // John Phone #: ###-####
|
Routing - PUBLIC WORKS | 7/30/2018 | | 7/30/2018 | | FAIL |
Morgan Webb
|
|
|
FLOOR DRAIN UNCOVERED.
|
Routing PW Drainage | 7/30/2018 | | 7/30/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLUMBING | 7/23/2018 | | 7/27/2018 | | FAIL |
Bill VanDegrift
|
|
|
public works requires exterior floor drains to be covered.
|
BLD-Framing/Rough-in | 7/24/2018 | 7/24/2018 | 7/24/2018 | P | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Energy code compliance | 7/24/2018 | 7/24/2018 | 7/24/2018 | P | PART |
Dave Hannah
|
|
|
air seal ok
|
Plan Modification Accepted | | | 7/23/2018 | | DONE |
|
|
|
Plan Mod #3 - Add hose bibb & drain
|
CHANGE STATUS TO (ISS) | | | 6/26/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/26/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 6/20/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 6/12/2018 | 6/12/2018 | 6/20/2018 | | DONE |
Julie Romig
|
|
|
Plan mod
|
Routing - PLAN CHECK | 6/18/2018 | | 6/20/2018 | | PASS |
Julie Romig
|
|
|
Plan Mod 2
|
Permit Ready to Issue | | | 6/20/2018 | | DONE |
|
|
|
Plan Mod please do not re issue 2 permits also see BLD17-02955
need
rev cert of val
|
Routing - Design Review | 6/18/2018 | | 6/18/2018 | | PASS |
Katelyn Menuge
|
|
|
Light changes okay.
|
Routing - MECHANICAL | 6/18/2018 | | 6/18/2018 | | PASS |
Troy James
|
|
|
New mechanical engineered drawings.
|
Plan Modification Accepted | | | 6/12/2018 | | DONE |
|
|
|
Plan mod workflow started to revise HVAC, remove exterior lights and switch at bedroom false balconies levels 2 & 3, revise landscape plan to remove lawn, add plants & specify xeroscape drip irrigation.
|
BLD-Footing | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####--footings for parking lot
|
BLD-Wall Bracing | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | PART |
Jim Sly
|
|
|
shear- John Phone #: ###-#### Holdowns from foundation......and Holdowns ....1st story center shear wall thru floor to 2nd story center shear wall OK (North and South ends).
|
BLD-Wall Bracing | 5/17/2018 | 5/17/2018 | 5/17/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Wall Bracing | 5/17/2018 | 5/17/2018 | 5/17/2018 | P | PASS |
Brandon Shaw
|
|
|
John Phone #: ###-####
|
BLD-Wall Bracing | 4/13/2018 | 4/13/2018 | 4/16/2018 | P | NR |
Dave Hannah
|
|
|
John Phone #: ###-####
|
Print Occupancy Form | | | 4/13/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/13/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/13/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 3/26/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 3/5/2018 | 3/5/2018 | 3/26/2018 | | DONE |
Julie Romig
|
|
|
**Plan Mod - 1st Rev Comp 2nd Rec'd 3/23 - Warm Springs Bldg A
|
Permit Ready to Issue | | | 3/26/2018 | | DONE |
|
|
|
DO NOT REISSUE - Plan mod fees due
|
Routing - Design Review | 3/23/2018 | | 3/23/2018 | | PASS |
Katelyn Menuge
|
|
|
Plan Mod - 2nd Review
|
Routing - PLAN CHECK | 3/23/2018 | | 3/23/2018 | | PASS |
Julie Romig
|
|
|
Plan Mod - 2nd Review
|
Routing - PLAN CHECK | 3/7/2018 | | 3/22/2018 | | FAIL |
Julie Romig
|
|
|
Plan Mod
|
Routing - Design Review | 3/7/2018 | | 3/20/2018 | | FAIL |
Katelyn Menuge
|
|
|
Plan Mod-Submitting updated elevations
|
Plan Modification Accepted | | | 3/5/2018 | | DONE |
Christina Prado
|
|
|
Plan Mod to remove windows at stairwell, add motion switches, replace metal band with stucco, revise roof insulation and add attic ventilation
|
BLD-Footing | 1/22/2018 | 1/22/2018 | 1/22/2018 | P | PASS |
Dave Hannah
|
|
|
Interior footings - John Phone #: ###-####
|
BLD-Foundation | 11/8/2017 | 11/9/2017 | 11/9/2017 | A | PASS |
Dave Hannah
|
|
|
John-pour time 1:00 Phone #: ###-####
|
BLD-Footing | 11/1/2017 | 11/2/2017 | 11/2/2017 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/30/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/30/2017 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 8/24/2017 | | |
|
|
|
|
Plan assigned to (JAR) | 4/14/2017 | 4/14/2017 | 8/24/2017 | | DONE |
Julie Romig
|
|
|
**1st Review Comp - 3rd Review Comp - 506 Warm Springs Apts
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/24/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/24/2017 | | DONE |
Christina Prado
|
|
|
Need:
ACHD - MET
RP
GC Form - MET
Revised Certificate of Value - MET
DO NOT ISSUE WITHOUT BLD17-02955 & BLD17-02956
|
Routing - PLAN CHECK | 8/21/2017 | | 8/21/2017 | | PASS |
Julie Romig
|
|
|
Plan Review #4
|
Routing Off Site - STRUCTURAL | 8/14/2017 | | 8/18/2017 | | PASS |
Julie Romig
|
|
|
Pass per ePlanReview
|
Routing - PLAN CHECK | 8/8/2017 | | 8/18/2017 | | FAIL |
Julie Romig
|
|
|
Plan Review report emailed to Architect.
|
Routing PW Street Lights | 8/9/2017 | | 8/17/2017 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 8/9/2017 | | 8/10/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing Off Site - STRUCTURAL | 8/8/2017 | | 8/10/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 8/9/2017 | | 8/9/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 8/9/2017 | | 8/9/2017 | | PASS |
Bill VanDegrift
|
|
|
perplans and ISPC
|
Routing - PUBLIC WORKS | 8/9/2017 | | 8/9/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Drainage | 8/9/2017 | | 8/9/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 7/24/2017 | | 8/3/2017 | | FAIL |
Julie Romig
|
|
|
See attached plan review report.
|
Routing PW Drainage | 7/24/2017 | | 8/3/2017 | | FAIL |
Brian Murphy
|
|
|
NEED INFILTRATION SWALE LABELED BIORETENTION
|
Routing Off Site - STRUCTURAL | 7/24/2017 | | 8/1/2017 | | FAIL |
Julie Romig
|
|
|
Corrections required per ePlanReview.
|
Routing PW Sewer Design | 7/24/2017 | | 7/28/2017 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Sewer service does not exist at this location. Tap sewer main in Goodman Street with a type "D" connection and install 4" PVC service line at 2% minimum slope. Call Boise Public Works 48 hours prior to construction to obtain tap permit and schedule inspection. Abandon unused sewer service at the main with watertight plug. Obtain plug permit from Boise Public Works at least 48 hours prior to performing work.
|
Routing - FIRE | 7/24/2017 | 7/24/2017 | 7/26/2017 | | PASS |
Scott Arellano
|
|
|
Attached revised comments to plans.
|
Routing PW Street Lights | 7/24/2017 | | 7/25/2017 | | FAIL |
Tom Marshall
|
|
|
|
Routing - Design Review | 7/24/2017 | | 7/24/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLUMBING | 7/24/2017 | | 7/24/2017 | | PASS |
Bill VanDegrift
|
|
|
1) Provide suds relief as required by ISPC 711.0
2) Provide building service protection as required by Suez water.
|
Routing - PUBLIC WORKS | 7/24/2017 | | 7/24/2017 | | PASS |
Rachael Beierle
|
|
|
|
Route to Impact Fee Review | 6/23/2017 | 6/26/2017 | 7/5/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 6/23/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 4/14/2017 | | 6/23/2017 | | FAIL |
Julie Romig
|
|
|
Plan review report emailed to Architect and uploaded to ePlanReview.
|
Routing Off Site - STRUCTURAL | 4/14/2017 | | 6/22/2017 | | FAIL |
Julie Romig
|
|
|
See list of structural comments in ePlanReview Agency Comments Folder.
|
Routing PW Drainage | 4/17/2017 | | 5/5/2017 | | FAIL |
Brian Murphy
|
|
|
apdx j ,depth to groundwaterBIORETENTION NOT INFILTRATION ON SWALES
|
Routing - FIRE | 4/14/2017 | 4/14/2017 | 4/21/2017 | | FAIL |
Scott Arellano
|
|
|
Emailed correction items to architect. Attached plan review report to case.
|
Telephone call | | | 4/20/2017 | | DONE |
|
|
|
Spoke with the architect. Previous approval for builidng design and aerial access roadway has been discussed with the Fire Marshal. I will contact the assistant Fire Marshal for confirmation of alternate approval.
|
Routing PW Solid Waste | 4/17/2017 | | 4/18/2017 | | PASS |
Evan Carpenter
|
|
|
Solid waste is OK as planned.
|
Routing - Erosion and Sediment | 4/14/2017 | | 4/18/2017 | | PASS |
Andy J. Long
|
|
|
|
Routing - PLUMBING | 4/14/2017 | | 4/18/2017 | | FAIL |
Bill VanDegrift
|
|
|
1) provide a site plan showing the sewer and water services to the locations on the plumbing design.
2) provide Suez Water required service protection.
|
Routing - MECHANICAL | 4/14/2017 | | 4/17/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING Land Div | 4/14/2017 | | 4/17/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 4/14/2017 | | 4/17/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/14/2017 | | 4/17/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Street Lights | 4/17/2017 | | 4/17/2017 | | FAIL |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 4/17/2017 | | 4/17/2017 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Include connection to public sewer in permit submittal. Utilize existing sewer services to the property if possible.
|
Routing - PLANNING | 4/14/2017 | | 4/14/2017 | | PASS |
Susan Riggs
|
|
|
Parking standards apply as identifed in DR comments.
|
Routing - Design Review | 4/14/2017 | | 4/14/2017 | | FAIL |
Andrea Tuning
|
|
|
Construct the standard parking spaces to be a minimum of 20-feet deep or a minimum of 18-feet deep with the appropriate 2-foot overhang required by Boise City Code.
Construct all second and third story windows to be recessed a minimum of 2-inches from the façade to provide additional depth and character.
Limit the amount of stucco on the street facing facade to be no greater than 50 percent.
|
Intake Approval | | | 4/14/2017 | | PASS |
Carl D Madsen
|
|
|
|
Intake Approval | | | 4/10/2017 | | FAIL |
|
|
|
1st Prescreen 4/10/17 Carl Madsen ###-####
Please provide the following items.
1. Soils and Geotechnical report
2. Verification of legal lot and parcel form completed and signed by planning staff member.
3. Form 310 special inspection start-up form completed by the structural engineer.
4. Drainage O & M plan
5. Permanent O&M agreement form
6. Remove all stamps indicating not for construction
7. Review all sheets and verify all sheets are stamped.
|
Application received | | | 4/7/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 7 2017 12:37PM
|
First Notice | | 9/2/2019 | | | |
|
|
|
|
First Notice | 8/22/2019 | 8/22/2019 | | | |
Brandon Shaw
|
|
|
|